Job Info for 0271-10-012

County: FORT BEND Highway: US 90 Date: 07/09/2020 (4 years ago) Engineer's Estimate: $457,109 Control Number: 0271-10-012
Project: C 271-10-12 District: HOUSTON Time: 90 WORKING DAYS Type: LANDSCAPE & SCENIC ENHANCEMENTS
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $457,109.10
APEX LANDSCAPE & IRRIGATION, LLC   $538,631.00 1
17.83% | $81,521.90
CENTRAL NORTH CONSTRUCTION, LLC   $551,418.50 2
20.63% | $94,309.40
2.37% | $12,787.50
TEXAS WALL & LANDSCAPE   $711,313.00 3
55.61% | $254,203.90
32.06% | $172,682.00
29.00% | $159,894.50
YELLOWSTONE LANDSCAPE - CENTRAL, INC.   $815,147.99 4
78.33% | $358,038.89
51.34% | $276,516.99
14.60% | $103,834.99

Bid Items

Items: 40, 0 filtered
FORT BEND US 90  |  HOUSTON  |  0271-10-012  |  07/09/2020  |  $457,109  |  C 271-10-12  |  LANDSCAPE & SCENIC ENHANS  |  90 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate APEX LANDSCAPE & IRRIGATION, LLC CENTRAL NORTH CONSTRUCTION, LLC TEXAS WALL & LANDSCAPE YELLOWSTONE LANDSCAPE - CENTRAL, INC.
100 6006 PREP ROW (TREE)(LESS THAN 24" DIA) EA 1.000 $425.000 $500.000 $1,800.000 $1,600.000 $833.333
100 6013 PREP ROW (TREE) (2" TO 12" DIA) EA 34.000 $250.000 $250.000 $250.000 $150.000 $245.098
160 6005 FURNISHING AND PLACING TOPSOIL CY 120.000 $30.000 $30.000 $50.000 $65.000 $312.500
161 6009 EROSION CONTROL COMPOST CY 195.000 $25.000 $25.000 $40.000 $35.000 $128.205
161 6012 GENERAL USE COMPOST CY 44.000 $30.000 $27.000 $45.000 $65.000 $304.356
162 6002 BLOCK SODDING SY 490.000 $3.000 $10.000 $10.000 $6.000 $4.252
166 6001 FERTILIZER AC 0.100 $1,250.000 $1,500.000 $35,000.000 $10,000.000 $2,200.000
168 6001 VEGETATIVE WATERING MG 12.080 $45.000 $50.000 $500.000 $600.000 $75.883
170 6003 IRRIGATION SYSTEM (TY II) LS 1.000 $40,000.000 $50,000.000 $55,000.000 $25,000.000 $17,333.330
192 6002 PLANT MATERIAL (1-GAL) EA 828.000 $15.500 $10.000 $11.000 $15.000 $8.052
192 6003 PLANT MATERIAL (3-GAL) EA 897.000 $22.500 $26.000 $18.000 $25.000 $16.351
192 6012 MULCH CY 2,089.000 $20.000 $22.000 $21.000 $25.000 $15.957
192 6021 PLANT MATERIAL (5 GAL) (TREE) EA 1,475.000 $20.000 $30.000 $20.000 $75.000 $13.559
192 6024 PLANT MATERIAL (30 GAL) (TREE) EA 10.000 $295.000 $260.000 $450.000 $650.000 $166.667
192 6026 PLANT MATERIAL (65 GAL) (TREE) EA 12.000 $585.000 $500.000 $650.000 $1,100.000 $694.444
192 6030 PLANT MATERIAL (3 GAL) (SHRUB) EA 401.000 $20.000 $22.000 $18.000 $25.000 $129.884
192 6065 PLANT BED PREP (TYPE III) SY 50.000 $0.400 $9.000 $100.000 $70.000 $5.000
192 6066 PLANT BED PREP (TYPE IV) SY 250.000 $2.000 $9.000 $40.000 $35.000 $1.667
193 6001 PLANT MAINTENANCE MO 18.000 $5,000.000 $3,500.000 $1,500.000 $1,700.000 $13,687.795
193 6002 PLANT MAINTENANCE CYC 8.000 $5,000.000 $10,000.000 $3,850.000 $11,000.000 $6,373.708
420 6002 CL A CONC (MISC) CY 1.500 $750.000 $750.000 $1,800.000 $3,600.000 $2,222.222
432 6003 RIPRAP (CONC)(6 IN) CY 6.000 $64.500 $750.000 $1,800.000 $1,500.000 $1,486.111
500 6001 MOBILIZATION LS 1.000 $38,000.000 $50,000.000 $25,000.000 $42,000.000 $78,791.667
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 6.000 $5,000.000 $5,000.000 $1,800.000 $2,000.000 $2,000.000
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 65.000 $4.000 $2.000 $10.000 $100.000 $8.471
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 65.000 $1.000 $1.000 $1.500 $1.000 $0.308
1000 6006 PRUNING AND TRIMMING TREES AND SHRUBS CYC 1.000 $5,000.000 $25,000.000 $35,000.000 $45,000.000 $36,860.000
1002 6002 LANDSCAPE AMENITY (TY 1) EA 40.000 $700.000 $600.000 $450.000 $750.000 $539.583
1002 6003 LANDSCAPE AMENITY (TY 2) EA 4.000 $125.000 $500.000 $1,500.000 $700.000 $828.000
1005 6001 LOOSE AGGR FOR GROUNDCOVER (TYPE I) CY 11.000 $250.000 $200.000 $850.000 $700.000 $583.333
1005 6002 LOOSE AGGR FOR GROUNDCOVER (TYPE II) CY 11.000 $250.000 $200.000 $850.000 $500.000 $439.394
1006 6001 LANDSCAPE SOIL AMENDMENT (TYPE I) SY 7,900.000 $0.200 $1.000 $0.650 $0.500 $0.949
1006 6002 LANDSCAPE SOIL AMENDMENT (TYPE II) SY 8,150.000 $0.150 $1.000 $1.250 $0.500 $0.716
1022 6001 LANDSCAPE TREATMENT(TY 1) EA 1,530.000 $0.500 $1.000 $1.250 $2.500 $0.899
1022 6002 LANDSCAPE TREATMENT(TY 2) EA 7,510.000 $0.500 $1.000 $1.250 $2.000 $0.255
1022 6003 LANDSCAPE TREATMENT(TY 3) EA 1.000 $15,000.000 $1.000 $50,000.000 $50,000.000 $30,716.667
1022 6004 LANDSCAPE TREATMENT(TY 4) EA 1.000 $9,000.000 $1.000 $50,000.000 $30,000.000 $24,583.333
1022 6005 LANDSCAPE TREATMENT (TY 5) EA 3,670.000 $0.350 $1.000 $1.250 $0.500 $3.860
6185 6002 TMA (STATIONARY) DAY 4.000 $340.000 $350.000 $500.000 $1,500.000 $708.333
6185 6005 TMA (MOBILE OPERATION) DAY 8.000 $80.000 $1,000.000 $500.000 $1,500.000 $1,151.042
Totals: $457,109.10 $538,631.00 $551,418.50 $711,313.00 $815,148.09