PREPARING ROW
|
STA
|
864.000
|
$2,500.000
|
$983.000
|
$1,500.000
|
$1,000.000
|
$800.000
|
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
210.000
|
$8.740
|
$16.650
|
$20.000
|
$15.000
|
$16.000
|
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
15,922.000
|
$8.560
|
$9.990
|
$16.000
|
$12.000
|
$16.000
|
|
|
|
SUBGRADE WIDENING (ORD COMP)
|
STA
|
564.000
|
$502.170
|
$492.750
|
$675.000
|
$200.000
|
$300.000
|
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
11,815.000
|
$7.400
|
$11.130
|
$9.000
|
$7.000
|
$13.000
|
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
319,017.000
|
$1.060
|
$0.780
|
$1.750
|
$3.300
|
$1.600
|
|
|
|
DRILL SEEDING (PERM) (RURAL) (CLAY)
|
SY
|
319,017.000
|
$0.160
|
$0.160
|
$0.180
|
$0.180
|
$0.130
|
|
|
|
DRILL SEED (TEMP)(WARM OR COOL)
|
SY
|
319,017.000
|
$0.120
|
$0.120
|
$0.130
|
$0.130
|
$0.100
|
|
|
|
VEGETATIVE WATERING
|
MG
|
4,985.000
|
$15.000
|
$19.980
|
$20.000
|
$28.000
|
$25.000
|
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY B)
|
SY
|
319,017.000
|
$1.180
|
$0.880
|
$0.630
|
$0.640
|
$1.000
|
|
|
|
PROOF ROLLING
|
HR
|
119.000
|
$98.900
|
$79.800
|
$85.000
|
$50.000
|
$78.000
|
|
|
|
FL BS (CIP)(TY A GR 1-2 OR 5) FINAL POS
|
CY
|
27,455.000
|
$45.000
|
$48.460
|
$58.000
|
$61.500
|
$60.000
|
|
|
|
FL BS (RDWY DEL)(TYA GR 1, 2 OR 5)F POS
|
CY
|
19,943.000
|
$35.000
|
$43.790
|
$48.000
|
$48.000
|
$55.000
|
|
|
|
REWORK BS MATL (TY B)(10")(OC)
|
SY
|
61,468.000
|
$3.000
|
$2.570
|
$1.700
|
$1.500
|
$2.900
|
|
|
|
REWRK BS MATL (TY B)(10")(DENS CONT)
|
SY
|
84,436.000
|
$5.000
|
$2.570
|
$1.700
|
$1.600
|
$2.900
|
|
|
|
CEMENT
|
TON
|
1,681.000
|
$158.920
|
$160.650
|
$152.000
|
$177.000
|
$170.000
|
|
|
|
CEMENT TREAT (SUBGRADE) (8")
|
SY
|
121,141.000
|
$3.000
|
$2.050
|
$2.250
|
$1.300
|
$2.700
|
|
|
|
PRIME COAT (MC-30)
|
GAL
|
24,225.000
|
$4.120
|
$3.950
|
$4.250
|
$4.000
|
$3.000
|
|
|
|
FOG SEAL (CSS-1H)
|
GAL
|
13,916.000
|
$3.780
|
$3.080
|
$5.000
|
$3.800
|
$2.750
|
|
|
|
ASPH(AC-15P,AC-20-5TR,AC-20XP,AC10-2TR)
|
GAL
|
36,000.000
|
$2.000
|
$0.000
|
$0.000
|
$0.000
|
$0.000
|
|
|
|
AGGR (TY-B GR-5)
|
CY
|
825.000
|
$20.720
|
$0.000
|
$0.000
|
$0.000
|
$0.000
|
|
|
|
ASPH (AC-15P, AC-20-5TR OR AC-20XP)
|
GAL
|
59,616.000
|
$3.340
|
$3.830
|
$3.400
|
$3.000
|
$4.000
|
|
|
|
AGGR (TY-PB GR-4)
|
CY
|
2,006.000
|
$148.430
|
$80.490
|
$85.000
|
$170.000
|
$60.000
|
|
|
|
CEM STABIL BKFL
|
CY
|
1,866.000
|
$66.430
|
$95.000
|
$150.000
|
$164.000
|
$180.000
|
|
|
|
CUT & RESTORING PAV
|
SY
|
1,327.000
|
$116.460
|
$130.000
|
$61.000
|
$37.000
|
$88.000
|
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
255.000
|
$3.610
|
$5.000
|
$6.000
|
$6.000
|
$17.000
|
|
|
|
TEMPORARY SPL SHORING
|
SF
|
2,682.000
|
$14.970
|
$5.000
|
$17.000
|
$17.000
|
$28.000
|
