Job Info for 0976-03-116

County: GALVESTON Highway: FM 518 Date: 06/28/2023 (1 year ago) Engineer's Estimate: $2,061,871 Control Number: 0976-03-116
Project: C 976-3-116 District: HOUSTON Time: 105 WORKING DAYS Type: LANDSCAPE DEVELOPMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,061,870.85
YELLOWSTONE LANDSCAPE - CENTRAL, INC.   $3,312,178.41 1
60.64% | $1,250,307.56
TEXAS WALL & LANDSCAPE   $4,935,162.50 2
139.35% | $2,873,291.65
49% | $1,622,984.09
Subcontractor Percentage Amount
D. L. MEACHAM CONSTRUCTION CO. 23.83% $789,292.18
HARDMAN SIGNS, LP 9.33% $309,026.27
PFEIFFER & SON LTD. 1.94% $64,256.27
ALL ACCESS TRAFFIX LIMITED LIABILITY COMPANY 1.49% $49,351.46
BILL HOUSTON CONCRETE CONSTRUCTION, INC. 0.94% $31,134.48
R & A DIRECTIONAL BORING 0.71% $23,516.47
FRANK FIFER ENTERPRISES INC. 0.23% $7,618.01
ZAMCO DIRECTIONAL DRILLING LLC 0.17% $5,630.70
Total: 38.64% $1,279,825.84

