Show Job Controls
Bid Cobra

GALVESTON FM 1765 (0686-02-032)

Items: 16

County: GALVESTON
Length: N/A
Highway: FM 1765
District: HOUSTON
Control Number: 0686-02-032
DBE Goal: 0.0%
Project: STP 2B24(175)VRU
Guaranty: N/A
Time: 119 WORKING DAYS
Engineer's Estimate: $1,693,031.70
Date: 08/01/2024 (1 year ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$1,693,031.70
Over/Under Est: -39.51% -$668,966.13
Over/Under Est: -32.44% -$549,262.55
Amt Left: 11.69% $119,703.58
$1,150,045.66
Over/Under Est: -32.07% -$542,986.04
Amt Left: 12.3% $125,980.09
Delta: -0.55% -$6,276.51
$1,367,417.40
Over/Under Est: -19.23% -$325,614.30
Amt Left: 33.53% $343,351.83
Delta: -18.90% -$217,371.74
Over/Under Est: -8.79% -$148,834.97
Amt Left: 50.79% $520,131.16
Delta: -12.93% -$176,779.33
Over/Under Est: 3.86% $65,365.80
Amt Left: 71.71% $734,331.93
Delta: -13.87% -$214,200.77
Subcontractor Percentage Amount
LONESTAR TRAFFIC SAFETY, LLC 1.00% $10,585.99
Total: 1.00% $10,585.99

Bid Items & Bid Tabulations

16 Total 0 of 16
GALVESTON  |  FM 1765  |  HOUSTON  |  0686-02-032  |  08/01/2024  |  $1,693,031.70  |  STP 2B24(175)VRU  |  HAZARD ELIM & SAFETY  |  119 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ALLSTATE SIGNAL & CONSTRUCTION, LLC
THIRD COAST SERVICES LLC
SICE, INC.
TRAF-TEX, INC.
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SELECT MAINTENANCE, L.L.C.
PREPARING ROW
STA 200.000 $500.000 $10.000 $23.380 $156.284 $483.000 $399.720 $125.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 830.000 $205.000 $188.670 $237.900 $161.632 $235.000 $466.020 $265.000
RIPRAP (CONC) (CL B) (4")
CY 29.000 $957.000 $985.520 $1,732.190 $1,231.041 $1,845.000 $1,338.060 $2,000.000
RIPRAP (MOW STRIP)(4 IN)
CY 2.000 $680.000 $1,420.000 $1,098.560 $1,229.919 $1,775.000 $1,266.800 $2,000.000
MOBILIZATION
LS 1.000 $153,912.000 $20,000.000 $114,376.910 $113,366.923 $34,925.000 $96,744.910 $175,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $10,000.000 $2,078.630 $2,964.040 $3,248.104 $4,360.000 $969.500 $30,000.000
IN RD IL (TY SA) 30T-8 (250W EQ) LED
EA 42.000 $4,190.000 $3,830.000 $3,417.270 $3,469.401 $4,535.000 $4,012.860 $6,500.000
IN RD IL (TY SA) 50T-8 (400W EQ) LED
EA 41.000 $5,500.000 $4,498.000 $4,121.370 $4,372.265 $5,474.000 $4,773.190 $6,500.000
CONDT (PVC) (SCH 80) (2")
LF 15,263.000 $19.050 $9.460 $6.440 $12.483 $12.300 $16.400 $12.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 7,172.000 $26.400 $14.460 $16.540 $14.417 $14.000 $19.570 $14.000
CONDT (RM) (2")
LF 120.000 $46.000 $30.000 $69.270 $35.047 $29.150 $29.100 $35.000
ELEC CONDR (NO.8) BARE
LF 23,195.000 $2.750 $1.790 $1.850 $0.922 $2.100 $1.330 $1.500
ELEC CONDR (NO.8) INSULATED
LF 46,390.000 $2.150 $1.880 $1.920 $1.095 $2.200 $1.670 $1.900
GROUND BOX TY D (162922)W/APRON
EA 7.000 $1,351.000 $1,025.000 $1,411.490 $1,598.199 $1,150.000 $1,648.820 $1,200.000
ELC SRV TY A 240/480 060(SS)SS(E)GC(U)
EA 5.000 $8,150.000 $8,505.000 $7,920.410 $8,229.138 $11,592.000 $6,861.240 $12,000.000
TMA (STATIONARY)
DAY 119.000 $496.000 $185.000 $268.250 $499.971 $215.000 $160.060 $150.000
Totals: $1,693,031.700 $1,024,065.570 $1,143,769.150 $1,150,045.714 $1,367,417.400 $1,544,196.730 $1,758,397.500