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
42.000
|
$438.690
|
$460.000
|
$470.000
|
$480.000
|
$600.000
|
|
|
|
GABION MATTRESSES (GALV)
|
CY
|
55.000
|
$222.640
|
$491.350
|
$445.000
|
$410.000
|
$300.000
|
|
|
|
CONC BOX CULV (3 FT X 2 FT)
|
LF
|
264.000
|
$194.540
|
$240.000
|
$210.000
|
$210.000
|
$280.000
|
|
|
|
CONC BOX CULV (4 FT X 2 FT)
|
LF
|
334.000
|
$233.980
|
$270.000
|
$225.000
|
$230.000
|
$300.000
|
|
|
|
CONC BOX CULV (5 FT X 2 FT)
|
LF
|
1,068.000
|
$245.720
|
$380.000
|
$325.000
|
$305.000
|
$390.000
|
|
|
|
CONC BOX CULV (9 FT X 5 FT)
|
LF
|
224.000
|
$801.910
|
$840.000
|
$725.000
|
$750.000
|
$890.000
|
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
890.000
|
$73.530
|
$100.000
|
$49.000
|
$50.000
|
$85.000
|
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
57.000
|
$117.880
|
$180.000
|
$105.000
|
$105.000
|
$150.000
|
|
|
|
RC PIPE (CL IV)(24 IN)
|
LF
|
517.000
|
$108.250
|
$95.000
|
$60.000
|
$60.000
|
$98.000
|
|
|
|
RC PIPE (ARCH)(CL III)(DES 1)
|
LF
|
916.000
|
$133.320
|
$135.000
|
$135.000
|
$135.000
|
$175.000
|
|
|
|
RC PIPE (ARCH)(CL III)(DES 3)
|
LF
|
279.000
|
$154.720
|
$160.000
|
$150.000
|
$150.000
|
$200.000
|
|
|
|
RC PIPE (ARCH)(CL IV)(DES 3)
|
LF
|
478.000
|
$162.660
|
$180.000
|
$180.000
|
$180.000
|
$220.000
|
|
|
|
HEADWALL (CH - FW - 0) (DIA= 36 IN)
|
EA
|
2.000
|
$6,053.450
|
$12,000.000
|
$9,500.000
|
$9,750.000
|
$6,800.000
|
|
|
|
HEADWALL (CH - PW - 0) (DIA= 48 IN)
|
EA
|
1.000
|
$10,977.580
|
$18,000.000
|
$10,250.000
|
$10,500.000
|
$7,800.000
|
|
|
|
WINGWALL (FW - S) (HW=3 FT)
|
EA
|
2.000
|
$10,084.070
|
$4,800.000
|
$9,200.000
|
$9,455.000
|
$7,800.000
|
|
|
|
WINGWALL (PW - 1) (HW=4 FT)
|
EA
|
6.000
|
$9,769.910
|
$11,000.000
|
$11,800.000
|
$11,975.000
|
$13,000.000
|
|
|
|
WINGWALL (PW - 1) (HW=6 FT)
|
EA
|
2.000
|
$16,721.580
|
$24,000.000
|
$20,000.000
|
$19,950.000
|
$24,000.000
|
|
|
|
SET (TY I)(S=3 FT)(HW=3FT)(3:1)(C)
|
EA
|
12.000
|
$5,769.610
|
$1,400.000
|
$5,400.000
|
$5,500.000
|
$5,000.000
|
|
|
|
SET (TY I)(S= 4 FT)(HW= 3 FT)(3:1) (C)
|
EA
|
2.000
|
$5,795.930
|
$1,800.000
|
$6,000.000
|
$6,100.000
|
$5,000.000
|
|
|
|
SET (TY I)(S= 4 FT)(HW= 3 FT)(4:1) (C)
|
EA
|
8.000
|
$7,299.290
|
$2,000.000
|
$6,300.000
|
$6,400.000
|
$5,300.000
|
|
|
|
SET (TY I)(S= 5 FT)(HW= 3 FT)(3:1) (C)
|
EA
|
2.000
|
$5,628.700
|
$6,200.000
|
$7,300.000
|
$7,300.000
|
$7,100.000
|
|
|
|
SET (TY I)(S= 5 FT)(HW= 3 FT)(4:1) (C)
|
EA
|
14.000
|
$6,761.400
|
$2,100.000
|
$7,600.000
|
$7,680.000
|
$5,400.000
|
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
19.000
|
$1,344.530
|
$2,300.000
|
$1,300.000
|
$1,300.000
|
$1,600.000
|
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (C)
|
EA
|
28.000
|
$1,599.840
|
$2,800.000
|
$1,300.000
|
$1,300.000
|
$1,600.000
|
