Show Job Controls
Bid Cobra

FREESTONE IH 45 (0675-01-072)

Items: 39

County: FREESTONE
Length: N/A
Highway: IH 45
District: BRYAN
Control Number: 0675-01-072
DBE Goal: N/A
Project: BR 1802(006)
Guaranty: N/A
Time: 77 WORKING DAYS
Engineer's Estimate: $2,169,120.00
Date: 06/05/2018 (8 years ago)
Contract Number: N/A
Type: INSTALLATION OF CRASH WALLS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (2)
E
Engineer's Estimate
$2,169,120.00
$1,744,338.76
Over/Under Est: -19.58% -$424,781.24
$1,885,848.00
Over/Under Est: -13.06% -$283,272.00
Amt Left: 8.11% $141,509.24

Bid Items & Bid Tabulations

39 Total 0 of 39
FREESTONE  |  IH 45  |  BRYAN  |  0675-01-072  |  06/05/2018  |  $2,169,120.00  |  BR 1802(006)  |  INSTL OF CRASH WALLS  |  77 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GIBSON & ASSOCIATES, INC.
A. L. HELMCAMP, INC.
REMOVING CONC (CTB)
LF 46.000 $25.000 $121.000 $300.000
BROADCAST SEED (PERM) (URBAN) (SANDY)
SY 1,936.000 $3.000 $0.550 $1.000
BROADCAST SEED (TEMP) (WARM)
SY 968.000 $1.000 $0.550 $1.000
BROADCAST SEED (TEMP) (COOL)
SY 968.000 $1.000 $0.550 $1.000
VEGETATIVE WATERING
MG 19.200 $100.000 $110.000 $45.000
CEM STABIL BKFL
CY 5.000 $160.000 $500.000 $650.000
CL C CONC (VEH DEFL WALL)(HPC)
CY 209.400 $1,200.000 $2,173.000 $2,350.000
EPOXY WATERPROOF FINISH
SF 594.000 $9.000 $8.000 $9.000
PENETRATING CONCRETE SURFACE TREATMENT
SY 10,187.000 $40.000 $5.580 $7.000
CONC STR REPAIR(CLEAN & COAT WTH EPOXY)
SF 50.000 $200.000 $157.000 $175.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 60.000 $150.000 $210.000 $230.000
RIPRAP (MOW STRIP)(4 IN)
CY 145.000 $600.000 $550.000 $720.000
CLEANING AND SEALING EXISTING JOINTS
LF 146.000 $50.000 $44.000 $48.000
CLEANING AND SEALING EXIST JOINTS(CL7)
LF 335.000 $40.000 $44.000 $48.000
MULTI-LAYER POLYMER OVERLAY
SY 3,750.000 $57.000 $32.000 $35.000
RETROFIT RAIL (TY T221)(HPC)
LF 629.000 $600.000 $253.000 $250.000
SHOT BLASTING
SY 3,750.000 $73.000 $6.000 $7.000
REMOVE STR (CONC)
EA 2.000 $10,000.000 $6,600.000 $25,000.000
REMOV STR (CURB)
EA 629.000 $5.000 $50.000 $25.000
MOBILIZATION
LS 1.000 $100,000.000 $165,000.000 $155,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $3,000.000 $22,000.000 $43,100.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 100.000 $3.500 $5.500 $6.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 100.000 $1.000 $2.200 $3.000
MTL W-BEAM GD FEN (TIM POST)
LF 1,650.000 $25.000 $18.700 $22.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 6.000 $1,700.000 $1,732.500 $1,550.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 6.000 $1,800.000 $973.500 $1,200.000
REMOVE METAL BEAM GUARD FENCE
LF 1,650.000 $2.000 $3.030 $2.500
REMOVE TERMINAL ANCHOR SECTION
EA 6.000 $350.000 $247.500 $160.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 4.000 $350.000 $247.500 $160.000
GUARDRAIL END TREATMENT (INSTALL)
EA 10.000 $2,200.000 $2,392.500 $2,800.000
GUARDRAIL END TREATMENT (REMOVE)
EA 10.000 $250.000 $247.500 $340.000
CRASH CUSH ATTEN (INSTL)
EA 6.000 $10,000.000 $35,000.000 $35,000.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1
EA 44.000 $30.000 $22.000 $26.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 72.000 $30.000 $27.500 $26.000
CNC CRACK REPAIR (DISCRETE)(GRAVITY)
LF 130.000 $45.000 $20.000 $25.000
BRIDGE JOINT REPAIR (FULL DEPTH)
LF 302.000 $475.000 $100.000 $49.000
CARBON FIBER REINF POLYMER PROTECTION
SF 145.000 $75.000 $115.000 $127.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,000.000 $12,800.000 $6,000.000
TMA (STATIONARY)
EA 2.000 $3,000.000 $38,700.000 $15,000.000
Totals: $2,169,120.000 $1,744,338.760 $1,885,848.000