Job Info for 0976-07-018

County: GALVESTON Highway: SH 96 Date: 05/04/2023 (1 year ago) Engineer's Estimate: $2,182,129 Control Number: 0976-07-018
Project: F 2023(751) District: HOUSTON Time: 105 WORKING DAYS Type: LANDSCAPE DEVELOPMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,182,128.50
GREEN SAGE SERVICES LLC   $2,212,100.33 1
1.37% | $29,971.83
APEX LANDSCAPE & IRRIGATION, LLC   $2,282,264.75 2
4.59% | $100,136.25
3.17% | $70,164.42
YELLOWSTONE LANDSCAPE - CENTRAL, INC.   $2,287,841.91 3
4.84% | $105,713.41
3.42% | $75,741.58
0.24% | $5,577.16
TEXAS WALL & LANDSCAPE   $2,672,996.05 4
22.49% | $490,867.55
20.84% | $460,895.72
16.83% | $385,154.14
Subcontractor Percentage Amount
SPECIALTY DRILLING, LLC 7.54% $166,792.36
R & A DIRECTIONAL BORING 4.14% $91,580.95
TRAFFIC SIGNS & LINES, LLC 0.58% $12,830.18
Total: 12.26% $271,203.49

Bid Items

Items: 37, 0 filtered
GALVESTON SH 96  |  HOUSTON  |  0976-07-018  |  05/04/2023  |  $2,182,129  |  F 2023(751)  |  LANDSCAPE DEVELOPMENT  |  105 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate GREEN SAGE SERVICES LLC APEX LANDSCAPE & IRRIGATION, LLC YELLOWSTONE LANDSCAPE - CENTRAL, INC. TEXAS WALL & LANDSCAPE
100 6008 PREPARING ROW (TREE) (0" TO 6" DIA) EA 1.000 $250.000 $550.000 $1,000.000 $165.733 $230.000
160 6005 FURNISHING AND PLACING TOPSOIL CY 1,409.000 $45.000 $42.000 $30.000 $47.732 $58.000
161 6009 EROSION CONTROL COMPOST CY 1,801.000 $30.000 $25.000 $21.000 $19.560 $46.000
161 6012 GENERAL USE COMPOST CY 936.000 $30.000 $29.000 $22.000 $21.385 $46.000
162 6002 BLOCK SODDING SY 7,591.000 $4.000 $4.450 $4.500 $3.902 $5.500
166 6001 FERTILIZER AC 1.570 $1,250.000 $950.000 $1,250.000 $2,090.845 $1,300.000
168 6001 VEGETATIVE WATERING MG 188.200 $45.000 $35.000 $10.000 $35.012 $128.000
170 6001 IRRIGATION SYSTEM LS 1.000 $250,000.000 $616,000.000 $345,000.000 $802,475.678 $820,000.000
180 6001 WILDFLOWER SEEDING AC 1.150 $2,500.000 $1,750.000 $2,000.000 $1,288.375 $3,600.000
192 6023 PLANT MATERIAL (15 GAL) (TREE) EA 694.000 $215.000 $135.000 $140.000 $133.934 $150.000
192 6024 PLANT MATERIAL (30 GAL) (TREE) EA 42.000 $295.000 $212.000 $300.000 $256.523 $250.000
192 6025 PLANT MATERIAL (45 GAL) (TREE) EA 114.000 $475.000 $365.000 $450.000 $493.124 $420.000
192 6028 PLANT MATERIAL (1 GAL) (SHRUB) EA 20,166.000 $12.000 $8.550 $10.000 $7.815 $7.250
192 6030 PLANT MATERIAL (3 GAL) (SHRUB) EA 4,720.000 $22.000 $20.600 $30.000 $22.085 $21.500
192 6031 PLANT MATERIAL (5 GAL) (SHRUB) EA 3,532.000 $45.000 $22.500 $30.000 $35.428 $31.000
192 6059 PALM MATERIAL (TYPE I) EA 13.000 $500.000 $1,290.000 $250.000 $821.057 $1,125.000
192 6064 PLANT BED PREP (TYPE II) SY 16,745.000 $4.000 $0.500 $2.000 $0.168 $1.150
192 6065 PLANT BED PREP (TYPE III) SY 16,745.000 $4.000 $0.350 $2.000 $0.297 $3.000
192 6068 LANDSCAPE EDGE (TYPE II) LF 21,038.000 $12.000 $21.000 $25.000 $17.887 $25.500
193 6002 PLANT MAINTENANCE CYC 5.000 $12,500.000 $12,200.000 $20,000.000 $1,761.409 $9,700.000
193 6007 IRRIGATION SYSTEM OPER AND MAINT MO 12.000 $1,500.000 $1,150.000 $4,500.000 $760.608 $600.000
500 6001 MOBILIZATION LS 1.000 $207,500.000 $125,000.000 $210,000.000 $132,264.480 $36,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 7.000 $5,000.000 $3,800.000 $5,500.000 $1,715.658 $5,700.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,600.000 $6.000 $2.500 $2.000 $3.283 $4.550
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,600.000 $1.000 $1.200 $1.000 $0.374 $1.520
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 800.000 $4.500 $12.000 $2.000 $5.428 $7.350
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 800.000 $1.000 $4.000 $1.000 $0.336 $3.050
618 6034 CONDT (PVC) (SCH 40) (4") (BORE) LF 36.000 $45.000 $65.000 $45.000 $49.611 $32.000
1006 6001 LANDSCAPE SOIL AMENDMENT (TYPE I) SY 33,202.000 $0.800 $0.290 $0.350 $0.147 $0.570
1006 6002 LANDSCAPE SOIL AMENDMENT (TYPE II) SY 33,202.000 $0.700 $0.300 $0.400 $0.134 $0.480
1006 6003 LANDSCAPE SOIL AMENDMENT (TYPE III) SY 857.000 $3.000 $0.400 $2.500 $0.934 $6.100
1006 6004 LANDSCAPE SOIL AMENDMENT (TYPE IV) SY 2,571.000 $1.000 $0.350 $1.250 $0.277 $4.900
1006 6005 LANDSCAPE SOIL AMENDMENT (TYPE V) SY 29,480.000 $3.000 $0.550 $0.500 $2.159 $2.100
1022 6002 LANDSCAPE TREATMENT(TY 2) EA 1.000 $650.000 $1,500.000 $5,000.000 $680.544 $500.000
1022 6003 LANDSCAPE TREATMENT(TY 3) EA 1.000 $75,000.000 $115,000.000 $100,000.000 $70,456.365 $120,000.000
6185 6002 TMA (STATIONARY) DAY 10.000 $1,000.000 $820.000 $350.000 $856.685 $500.000
6185 6005 TMA (MOBILE OPERATION) DAY 60.000 $1,000.000 $750.000 $400.000 $856.685 $700.000
Totals: $2,182,128.50 $2,212,100.33 $2,282,264.75 $2,287,842.04 $2,672,996.05