Job Info for 0367-07-009

County: GALVESTON Highway: SL 108 Date: 09/07/2023 (1 year ago) Engineer's Estimate: $1,773,346 Control Number: 0367-07-009
Project: BR 2023(926) District: HOUSTON Time: 116 WORKING DAYS Type: BRIDGE REPLACEMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,773,346.00
JOHN REED AND COMPANY, LLC   $2,472,329.00 1
39.42% | $698,983.00
RAGLE CONSTRUCTION, INC.   $3,098,071.75 2
74.7% | $1,324,725.75
25.31% | $625,742.75
Subcontractor Percentage Amount
TRAFFIC SIGNS & LINES, LLC 2.36% $58,346.96
MESA ROD BUSTERS, INC. 0.34% $8,405.92
Total: 2.70% $66,752.88

Bid Items

Items: 51, 0 filtered
GALVESTON SL 108  |  HOUSTON  |  0367-07-009  |  09/07/2023  |  $1,773,346  |  BR 2023(926)  |  BRIDGE REPL  |  116 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate JOHN REED AND COMPANY, LLC RAGLE CONSTRUCTION, INC.
100 6002 PREPARING ROW STA 7.200 $3,000.000 $20,000.000 $26,000.000
104 6009 REMOVING CONC (RIPRAP) SY 355.000 $10.000 $20.000 $16.000
105 6019 REMOVING STAB BASE & ASPH PAV(14") SY 1,881.000 $5.000 $14.000 $21.000
110 6001 EXCAVATION (ROADWAY) CY 800.000 $10.000 $25.000 $52.000
132 6006 EMBANKMENT (FINAL)(DENS CONT)(TY C) CY 102.000 $15.000 $35.000 $43.000
162 6002 BLOCK SODDING SY 1,844.000 $4.000 $4.000 $13.000
162 6003 STRAW OR HAY MULCH SY 1,844.000 $0.500 $1.000 $1.000
164 6009 BROADCAST SEED (TEMP) (WARM) SY 922.000 $0.500 $0.500 $1.000
164 6051 DRILL SEED (TEMP)(WARM OR COOL) SY 922.000 $0.500 $0.500 $1.000
166 6001 FERTILIZER AC 0.380 $1,000.000 $500.000 $1,000.000
168 6001 VEGETATIVE WATERING MG 46.000 $20.000 $50.000 $67.000
276 6238 CEM TRT(PLNT MX) (CL N)(TYE)(GR 4)(12") SY 2,494.000 $30.000 $80.000 $61.000
340 6272 TACK COAT GAL 150.000 $13.000 $6.000 $15.000
400 6005 CEM STABIL BKFL CY 101.000 $120.000 $80.000 $172.000
409 6001 PRESTR CONC PIL (16 IN SQ) LF 1,584.000 $140.000 $120.000 $94.500
409 6006 PRESTR CONC SHEET PIL (12")(HPC) SF 7,358.000 $60.000 $90.000 $93.000
420 6013 CL C CONC (ABUT) CY 59.000 $1,200.000 $1,800.000 $1,050.000
422 6001 REINF CONC SLAB SF 3,780.000 $24.000 $32.000 $33.000
422 6015 APPROACH SLAB CY 64.000 $700.000 $950.000 $750.000
425 6037 PRESTR CONC GIRDER (TX40) LF 447.500 $200.000 $280.000 $217.000
432 6008 RIPRAP (CONC)(CL B)(RR8&RR9) CY 45.000 $500.000 $350.000 $860.000
432 6026 RIPRAP (STONE COMMON)(DRY)(18 IN) CY 692.000 $180.000 $140.000 $265.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 26.000 $580.000 $450.000 $1,000.000
450 6006 RAIL (TY T223) LF 240.000 $100.000 $120.000 $150.000
454 6003 ARMOR JOINT LF 81.000 $140.000 $90.000 $221.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 1.000 $30,000.000 $180,000.000 $316,000.000
500 6001 MOBILIZATION LS 1.000 $139,000.000 $240,000.000 $309,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 8.000 $8,000.000 $2,000.000 $38,750.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 156.000 $30.000 $40.000 $35.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 156.000 $10.000 $10.000 $15.000
506 6034 CONSTRUCTION PERIMETER FENCE LF 100.000 $5.000 $6.000 $15.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,501.000 $5.000 $3.000 $3.500
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,501.000 $1.000 $1.000 $1.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 250.000 $26.000 $30.250 $28.250
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $2,500.000 $1,840.000 $2,065.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 225.000 $3.000 $2.500 $3.250
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 4.000 $250.000 $225.000 $250.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $3,300.000 $3,185.000 $3,185.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 4.000 $280.000 $225.000 $390.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 4.000 $800.000 $584.500 $765.000
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 2.000 $950.000 $984.000 $915.000
644 6076 REMOVE SM RD SN SUP&AM EA 4.000 $150.000 $70.000 $85.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 6.000 $30.000 $25.000 $25.000
658 6016 INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI) EA 10.000 $30.000 $28.000 $27.000
666 6174 REFL PAV MRK TY II (W) 6" (SLD) LF 1,440.000 $1.000 $1.000 $1.000
666 6210 REFL PAV MRK TY II (Y) 6" (SLD) LF 1,440.000 $1.000 $1.000 $1.000
666 6225 PAVEMENT SEALER 6" LF 520.000 $0.500 $0.100 $0.100
672 6009 REFL PAV MRKR TY II-A-A EA 18.000 $5.000 $8.000 $8.000
678 6002 PAV SURF PREP FOR MRK (6") LF 520.000 $0.500 $0.100 $0.100
3076 6076 D-GR HMA TY-D SAC-A PG70-22 (EXEMPT) TON 548.000 $300.000 $230.000 $250.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 240.000 $75.000 $40.000 $87.000
Totals: $1,773,346.00 $2,472,329.00 $3,098,071.75