Job Info for 0912-73-212

County: GALVESTON Highway: CS Date: 07/02/2021 (3 years ago) Engineer's Estimate: $429,837 Control Number: 0912-73-212
Project: BR 1802(833) District: HOUSTON Time: 112 WORKING DAYS Type: REPLACE BRIDGE AND APPROACHES

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $429,836.83
TREVWAY, INC.   $474,034.06 1
10.28% | $44,197.23
ARANDA BROTHERS CONSTRUCTION CO., INC.   $480,315.50 2
11.74% | $50,478.67
1.33% | $6,281.44
JOHN REED AND COMPANY, LLC   $538,299.37 3
25.23% | $108,462.54
13.56% | $64,265.31
12.07% | $57,983.87
ISI CONTRACTING, INC.   $583,636.35 4
35.78% | $153,799.52
23.12% | $109,602.29
8.42% | $45,336.98
EARTH BUILDERS, L.P.   $597,995.00 5
39.12% | $168,158.17
26.15% | $123,960.94
2.46% | $14,358.65
MILLIS DEVELOPMENT AND CONSTRUCTION, LLC   $632,670.97 6
47.19% | $202,834.14
33.47% | $158,636.91
5.80% | $34,675.97

Bid Items

Items: 50, 0 filtered
GALVESTON CS  |  HOUSTON  |  0912-73-212  |  07/02/2021  |  $429,837  |  BR 1802(833)  |  REPLACE BRIDGE AND APPROACHES  |  112 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate TREVWAY, INC. ARANDA BROTHERS CONSTRUCTION CO., INC. JOHN REED AND COMPANY, LLC ISI CONTRACTING, INC. EARTH BUILDERS, L.P. MILLIS DEVELOPMENT AND CONSTRUCTION, LLC
100 6002 PREPARING ROW STA 3.600 $2,800.000 $701.170 $3,000.000 $2,500.000 $5,000.000 $7,500.000 $5,428.200
110 6001 EXCAVATION (ROADWAY) CY 373.000 $7.500 $7.970 $12.000 $25.000 $34.000 $25.000 $23.440
110 6002 EXCAVATION (CHANNEL) CY 120.000 $10.500 $10.520 $13.500 $30.000 $50.000 $25.000 $37.060
132 6006 EMBANKMENT (FINAL)(DENS CONT)(TY C) CY 868.000 $8.500 $15.000 $15.500 $30.000 $35.000 $25.000 $22.350
162 6002 BLOCK SODDING SY 1,041.000 $3.200 $8.740 $4.500 $3.500 $6.000 $8.000 $7.090
162 6003 STRAW OR HAY MULCH SY 1,041.000 $0.190 $1.210 $0.500 $1.000 $1.100 $3.500 $1.360
164 6009 BROADCAST SEED (TEMP) (WARM) SY 521.000 $0.140 $2.760 $0.500 $0.500 $2.000 $3.500 $2.450
164 6051 DRILL SEED (TEMP)(WARM OR COOL) SY 521.000 $0.100 $5.000 $0.500 $3.000 $2.000 $3.500 $2.450
166 6001 FERTILIZER AC 0.100 $650.000 $10,000.000 $1,500.000 $2,000.000 $2,050.000 $5,000.000 $2,463.400
168 6001 VEGETATIVE WATERING MG 26.000 $17.000 $60.120 $35.000 $50.000 $13.000 $150.000 $58.320
340 6011 D-GR HMA(SQ) TY-B PG64-22 TON 298.000 $10.500 $204.000 $115.000 $120.000 $135.000 $250.000 $144.970
340 6272 TACK COAT GAL 41.000 $4.000 $12.630 $15.000 $5.000 $3.000 $20.000 $3.270
400 6005 CEM STABIL BKFL CY 27.000 $60.000 $100.000 $60.000 $60.000 $46.000 $120.000 $61.590
416 6003 DRILL SHAFT (30 IN) LF 252.000 $150.000 $179.000 $225.000 $295.000 $320.000 $260.000 $256.150
420 6013 CL C CONC (ABUT) CY 25.200 $839.000 $674.420 $975.000 $1,600.000 $1,120.000 $1,400.000 $1,209.900
422 6007 REINF CONC SLAB (SLAB BEAM) SF 1,570.000 $14.000 $18.000 $13.700 $15.000 $22.500 $24.000 $20.710
422 6015 APPROACH SLAB CY 39.000 $450.000 $450.000 $455.000 $500.000 $780.000 $650.000 $547.180
425 6001 PRESTR CONC BOX BEAM (4B20) LF 238.000 $250.000 $232.000 $245.000 $250.000 $210.000 $220.000 $263.780
425 6002 PRESTR CONC BOX BEAM (5B20) LF 119.000 $250.000 $264.000 $245.000 $250.000 $210.000 $220.000 $383.680
432 6031 RIPRAP (STONE PROTECTION)(12 IN) CY 128.000 $89.000 $146.000 $205.000 $110.000 $110.000 $170.000 $249.610
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 13.000 $450.000 $400.000 $675.000 $500.000 $750.000 $500.000 $531.920
