County: GALVESTON Highway: VA Date: 05/08/2019 (5 years ago) Engineer's Estimate: $3,945,318 Control Number: 0912-73-216
Project: STP 2019(949) District: HOUSTON Time: 240 WORKING DAYS Type: UPGRADE MBGF

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,945,318.37
TALBRAN ENTERPRISES LLC   $3,789,500.00 1
-3.95% | -$155,818.37
DBI SERVICES, LLC   $3,999,000.00 2
1.36% | $53,681.63
5.53% | $209,500.00
ISI CONTRACTING, INC.   $4,409,725.00 3
11.77% | $464,406.63
16.37% | $620,225.00
10.27% | $410,725.00
3LW CIVIL LLC   $4,411,082.55 4
11.81% | $465,764.18
16.4% | $621,582.55
0.03% | $1,357.55
FNH CONSTRUCTION, LLC   $5,102,375.00 5
29.33% | $1,157,056.63
34.65% | $1,312,875.00
15.67% | $691,292.45
VANN/ELLI, INC.   $5,924,725.00 6
50.17% | $1,979,406.63
56.35% | $2,135,225.00
16.12% | $822,350.00

Bid Items

Items: 17, 0 filtered
GALVESTON VA  |  HOUSTON  |  0912-73-216  |  05/08/2019  |  $3,945,318  |  STP 2019(949)  |  UPGRADE MBGF  |  240 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate TALBRAN ENTERPRISES LLC DBI SERVICES, LLC ISI CONTRACTING, INC. 3LW CIVIL LLC FNH CONSTRUCTION, LLC VANN/ELLI, INC.
104 6010 REMOVING CONC (RIPRAP) CY 2,400.000 $36.000 $10.000 $23.000 $100.000 $152.550 $100.000 $150.000
132 6005 EMBANKMENT (FINAL)(ORD COMP)(TY C) CY 125.000 $25.000 $100.000 $70.000 $100.000 $30.000 $50.000 $40.000
134 6004 BACKFILL (TY A OR B) STA 565.000 $171.000 $125.000 $360.000 $180.000 $218.800 $450.000 $390.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 2,375.000 $381.000 $400.000 $350.000 $520.000 $450.000 $500.000 $648.000
500 6001 MOBILIZATION LS 1.000 $332,102.120 $340,000.000 $288,000.000 $195,000.000 $150,000.000 $550,000.000 $350,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 16.000 $3,500.000 $4,000.000 $5,675.000 $2,900.000 $17,000.000 $8,500.000 $9,800.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 50,000.000 $23.000 $17.190 $18.750 $21.000 $21.000 $21.000 $26.750
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 105.000 $1,680.000 $1,600.000 $1,770.000 $2,100.000 $1,810.750 $1,550.000 $3,300.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 170.000 $170.000 $1,200.000 $1,260.000 $1,300.000 $1,198.450 $1,400.000 $1,510.000
540 6020 MTL W - BEAM GD FEN (LOW FILL CULVERT) LF 2,875.000 $61.670 $65.000 $56.000 $70.000 $70.000 $75.000 $65.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 50,000.000 $5.770 $2.000 $4.700 $2.000 $1.500 $3.000 $4.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 170.000 $184.000 $200.000 $250.000 $170.000 $238.970 $500.000 $300.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 205.000 $2,362.000 $3,000.000 $2,700.000 $2,900.000 $2,600.000 $2,500.000 $3,500.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 205.000 $210.000 $200.000 $250.000 $475.000 $301.680 $500.000 $300.000
658 6028 INSTL DEL ASSM (D-SY)SZ (BRF)GF1 EA 800.000 $8.000 $30.000 $10.000 $10.000 $28.130 $50.000 $25.000
658 6068 INSTL DEL ASSM (D-DY)SZ 1(BRF)GF2 EA 800.000 $15.000 $30.000 $16.000 $12.000 $23.440 $50.000 $55.000
6185 6002 TMA (STATIONARY) DAY 240.000 $284.000 $300.000 $500.000 $200.000 $125.000 $550.000 $300.000
Totals: $3,945,318.37 $3,789,500.00 $3,999,000.00 $4,409,725.00 $4,411,082.55 $5,102,375.00 $5,924,725.00