Job Info for 0612-01-046

County: FREESTONE Highway: FM 80 Date: 07/09/2024 (4 months ago) Engineer's Estimate: $3,479,854 Control Number: 0612-01-046
Project: BR 2B24(084) District: BRYAN Time: 192 WORKING DAYS Type: BRIDGE REPLACEMENT
Bidder's List
Informational:

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,479,853.55
PMCO CONSTRUCTION LLC   $2,767,000.00 1
-20.49% | -$712,853.55
SKYLINE BRIDGE LLC   $2,853,360.35 2
-18% | -$626,493.20
3.12% | $86,360.35
KNIFE RIVER CORPORATION - SOUTH   $3,026,665.90 3
-13.02% | -$453,187.65
9.38% | $259,665.90
6.07% | $173,305.55
C. E. BARKER, LTD.   $3,174,397.05 4
-8.78% | -$305,456.50
14.72% | $407,397.05
4.88% | $147,731.15
A. L. HELMCAMP, INC.   $3,409,472.55 5
-2.02% | -$70,381.00
23.22% | $642,472.55
7.41% | $235,075.50
TALBERT COMPANIES LLC   $3,430,085.17 6
-1.43% | -$49,768.38
23.96% | $663,085.17
0.60% | $20,612.62
FUQUA CONSTRUCTION CO., INC.   $4,546,105.04 7
30.64% | $1,066,251.49
64.3% | $1,779,105.04
32.54% | $1,116,019.87

Bid Items

Items: 59, 0 filtered
FREESTONE FM 80  |  BRYAN  |  0612-01-046  |  07/09/2024  |  $3,479,854  |  BR 2B24(084)  |  BRIDGE REPL  |  192 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate PMCO CONSTRUCTION LLC SKYLINE BRIDGE LLC KNIFE RIVER CORPORATION - SOUTH C. E. BARKER, LTD. A. L. HELMCAMP, INC. TALBERT COMPANIES LLC FUQUA CONSTRUCTION CO., INC.
100 6002 PREPARING ROW STA 17.200 $6,000.000 $2,900.000 $2,800.000 $5,800.000 $12,500.000 $3,000.000 $2,875.000 $26,166.487
104 6017 REMOVING CONC (DRIVEWAYS) SY 128.000 $24.000 $33.000 $30.000 $20.000 $54.780 $75.000 $22.860 $33.177
105 6137 REMOVE TRT BASE & ASPH PAV (12"-20") SY 4,574.000 $20.000 $14.500 $12.000 $9.000 $20.090 $13.000 $7.190 $15.275
110 6001 EXCAVATION (ROADWAY) CY 605.000 $50.000 $22.000 $18.000 $30.000 $16.640 $30.000 $37.230 $40.173
110 6002 EXCAVATION (CHANNEL) CY 540.000 $50.000 $24.000 $15.000 $30.000 $44.640 $30.000 $55.960 $45.278
132 6006 EMBANKMENT (FINAL)(DENS CONT)(TY C) CY 6,532.000 $40.000 $30.000 $30.000 $32.000 $45.450 $55.000 $58.730 $32.322
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 6,644.000 $2.750 $4.500 $4.000 $1.750 $6.590 $3.500 $4.700 $11.494
164 6021 CELL FBR MLCH SEED(PERM)(RURAL)(SANDY) SY 6,644.000 $1.100 $0.650 $1.000 $0.800 $0.790 $0.700 $1.970 $0.741
164 6029 CELL FBR MLCH SEED(TEMP)(WARM) SY 3,322.000 $1.100 $0.750 $1.000 $0.800 $0.790 $0.700 $2.070 $0.845
164 6031 CELL FBR MLCH SEED(TEMP)(COOL) SY 3,322.000 $1.100 $0.750 $1.000 $0.800 $0.790 $0.700 $2.270 $1.300
168 6001 VEGETATIVE WATERING MG 66.500 $50.000 $50.000 $1.000 $80.000 $62.900 $10.000 $342.480 $340.393
247 6230 FL BS (CMP IN PLACE)(TY A GR 1-2)(8") SY 6,159.000 $60.000 $26.000 $40.000 $22.000 $19.880 $28.000 $50.730 $39.000
260 6003 LIME (COMMERCIAL LIME SLURRY) TON 110.000 $460.000 $390.000 $400.000 $350.000 $393.860 $450.000 $372.070 $598.000
