Job Info for 0051-03-119

County: GALVESTON Highway: SH 3 Date: 08/03/2022 (2 years ago) Engineer's Estimate: $1,281,785 Control Number: 0051-03-119
Project: STP 2022(919)HES District: HOUSTON Time: 357 WORKING DAYS Type: HAZARD ELIMINATION & SAFETY
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,281,785.19
MAIN LANE INDUSTRIES LTD.   $1,131,153.80 1
-11.75% | -$150,631.39
MAR-CON SERVICES, LLC   $1,828,577.98 2
42.66% | $546,792.79
61.66% | $697,424.18
Subcontractor Percentage Amount
TEXAS DRAINAGE INC. 7.48% $84,610.30
J.KRU LAND SERVICES, LLC 4.87% $55,087.19
REPUBLIC TRAFFIC SAFETY, INC. 4.06% $45,924.84
TEXAS REEXCAVATION 1.87% $21,152.58
LONESTAR TRAFFIC SAFETY, LLC 1.22% $13,800.08
Total: 19.50% $220,574.99

Bid Items

Items: 23, 0 filtered
GALVESTON SH 3  |  HOUSTON  |  0051-03-119  |  08/03/2022  |  $1,281,785  |  STP 2022(919)HES  |  HAZARD ELIM & SAFETY  |  357 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate MAIN LANE INDUSTRIES LTD. MAR-CON SERVICES, LLC
100 6002 PREPARING ROW STA 184.800 $2,000.000 $600.000 $1,953.100
162 6002 BLOCK SODDING SY 2,425.000 $4.000 $8.000 $5.900
164 6039 DRILL SEEDING (PERM) (URBAN) (CLAY) SY 27,555.600 $0.080 $0.500 $0.600
166 6001 FERTILIZER AC 5.690 $564.510 $1,000.000 $877.500
168 6001 VEGETATIVE WATERING MG 683.200 $18.720 $50.000 $11.700
400 6005 CEM STABIL BKFL CY 190.660 $44.680 $100.000 $65.500
420 6009 CL A CONC (COLLAR) EA 102.000 $646.560 $1,000.000 $1,131.700
464 6003 RC PIPE (CL III)(18 IN) LF 104.000 $78.000 $250.000 $129.200
464 6005 RC PIPE (CL III)(24 IN) LF 142.000 $77.000 $300.000 $147.200
464 6007 RC PIPE (CL III)(30 IN) LF 72.000 $85.000 $330.000 $183.600
467 6357 SET (TY II) (18 IN) (RCP) (3: 1) (P) EA 2.000 $945.130 $2,800.000 $1,425.300
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 19.000 $1,278.000 $2,900.000 $1,676.900
467 6389 SET (TY II) (24 IN) (RCP) (3: 1) (P) EA 2.000 $1,198.930 $3,000.000 $1,715.400
467 6395 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA 72.000 $1,563.000 $3,200.000 $2,198.200
467 6423 SET (TY II) (30 IN) (RCP) (6: 1) (P) EA 22.000 $2,857.000 $3,900.000 $2,973.500
480 6001 CLEAN EXIST CULVERTS EA 89.000 $1,850.000 $750.000 $394.400
500 6001 MOBILIZATION LS 1.000 $50,000.000 $110,000.000 $425,856.600
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 24.000 $6,000.000 $750.000 $887.300
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 2,425.000 $2.510 $7.000 $6.100
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 2,425.000 $0.820 $1.000 $1.200
760 6001 DITCH CLEANING AND RESHAPING (FOOT) LF 12,600.000 $1.690 $10.000 $24.500
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 1,440.000 $50.000 $5.000 $65.000
6185 6005 TMA (MOBILE OPERATION) DAY 357.000 $338.000 $10.000 $236.000
Totals: $1,281,785.19 $1,131,153.80 $1,828,577.98