450 6006 RAIL (TY T223) LF 152.000 $120.000 $99.630 $90.000 $140.000 $93.000 $110.000 $156.960
454 6003 ARMOR JOINT LF 44.000 $85.000 $92.290 $140.000 $58.000 $105.000 $90.000 $82.840
464 6007 RC PIPE (CL III)(30 IN) LF 47.000 $85.000 $125.000 $85.000 $100.000 $100.000 $150.000 $117.720
467 6423 SET (TY II) (30 IN) (RCP) (6: 1) (P) EA 1.000 $2,500.000 $5,000.000 $2,650.000 $2,100.000 $2,705.000 $3,000.000 $6,223.900
496 6007 REMOV STR (PIPE) LF 44.000 $17.500 $10.000 $10.000 $10.000 $21.000 $20.000 $18.530
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 1.000 $18,000.000 $25,000.000 $25,000.000 $46,000.000 $27,000.000 $20,000.000 $36,297.000
500 6001 MOBILIZATION LS 1.000 $43,000.000 $47,000.000 $45,000.000 $50,000.000 $58,000.000 $55,000.000 $80,878.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 7.000 $10,000.000 $631.000 $1,600.000 $1,400.000 $3,500.000 $1,000.000 $1,754.900
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 60.000 $30.000 $18.080 $30.000 $40.000 $35.000 $55.000 $45.240
506 6011 ROCK FILTER DAMS (REMOVE) LF 60.000 $10.000 $13.030 $5.000 $8.000 $10.000 $10.000 $10.900
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 78.000 $25.000 $28.970 $25.000 $20.000 $25.000 $40.000 $23.440
506 6024 CONSTRUCTION EXITS (REMOVE) SY 78.000 $10.000 $10.020 $5.000 $5.000 $7.500 $10.000 $6.540
506 6034 CONSTRUCTION PERIMETER FENCE LF 106.000 $2.600 $11.160 $4.000 $5.000 $1.500 $8.000 $1.910
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 557.000 $2.500 $4.070 $5.000 $5.000 $4.000 $4.500 $1.910
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 557.000 $0.700 $1.400 $2.000 $2.000 $2.500 $1.000 $0.820
530 6005 DRIVEWAYS (ACP) SY 38.000 $45.000 $126.000 $30.000 $60.000 $56.000 $65.000 $64.860
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 87.500 $20.000 $14.420 $35.000 $25.810 $27.500 $28.000 $33.250
540 6007 MTL BEAM GD FEN TRANS (TL2) EA 3.000 $1,200.000 $420.700 $1,775.000 $1,364.000 $1,450.000 $1,400.000 $1,765.800
540 6014 SHORT RADIUS LF 9.000 $30.000 $140.230 $60.000 $105.000 $112.000 $55.000 $136.250
540 6015 DRIVEWAY TERMINAL ANCHOR SECTION EA 1.000 $1,200.000 $1,262.090 $1,500.000 $1,291.000 $1,375.000 $800.000 $1,678.600
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 3.000 $2,400.000 $420.700 $3,050.000 $2,734.000 $2,905.000 $3,000.000 $3,542.500
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 2.000 $450.000 $1,071.000 $550.000 $612.000 $650.000 $650.000 $793.520
644 6076 REMOVE SM RD SN SUP&AM EA 2.000 $85.000 $100.000 $150.000 $100.000 $106.000 $150.000 $129.710
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 6.000 $22.000 $15.000 $50.000 $20.000 $21.250 $10.000 $26.160
658 6081 INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND(BI) EA 10.000 $22.000 $18.000 $65.000 $120.000 $127.000 $50.000 $155.870
666 6174 REFL PAV MRK TY II (W) 6" (SLD) LF 720.000 $0.150 $1.580 $5.000 $1.250 $1.350 $2.000 $1.640
666 6210 REFL PAV MRK TY II (Y) 6" (SLD) LF 720.000 $0.150 $1.580 $5.000 $1.250 $1.350 $2.000 $1.640
672 6009 REFL PAV MRKR TY II-A-A EA 9.000 $3.500 $12.000 $85.000 $12.000 $13.000 $15.000 $15.810
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 210.000 $45.000 $108.000 $75.000 $35.000 $100.000 $85.000 $90.470
Totals: $429,836.83 $474,034.07 $480,315.50 $538,299.38 $583,636.35 $597,995.00 $632,670.97