260 6009 LIME TRT (EXST MATL)(10") SY 6,598.000 $30.000 $9.000 $10.000 $6.500 $28.400 $10.000 $11.500 $39.000
275 6001 CEMENT TON 69.000 $300.000 $410.000 $400.000 $275.000 $401.730 $350.000 $326.660 $367.594
275 6006 CEMENT TREAT (EXIST MATL) (10") SY 6,598.000 $6.000 $9.000 $11.300 $3.000 $7.100 $7.000 $5.870 $6.500
316 6029 ASPH (RC-250) GAL 1,430.000 $20.000 $30.000 $15.000 $10.000 $10.960 $8.000 $11.480 $20.178
316 6403 AGGR (TY-B GR-5 OR TY-L GR-5) CY 43.000 $650.000 $795.000 $800.000 $475.000 $913.010 $800.000 $1,468.710 $845.000
400 6005 CEM STABIL BKFL CY 206.000 $230.000 $325.000 $350.000 $340.000 $182.600 $525.000 $317.750 $279.105
416 6004 DRILL SHAFT (36 IN) LF 760.000 $350.000 $350.000 $340.000 $425.000 $387.180 $325.000 $325.450 $409.533
420 6013 CL C CONC (ABUT) CY 79.200 $1,535.000 $1,350.000 $1,100.000 $2,150.000 $1,294.290 $2,900.000 $1,915.240 $2,037.615
422 6001 REINF CONC SLAB SF 4,680.000 $40.000 $32.000 $33.500 $40.000 $30.370 $80.000 $35.740 $39.762
422 6015 APPROACH SLAB CY 100.800 $975.000 $900.000 $900.000 $1,000.000 $847.010 $1,200.000 $1,074.100 $1,083.193
425 6035 PRESTR CONC GIRDER (TX28) LF 645.000 $250.000 $245.000 $260.000 $375.000 $320.210 $275.000 $188.380 $330.850
432 6001 RIPRAP (CONC)(4 IN) CY 81.000 $900.000 $715.000 $750.000 $785.000 $595.820 $1,100.000 $918.180 $1,252.730
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 1,163.000 $240.000 $175.000 $200.000 $148.000 $118.890 $115.000 $271.030 $279.457
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 109.000 $875.000 $685.000 $750.050 $750.000 $606.780 $1,000.000 $817.190 $951.757
450 6006 RAIL (TY T223) LF 324.000 $208.000 $150.000 $150.000 $175.000 $182.020 $275.000 $177.090 $305.175
454 6020 SEALED EXPANSION JOINT (4 IN) (SEJ - B) LF 140.000 $166.000 $120.000 $150.000 $175.000 $255.640 $280.000 $115.000 $221.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 2.000 $20,300.000 $30,000.000 $15,000.000 $60,000.000 $27,999.080 $40,000.000 $28,976.650 $48,411.160
496 6043 REMOV STR (SMALL FENCE) LF 190.000 $17.000 $13.500 $5.000 $15.000 $22.420 $30.000 $11.500 $8.775
500 6001 MOBILIZATION LS 1.000 $259,832.000 $276,000.000 $270,000.000 $300,000.000 $300,000.000 $290,000.000 $381,191.170 $573,090.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 12.000 $14,000.000 $3,500.000 $2,100.000 $5,000.000 $3,226.290 $4,000.000 $5,750.000 $16,741.060
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 109.000 $45.000 $58.000 $45.000 $48.000 $46.260 $42.000 $46.910 $59.162
506 6011 ROCK FILTER DAMS (REMOVE) LF 109.000 $14.000 $16.000 $10.000 $18.000 $18.260 $16.000 $11.940 $19.079
506 6022 CONSTRUCTION EXITS (INSTALL) (TY 3) SY 222.000 $40.000 $48.000 $10.000 $25.000 $34.090 $30.000 $49.060 $78.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 222.000 $11.000 $16.000 $1.000 $6.000 $6.090 $10.000 $7.210 $14.261