Bid Items

Items: 53, 0 filtered
GALVESTON FM 518  |  HOUSTON  |  0976-03-116  |  06/28/2023  |  $2,061,871  |  C 976-3-116  |  LANDSCAPE DEVELOPMENT  |  105 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate YELLOWSTONE LANDSCAPE - CENTRAL, INC. TEXAS WALL & LANDSCAPE
100 6013 PREP ROW (TREE) (2" TO 12" DIA) EA 73.000 $250.000 $99.426 $1,200.000
160 6005 FURNISHING AND PLACING TOPSOIL CY 296.000 $45.000 $49.041 $75.000
161 6009 EROSION CONTROL COMPOST CY 2,638.000 $21.000 $19.565 $50.000
161 6012 GENERAL USE COMPOST CY 554.000 $25.000 $22.709 $40.000
162 6002 BLOCK SODDING SY 255.000 $4.500 $4.111 $7.000
166 6001 FERTILIZER AC 13.052 $1,450.000 $1,853.628 $5,500.000
168 6001 VEGETATIVE WATERING MG 84.240 $85.000 $34.464 $200.000
170 6002 IRRIGATION SYSTEM (TY I) LS 1.000 $15,000.000 $24,004.839 $230,000.000
170 6003 IRRIGATION SYSTEM (TY II) LS 1.000 $85,000.000 $119,648.387 $125,000.000
170 6004 IRRIGATION SYSTEM (TY III) LS 1.000 $35,000.000 $19,258.871 $190,000.000
180 6001 WILDFLOWER SEEDING AC 13.000 $1,700.000 $806.452 $4,500.000
192 6023 PLANT MATERIAL (15 GAL) (TREE) EA 81.000 $130.000 $139.387 $200.000
192 6024 PLANT MATERIAL (30 GAL) (TREE) EA 674.000 $250.000 $277.592 $400.000
192 6026 PLANT MATERIAL (65 GAL) (TREE) EA 10.000 $800.000 $645.161 $950.000
192 6028 PLANT MATERIAL (1 GAL) (SHRUB) EA 8,705.000 $12.500 $7.967 $15.000
192 6030 PLANT MATERIAL (3 GAL) (SHRUB) EA 1,124.000 $25.000 $22.959 $25.000
192 6031 PLANT MATERIAL (5 GAL) (SHRUB) EA 368.000 $32.500 $17.532 $55.000
192 6050 PLANT MATERIAL (MIN 6' TRNK HT) (PALM) EA 30.000 $600.000 $1,505.376 $1,290.000
192 6064 PLANT BED PREP (TYPE II) SY 104.000 $2.750 $0.388 $55.000
192 6065 PLANT BED PREP (TYPE III) SY 8,600.000 $0.500 $0.338 $8.000
192 6066 PLANT BED PREP (TYPE IV) SY 1,522.000 $3.000 $0.530 $8.000
192 6067 LANDSCAPE EDGE (TYPE I) LF 500.000 $7.850 $8.387 $25.000
193 6001 PLANT MAINTENANCE MO 6.000 $12,500.000 $6,586.022 $10,000.000
193 6002 PLANT MAINTENANCE CYC 18.000 $2,500.000 $26,702.509 $7,800.000
193 6007 IRRIGATION SYSTEM OPER AND MAINT MO 25.000 $1,500.000 $18,064.516 $2,000.000
432 6003 RIPRAP (CONC)(6 IN) CY 73.950 $660.000 $974.318 $1,350.000
432 6006 RIPRAP (CONC)(CL B) CY 16.000 $660.000 $3,773.438 $1,500.000
500 6001 MOBILIZATION LS 1.000 $187,000.000 $77,298.371 $480,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 7.000 $5,000.000 $1,831.797 $4,500.000
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 2,802.000 $6.000 $2.590 $10.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 2,802.000 $1.000 $0.242 $5.000
528 6004 LANDSCAPE PAVERS SY 333.000 $275.000 $450.313 $300.000
528 6006 REMOVE AND RELAY PAVERS SY 4.000 $285.000 $769.688 $1,500.000
528 6011 LANDSCAPE PAVERS (TYPE I) SY 554.250 $225.000 $432.209 $300.000
628 6144 ELC SRV TY D 120/240 060(NS)SS(E)PS(U) EA 1.000 $8,000.000 $37,500.000 $250,000.000
1002 6002 LANDSCAPE AMENITY (TY 1) EA 1.000 $12,000.000 $51,680.745 $150,000.000
1002 6003 LANDSCAPE AMENITY (TY 2) EA 1.000 $5,000.000 $12,500.000 $200,000.000
1002 6004 LANDSCAPE AMENITY (TY 3) EA 6.000 $6,000.000 $10,363.957 $65,000.000
1002 6005 LANDSCAPE AMENITY (TY 4) EA 1.000 $250,000.000 $97,500.000 $98,000.000
1002 6006 LANDSCAPE AMENITY (TY 5) EA 1.000 $150,000.000 $413,968.911 $110,200.000
1005 6001 LOOSE AGGR FOR GROUNDCOVER (TYPE I) CY 4.000 $185.000 $141.129 $450.000
1006 6001 LANDSCAPE SOIL AMENDMENT (TYPE I) SY 23,906.000 $0.150 $0.142 $1.000
1006 6002 LANDSCAPE SOIL AMENDMENT (TYPE II) SY 23,906.000 $0.150 $0.128 $1.000
1006 6003 LANDSCAPE SOIL AMENDMENT (TYPE III) SY 765.000 $1.500 $0.907 $3.000
1006 6004 LANDSCAPE SOIL AMENDMENT (TYPE IV) SY 5,709.000 $0.500 $0.261 $2.000
1006 6005 LANDSCAPE SOIL AMENDMENT (TYPE V) SY 10,962.000 $2.000 $2.133 $5.000
1022 6003 LANDSCAPE TREATMENT(TY 3) EA 1.000 $17,500.000 $48,387.097 $90,000.000
1022 6005 LANDSCAPE TREATMENT (TY 5) EA 1.000 $17,500.000 $80,645.161 $65,000.000
1022 6008 LANDSCAPE TREATMENT (TY 8) EA 1.000 $26,250.000 $9,677.419 $150,000.000
1022 6009 LANDSCAPE TREATMENT (TY 9) EA 7.000 $7,000.000 $1,764.660 $55,000.000
1022 6010 LANDSCAPE TREATMENT (TY 10) EA 1.000 $8,750.000 $56,451.613 $79,000.000
6185 6002 TMA (STATIONARY) DAY 80.000 $750.000 $967.742 $500.000
6185 6005 TMA (MOBILE OPERATION) DAY 80.000 $750.000 $967.742 $500.000
Totals: $2,061,870.85 $3,312,178.62 $4,935,162.50