|
|
|
SET (TY II) (DES 1) (RCP) (4: 1) (P)
|
EA
|
54.000
|
$2,435.000
|
$2,600.000
|
$1,800.000
|
$1,800.000
|
$2,400.000
|
|
|
|
SET (TY II) (DES 3) (RCP) (4: 1) (C)
|
EA
|
4.000
|
$2,350.000
|
$3,200.000
|
$3,200.000
|
$2,100.000
|
$3,800.000
|
|
|
|
SET (TY II) (DES 3) (RCP) (6: 1) (C)
|
EA
|
24.000
|
$2,773.700
|
$5,000.000
|
$3,200.000
|
$3,130.000
|
$3,800.000
|
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
7.000
|
$1,823.960
|
$750.000
|
$2,100.000
|
$2,080.000
|
$1,700.000
|
|
|
|
REMOV STR (SET)
|
EA
|
22.000
|
$427.160
|
$350.000
|
$675.000
|
$680.000
|
$880.000
|
|
|
|
REMOV STR (WINGWALL)
|
EA
|
2.000
|
$1,302.760
|
$2,000.000
|
$2,000.000
|
$2,050.000
|
$1,000.000
|
|
|
|
REMOV STR (HEADWALL)
|
EA
|
8.000
|
$1,068.440
|
$750.000
|
$1,900.000
|
$1,920.000
|
$1,000.000
|
|
|
|
REMOV STR (PIPE)
|
LF
|
2,447.000
|
$15.370
|
$15.000
|
$20.000
|
$20.000
|
$11.000
|
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$2,250,000.000
|
$1,938,306.000
|
$2,360,000.000
|
$2,125,000.000
|
$2,000,000.000
|
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
33.000
|
$14,000.000
|
$2,224.120
|
$11,500.000
|
$2,000.000
|
$12,000.000
|
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
820.000
|
$30.010
|
$31.010
|
$32.000
|
$29.000
|
$26.000
|
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
820.000
|
$8.780
|
$6.510
|
$5.000
|
$9.000
|
$14.000
|
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 2)
|
SY
|
2,808.000
|
$16.470
|
$42.090
|
$44.000
|
$42.000
|
$40.000
|
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
2,808.000
|
$6.590
|
$6.380
|
$5.000
|
$10.400
|
$7.000
|
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
117,730.000
|
$2.430
|
$2.350
|
$2.500
|
$2.400
|
$3.000
|
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
117,730.000
|
$0.670
|
$0.250
|
$0.100
|
$0.500
|
$1.000
|
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
3,505.000
|
$3.950
|
$6.270
|
$7.000
|
$4.000
|
$5.800
|
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
3,505.000
|
$1.040
|
$0.750
|
$0.250
|
$1.000
|
$1.000
|
|
|
|
CONSTRUCTING DETOURS
|
SY
|
22,565.000
|
$52.410
|
$49.820
|
$30.000
|
$64.000
|
$60.000
|
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
8,095.000
|
$32.280
|
$12.000
|
$32.000
|
$31.000
|
$24.000
|
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
240.000
|
$37.700
|
$10.000
|
$32.000
|
$31.000
|
$24.000
|
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
75,980.000
|
$5.000
|
$9.000
|
$4.000
|
$7.000
|
$6.500
|
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
4,000.000
|
$9.100
|
$8.000
|
$4.000
|
$8.000
|
$6.500
|
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
8,095.000
|
$6.660
|
$12.000
|
$8.000
|
$13.000
|
$11.000
|
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
