Job Info for 6369-07-001

County: FREESTONE Highway: FM0080 Date: 12/17/2020 (3 years ago) Engineer's Estimate: $88,430 Control Number: 6369-07-001
Project: BPM - 636907001 District: BRYAN Time: 24 W Type: SCOUR REPAIR & PILE REPAIR

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $88,430.00
GV LANDSCAPE AND CONSTRUCTION LLC   $70,040.00 1
-20.8% | -$18,390.00
BECK-REIT & SONS, LTD.   $75,641.00 2
-14.46% | -$12,789.00
8% | $5,601.00
LELAND & BRADLEE CONSTRUCTION, INC.   $79,955.00 3
-9.58% | -$8,475.00
14.16% | $9,915.00
5.70% | $4,314.00
DBI SERVICES, LLC   $98,405.00 4
11.28% | $9,975.00
40.5% | $28,365.00
23.08% | $18,450.00
B & MS CONSTRUCTION, INC.   $98,637.40 5
11.54% | $10,207.40
40.83% | $28,597.40
0.24% | $232.40
STRAIGHT LINE SAWING & SEALING, INC.   $99,705.00 6
12.75% | $11,275.00
42.35% | $29,665.00
1.08% | $1,067.60
JC ROAD MAINTENANCE, LLC   $121,911.04 7
37.86% | $33,481.04
74.06% | $51,871.04
22.27% | $22,206.04
JAMES CONSTRUCTION GROUP, L.L.C.   $128,344.89 8
45.14% | $39,914.89
83.25% | $58,304.89
5.28% | $6,433.85
TREVWAY, INC.   $171,700.00 9
94.16% | $83,270.00
145.15% | $101,660.00
33.78% | $43,355.11
STRUCTURAL INTEGRITY GROUP LLC   $184,950.00 10
109.15% | $96,520.00
164.06% | $114,910.00
7.72% | $13,250.00
KNIFE RIVER CORPORATION - SOUTH   $273,915.00 11
209.75% | $185,485.00
291.08% | $203,875.00
48.10% | $88,965.00

Bid Items

Items: 12, 0 filtered
FREESTONE FM0080  |  BRYAN  |  6369-07-001  |  12/17/2020  |  $88,430  |  BPM - 636907001  |  SCOUR REPAIR & PILE REPAIR  |  24 W
Item code Description Unit Quantity Engineer's Estimate GV LANDSCAPE AND CONSTRUCTION LLC BECK-REIT & SONS, LTD. LELAND & BRADLEE CONSTRUCTION, INC. DBI SERVICES, LLC B & MS CONSTRUCTION, INC. STRAIGHT LINE SAWING & SEALING, INC. JC ROAD MAINTENANCE, LLC JAMES CONSTRUCTION GROUP, L.L.C. TREVWAY, INC. STRUCTURAL INTEGRITY GROUP LLC KNIFE RIVER CORPORATION - SOUTH
164 6001 BROADCAST SEED (PERM) (RURAL) (SANDY) SY 1,000.000 $1.000 $1.000 $1.000 $3.000 $1.500 $1.500 $1.000 $1.000 $1.080 $3.000 $1.500 $1.250
164 6009 BROADCAST SEED (TEMP) (WARM) SY 500.000 $0.500 $1.000 $1.000 $1.000 $1.500 $0.320 $1.000 $1.000 $1.080 $3.000 $1.500 $1.750
164 6011 BROADCAST SEED (TEMP) (COOL) SY 500.000 $0.500 $1.000 $1.000 $1.500 $1.500 $0.320 $1.000 $12.000 $1.080 $3.000 $1.500 $1.750
168 6001 VEGETATIVE WATERING MG 10.000 $295.000 $10.000 $50.000 $100.000 $50.000 $115.000 $80.000 $290.000 $108.250 $100.000 $250.000 $55.000
401 6001 FLOWABLE BACKFILL CY 20.000 $295.000 $180.000 $250.000 $250.000 $350.000 $210.000 $200.000 $280.000 $250.000 $350.000 $390.000 $650.000
420 6158 CL C CONC(PILE ENCASEMENT) LF 114.000 $495.000 $230.000 $405.000 $270.000 $375.000 $510.000 $595.000 $61.500 $750.000 $1,000.000 $1,050.000 $1,800.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 31.000 $150.000 $220.000 $333.000 $75.000 $355.000 $205.000 $225.000 $2,000.000 $400.000 $700.000 $350.000 $415.000
500 6001 MOBILIZATION LS 1.000 $10,000.000 $20,000.000 $8,888.000 $20,000.000 $25,000.000 $15,000.000 $8,000.000 $18,400.000 $11,031.370 $15,000.000 $20,000.000 $27,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 $2,500.000 $5,000.000 $1,200.000 $6,500.000 $3,000.000 $5,000.000 $4,000.000 $5,000.000 $2,409.510 $1,800.000 $9,000.000 $4,300.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 100.000 $4.000 $3.000 $2.000 $3.000 $1.000 $3.160 $4.000 $25.000 $2.710 $3.000 $2.000 $8.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 100.000 $1.000 $1.000 $1.000 $3.000 $0.500 $1.660 $2.000 $10.000 $0.810 $1.000 $2.000 $2.000
6185 6002 TMA (STATIONARY) DAY 6.000 $250.000 $150.000 $10.000 $500.000 $500.000 $248.400 $250.000 $833.340 $1,000.000 $500.000 $450.000 $450.000
Totals: $88,430.00 $70,040.00 $75,641.00 $79,955.00 $98,405.00 $98,637.40 $99,705.00 $121,911.04 $128,344.89 $171,700.00 $184,950.00 $273,915.00