Job Info for 0017-06-091

County: FRIO Highway: IH 35 Date: 08/03/2022 (2 years ago) Engineer's Estimate: $1,608,895 Control Number: 0017-06-091
Project: STP 2022(882)HES District: SAN ANTONIO Time: 56 WORKING DAYS Type: HAZARD ELIMINATION & SAFETY
HCS
Pay Estimate
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,608,894.71
DAN WILLIAMS COMPANY   $1,300,000.00 1
-19.2% | -$308,894.71
GRATIOT CONSTRUCTION, LTD.   $1,336,598.86 2
-16.92% | -$272,295.85
2.82% | $36,598.86
MASSANA CONSTRUCTION INC.   $1,398,543.22 3
-13.07% | -$210,351.49
7.58% | $98,543.22
4.63% | $61,944.36
SCR CIVIL CONSTRUCTION, LLC   $1,462,261.20 4
-9.11% | -$146,633.51
12.48% | $162,261.20
4.56% | $63,717.98
ROADWAY SPECIALTIES, INC.   $1,470,098.86 5
-8.63% | -$138,795.85
13.08% | $170,098.86
0.54% | $7,837.66

Bid Items

Items: 12, 0 filtered
FRIO IH 35  |  SAN ANTONIO  |  0017-06-091  |  08/03/2022  |  $1,608,895  |  STP 2022(882)HES  |  HAZARD ELIM & SAFETY  |  56 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate DAN WILLIAMS COMPANY GRATIOT CONSTRUCTION, LTD. MASSANA CONSTRUCTION INC. SCR CIVIL CONSTRUCTION, LLC ROADWAY SPECIALTIES, INC.
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 24,361.000 $1.600 $1.250 $0.410 $1.000 $5.000 $5.590
164 6021 CELL FBR MLCH SEED(PERM)(RURAL)(SANDY) SY 24,361.000 $2.500 $0.700 $0.400 $0.700 $0.600 $0.750
168 6001 VEGETATIVE WATERING MG 380.000 $17.000 $1.000 $5.360 $74.000 $190.000 $100.000
432 6066 RIPRAP (CL A) (MOW STRIP) (3 IN) CY 1,031.000 $510.000 $415.000 $547.170 $450.000 $515.000 $500.000
500 6001 MOBILIZATION LS 1.000 $144,808.610 $125,460.050 $248,357.290 $159,569.770 $106,400.000 $100,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 $4,000.000 $14,000.000 $1.000 $25,000.000 $5,700.000 $990.500
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 2,137.000 $4.000 $6.000 $6.530 $5.750 $4.400 $5.590
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 2,137.000 $2.000 $1.000 $1.140 $1.000 $1.150 $1.420
543 6002 CABLE BARRIER SYSTEM (TL-4) LF 36,295.000 $20.000 $15.000 $12.460 $14.000 $14.150 $16.290
543 6020 CABLE BARRIER TERMINAL SECTION (TL-4) EA 14.000 $4,000.000 $4,400.000 $2,377.900 $3,500.000 $2,300.000 $2,011.720
658 6110 INSTL DEL ASSM (D-SY)SZ 1(BRF)(GF2)(BI) EA 366.000 $29.000 $27.000 $1.000 $50.000 $40.000 $28.820
6185 6002 TMA (STATIONARY) DAY 53.000 $200.000 $225.000 $1.000 $295.000 $400.000 $250.000
Totals: $1,608,894.71 $1,300,000.00 $1,336,598.86 $1,398,543.22 $1,462,261.20 $1,470,098.86