240.000
|
$9.140
|
$9.000
|
$8.000
|
$11.000
|
$11.000
|
|
|
|
TURNOUTS (ACP)
|
SY
|
233.000
|
$54.990
|
$39.420
|
$50.000
|
$28.000
|
$50.000
|
|
|
|
DRIVEWAYS (ACP)(TYPE 1)
|
SY
|
3,834.000
|
$29.090
|
$32.850
|
$35.000
|
$40.000
|
$30.000
|
|
|
|
DRIVEWAYS (ACP) (TYPE 2)
|
SY
|
9,327.000
|
$19.130
|
$39.420
|
$45.000
|
$55.000
|
$45.000
|
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 1
|
EA
|
9.000
|
$213.210
|
$187.000
|
$187.000
|
$195.000
|
$200.000
|
|
|
|
MAILBOX INSTALL-D (TWG-POST) TY 1
|
EA
|
1.000
|
$207.800
|
$226.000
|
$226.000
|
$235.000
|
$240.000
|
|
|
|
MAILBOX INSTALL-M (TWG-POST) TY 1
|
EA
|
3.000
|
$336.480
|
$394.000
|
$394.000
|
$410.000
|
$420.000
|
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
57.000
|
$536.880
|
$522.000
|
$522.000
|
$540.000
|
$550.000
|
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
24.000
|
$659.500
|
$597.000
|
$597.000
|
$620.000
|
$640.000
|
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
3.000
|
$1,299.320
|
$816.000
|
$816.000
|
$850.000
|
$880.000
|
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
15.000
|
$643.170
|
$619.000
|
$619.000
|
$645.000
|
$660.000
|
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
75.000
|
$89.880
|
$87.000
|
$87.000
|
$91.000
|
$95.000
|
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
131.000
|
$26.140
|
$7.000
|
$7.000
|
$7.000
|
$8.000
|
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
|
EA
|
54.000
|
$71.420
|
$72.000
|
$72.000
|
$75.000
|
$76.000
|
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND
|
EA
|
122.000
|
$79.080
|
$72.000
|
$72.000
|
$75.000
|
$76.000
|
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
7,731.000
|
$3.570
|
$2.900
|
$2.900
|
$2.600
|
$3.100
|
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
237,363.000
|
$0.650
|
$0.440
|
$0.440
|
$0.600
|
$0.470
|
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
1,728.000
|
$7.050
|
$6.000
|
$6.000
|
$10.400
|
$6.300
|
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
312,450.000
|
$0.660
|
$0.440
|
$0.440
|
$0.600
|
$0.470
|
|
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
3,401.000
|
$0.840
|
$0.700
|
$0.700
|
$1.150
|
$0.740
|
|
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
362.000
|
$5.920
|
$6.000
|
$6.000
|
$7.000
|
$6.300
|
|
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
6.000
|
$133.630
|
$150.000
|
$150.000
|
$156.000
|
$165.000
|
|
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
6.000
|
$152.340
|
$150.000
|
$150.000
|
$156.000
|
$165.000
|
|
|
|
REF PAV MRK TY I (W)(MED NOSE)(100MIL)
|
EA
|
1.000
|
$157.000
|
$344.000
|
$344.000
|
$468.000
|
$380.000
|
|
|
|
PAVEMENT SEALER 4"
|
LF
|
88,058.000
|
$0.120
|
$0.130
|
$0.130
|
$0.160
|
$0.140
|
|
|
|
PAVEMENT SEALER 6"
|
LF
|
172,115.000