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 2,229.000 $5.000 $4.250 $3.500 $7.750 $4.570 $4.000 $5.210 $5.734
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 2,229.000 $1.750 $1.100 $1.500 $1.250 $1.220 $1.050 $1.640 $1.900
530 6014 DRIVEWAYS AND TURNOUTS (ACP) SY 183.000 $50.000 $80.000 $125.000 $80.000 $68.170 $200.000 $35.190 $126.100
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 1,575.000 $27.000 $24.000 $26.000 $33.000 $27.390 $25.000 $27.030 $41.592
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 8.000 $2,500.000 $1,750.000 $2,000.000 $3,000.000 $2,641.650 $2,500.000 $2,070.000 $3,031.648
542 6001 REMOVE METAL BEAM GUARD FENCE LF 1,700.000 $5.000 $2.150 $5.000 $5.000 $4.260 $4.000 $2.880 $7.919
542 6005 RM MTL BM GD FEN TRANS (T101) EA 8.000 $230.000 $170.000 $250.000 $300.000 $182.600 $170.000 $287.500 $291.200
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 8.000 $3,200.000 $3,150.000 $3,400.000 $3,300.000 $3,499.880 $3,200.000 $3,335.000 $4,180.971
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 8.000 $210.000 $225.000 $250.000 $350.000 $304.340 $300.000 $287.500 $378.181
552 6001 WIRE FENCE (TY A) LF 55.000 $40.000 $54.000 $50.000 $100.000 $121.740 $45.000 $24.380 $24.575
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 4.000 $650.000 $750.000 $1,250.000 $1,400.000 $821.710 $750.000 $847.440 $1,053.791
644 6076 REMOVE SM RD SN SUP&AM EA 9.000 $129.000 $128.750 $200.000 $100.000 $140.000 $130.000 $134.930 $194.149
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 4.000 $28.000 $44.250 $50.000 $25.000 $24.350 $25.000 $25.300 $33.502
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 20.000 $37.000 $30.000 $50.000 $40.000 $31.040 $30.000 $27.600 $43.883
666 6225 PAVEMENT SEALER 6" LF 5,540.000 $0.500 $1.100 $1.500 $1.250 $0.290 $1.300 $0.280 $0.702
666 6343 REF PROF PAV MRK TY I(W)6"(SLD)(100MIL) LF 3,430.000 $2.000 $2.650 $2.850 $3.000 $3.350 $3.000 $3.160 $2.646
666 6346 REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL) LF 190.000 $2.000 $5.700 $6.000 $6.000 $3.350 $6.000 $3.160 $1.497
666 6347 REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL) LF 1,920.000 $2.000 $2.700 $3.000 $3.000 $3.350 $3.000 $3.160 $1.747
672 6009 REFL PAV MRKR TY II-A-A EA 35.000 $8.000 $13.000 $12.500 $12.500 $12.170 $12.500 $11.500 $12.547
678 6002 PAV SURF PREP FOR MRK (6") LF 5,540.000 $0.350 $0.550 $0.750 $0.650 $0.070 $0.600 $0.070 $0.574
3077 6012 SP MIXES SP-C SAC-A PG64-22 TON 629.000 $210.000 $260.000 $300.000 $220.000 $301.900 $190.000 $253.900 $221.000
3084 6001 BONDING COURSE GAL 572.000 $7.000 $9.000 $9.500 $5.000 $10.350 $5.000 $18.880 $7.455
Totals: $3,479,853.55 $2,767,000.00 $2,853,360.35 $3,026,665.90 $3,174,397.07 $3,409,472.55 $3,430,085.18 $4,546,105.16