GALVESTON FM 517 (0978-01-045)
Items: 17
County: GALVESTON
Length: 0.0000 MILES (9.8577 MILES)
Highway: FM 517
District: HOUSTON
Control Number: 0978-01-045
DBE Goal: 0.0%
Project: STP 2025(960)HES
Guaranty: $67,000.00
Time: 180 WORKING DAYS
Engineer's Estimate: $3,256,548.60
Date: 07/02/2026 1:00 PM CDT (16 days ago)
Contract Number: 7263215
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00193582
Contract Type: FEDERAL
Project Description: INSTALL SAFETY LIGHTING
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
EUGENE AMPOMAH
KIALEE GBOSI
GALVESTON FM 517 (0978-01-045)
Project Name: N/A
Project: STP 2025(960)HES
Engineer's Estimate: $1,205,072.40
Length: 0.0000 MILES (2.7423 MILES)
Project Class: SAFETY IMPROVEMENT PROJECTS
Limits From: FM 646
Limits To: SH 3
Project Description: INSTALL SAFETY LIGHTING
GALVESTON SH 3 (0051-03-122)
Project Name: HOU_SH 3, FM 1765-SH 146
Project: STP 2025(960)HES
Engineer's Estimate: $723,873.60
Length: N/A (2.6798 MILES)
Project Class: SAFETY IMPROVEMENT PROJECTS
Limits From: FM 1765
Limits To: SH 146
Project Description: INSTALL SAFETY LIGHTING
GALVESTON FM 517 (0978-02-085)
Project Name: FM 517, SH 3 TO SH 146
Project: STP 2025(960)HES
Engineer's Estimate: $1,327,602.60
Length: N/A (4.4356 MILES)
Project Class: SAFETY IMPROVEMENT PROJECTS
Limits From: SH 3
Limits To: SH 146
Project Description: INSTALL SAFETY LIGHTING
Bidders (10)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,256,548.60 | |||
| $2,165,895.50 |
-33.49%
-$1,090,653.10
|
|||
| $2,321,115.00 |
-28.72%
-$935,433.60
|
7.17%
$155,219.50
|
||
| $2,359,048.91 |
-27.56%
-$897,499.69
|
8.92%
$193,153.41
|
-1.63%
-$37,933.91
|
|
| $2,373,317.15 |
-27.12%
-$883,231.45
|
9.58%
$207,421.65
|
-0.60%
-$14,268.24
|
|
| $2,470,135.17 |
-24.15%
-$786,413.43
|
14.05%
$304,239.67
|
-4.08%
-$96,818.02
|
|
| $2,573,888.04 |
-20.96%
-$682,660.56
|
18.84%
$407,992.54
|
-4.20%
-$103,752.87
|
|
| $2,577,380.68 |
-20.86%
-$679,167.92
|
19%
$411,485.18
|
-0.14%
-$3,492.64
|
|
|
8
|
$2,581,271.85 |
-20.74%
-$675,276.75
|
19.18%
$415,376.35
|
-0.15%
-$3,891.17
|
| $2,723,723.00 |
-16.36%
-$532,825.60
|
25.76%
$557,827.50
|
-5.52%
-$142,451.15
|
|
| $3,254,985.61 |
-0.05%
-$1,562.99
|
50.28%
$1,089,090.11
|
-19.51%
-$531,262.61
|
E
Engineer's Estimate
$3,256,548.60
$2,165,895.50
Over/Under Est:
-33.49%
-$1,090,653.10
$2,321,115.00
Over/Under Est:
-28.72%
-$935,433.60
Amt Left:
7.17%
$155,219.50
$2,359,048.91
Over/Under Est:
-27.56%
-$897,499.69
Amt Left:
8.92%
$193,153.41
Delta:
-1.63%
-$37,933.91
$2,373,317.15
Over/Under Est:
-27.12%
-$883,231.45
Amt Left:
9.58%
$207,421.65
Delta:
-0.60%
-$14,268.24
$2,470,135.17
Over/Under Est:
-24.15%
-$786,413.43
Amt Left:
14.05%
$304,239.67
Delta:
-4.08%
-$96,818.02
$2,573,888.04
Over/Under Est:
-20.96%
-$682,660.56
Amt Left:
18.84%
$407,992.54
Delta:
-4.20%
-$103,752.87
$2,577,380.68
Over/Under Est:
-20.86%
-$679,167.92
Amt Left:
19%
$411,485.18
Delta:
-0.14%
-$3,492.64
8
$2,581,271.85
Over/Under Est:
-20.74%
-$675,276.75
Amt Left:
19.18%
$415,376.35
Delta:
-0.15%
-$3,891.17
$2,723,723.00
Over/Under Est:
-16.36%
-$532,825.60
Amt Left:
25.76%
$557,827.50
Delta:
-5.52%
-$142,451.15
$3,254,985.61
Over/Under Est:
-0.05%
-$1,562.99
Amt Left:
50.28%
$1,089,090.11
Delta:
-19.51%
-$531,262.61
Bid Items & Bid Tabulations
17
Total
0 of 17
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $10,000.00 |
| Total: | $30,000.00 |