|
$0.180
|
$0.200
|
$0.200
|
$0.200
|
$0.210
|
|
|
|
PAVEMENT SEALER 8"
|
LF
|
3,401.000
|
$0.340
|
$0.440
|
$0.440
|
$0.300
|
$0.470
|
|
|
|
PAVEMENT SEALER 24"
|
LF
|
362.000
|
$1.850
|
$3.000
|
$3.000
|
$2.600
|
$3.200
|
|
|
|
PAVEMENT SEALER (ARROW)
|
EA
|
6.000
|
$43.580
|
$65.000
|
$65.000
|
$26.000
|
$70.000
|
|
|
|
PAVEMENT SEALER (WORD)
|
EA
|
6.000
|
$46.890
|
$65.000
|
$65.000
|
$36.000
|
$70.000
|
|
|
|
PAVEMENT SEALER (MED NOSE)
|
EA
|
1.000
|
$85.950
|
$244.000
|
$244.000
|
$78.000
|
$260.000
|
|
|
|
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
|
LF
|
172,115.000
|
$0.730
|
$0.780
|
$0.780
|
$0.800
|
$0.830
|
|
|
|
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
|
LF
|
18,797.000
|
$0.450
|
$0.580
|
$0.580
|
$0.600
|
$0.630
|
|
|
|
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
|
LF
|
69,261.000
|
$0.500
|
$0.580
|
$0.580
|
$0.600
|
$0.630
|
|
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
1,194.000
|
$2.910
|
$3.330
|
$3.330
|
$5.200
|
$3.500
|
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
196,041.000
|
$0.320
|
$0.370
|
$0.370
|
$0.200
|
$0.380
|
|
|
|
FULL - WIDTH MOWING
|
CYC
|
11.000
|
$3,600.000
|
$12,000.000
|
$2,500.000
|
$4,990.000
|
$10,000.000
|
|
|
|
LITTER REMOVAL
|
CYC
|
33.000
|
$1,960.000
|
$2,000.000
|
$1,000.000
|
$2,080.000
|
$3,000.000
|
|
|
|
CLEANING / SWEEPING (OUTSIDE MAIN LANE)
|
CYC
|
33.000
|
$990.000
|
$1,050.000
|
$500.000
|
$555.000
|
$3,000.000
|
|
|
|
NO. OF WORKING DAYS
|
$/D
|
1,875.000
|
$645.000
|
$581.000
|
$551.000
|
$640.000
|
$517.000
|
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
26,411.000
|
$65.980
|
$68.460
|
$71.000
|
$68.000
|
$65.000
|
|
|
|
D-GR HMA TY-C PG70-22
|
TON
|
21,758.000
|
$81.000
|
$73.710
|
$78.500
|
$77.000
|
$85.000
|
|
|
|
SP MIXES SP-C SAC-B PG70-22
|
TON
|
36,143.000
|
$88.260
|
$79.140
|
$80.000
|
$92.000
|
$90.000
|
|
|
|
TACK COAT
|
GAL
|
19,701.000
|
$2.510
|
$3.380
|
$3.000
|
$3.000
|
$4.000
|
|
|
|
CEMENT
|
TON
|
841.000
|
$185.220
|
$160.650
|
$152.000
|
$177.000
|
$1,700.000
|
|
|
|
ASPHALT BINDER (PG 64-22)
|
TON
|
2,395.000
|
$475.000
|
$472.500
|
$525.000
|
$517.000
|
$580.000
|
|
|
|
FOAMED ASPHALT TREAT (9")(DC)
|
SY
|
198,677.000
|
$4.000
|
$2.820
|
$4.250
|
$4.500
|
$5.500
|
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$10,050.680
|
$7,500.000
|
$12,000.000
|
$35,000.000
|
$10,000.000
|
|
|
|
TMA (STATIONARY)
|
DAY
|
336.000
|
$164.080
|
$300.000
|
$150.000
|
$180.000
|
$250.000
|
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
222.000
|
$178.960
|
$500.000
|
$150.000
|
$620.000
|
$300.000
|
|
1
|
|
UNDERSEAL COURSE
|
GAL
|
29,698.000
|
$3.000
|
$3.380
|
$3.000
|
$4.000
|
$3.250
|
|
Totals: |
$26,085,475.460
|
$23,587,273.080
|
$24,958,879.760
|
$26,365,216.480
|
$27,978,330.070
|