FORT BEND SH 36 (0187-05-066)

Items: 41

County: FORT BEND
Length: 0.2610 MILES (0.4385 MILES)
Highway: SH 36
District: HOUSTON
Control Number: 0187-05-066
DBE Goal: 0.0%
Project: F 2026(619)
Guaranty: $9,000.00
Time: 51 WORKING DAYS
Engineer's Estimate: $425,243.67
Date: 07/01/2026 1:00 PM CDT (17 days ago) Changed
Contract Number: 7263232
Type: INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT T
Project ID: A00209198
Contract Type: FEDERAL
Project Description: ADD RIGHT TURN LANE AND LEFT TURN LANE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DANIEL DVORAK
TARIK TAHERI
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$425,243.67
Over/Under Est: 49.82% $211,859.98
Over/Under Est: 50.3% $213,904.86
Amt Left: 0.32% $2,044.88
$649,810.93
Over/Under Est: 52.81% $224,567.26
Amt Left: 1.99% $12,707.28
Delta: -1.67% -$10,662.40
$782,581.40
Over/Under Est: 84.03% $357,337.73
Amt Left: 22.83% $145,477.75
Delta: -20.43% -$132,770.47

Bid Items & Bid Tabulations

41 Total 0 of 41
FORT BEND  |  SH 36  |  HOUSTON  |  0187-05-066  |  07/01/2026 1:00 PM CDT  |  $425,243.67  |  F 2026(619)  |  INTERS IMPRVS WITH RIGHT AND/OR LEFT...  |  51 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FORDE CONSTRUCTION COMPANY, INC.
DURWOOD GREENE CONSTRUCTION CO.
MC2 CIVIL, LLC
HAYDEN PAVING, INC.
PREPARING ROW
STA 31.000 $500.000 $900.000 $1,250.000 $750.000 $500.000
SUBGR WIDEN (DC)
SY 684.000 $4.500 $35.000 $30.000 $25.000 $40.000
EMBANK (FNL)(DC)(TY C)
CY 197.000 $10.000 $70.000 $50.000 $45.000 $42.000
BACKFILL (TY A OR B)
STA 31.000 $180.000 $500.000 $250.000 $500.000 $250.000
BLOCK SODDING
SY 99.000 $5.000 $15.000 $6.000 $7.000 $4.000
ASPHALT TRT BASE (GR 2)(PG 70)
TON 451.000 $140.000 $165.000 $144.000 $155.000 $195.000
TACK COAT
GAL 148.000 $1.000 $15.000 $7.000 $4.000 $3.500
SALV, HAUL & STKPL RCL APH PV (1 1/2")
SY 16,008.000 $1.000 $1.000 $1.300 $1.000 $1.250
D-GR HMA TY-D SAC-B PG76-22
TON 1,321.000 $135.000 $150.000 $175.000 $186.000 $205.000
PLANE ASPH CONC PAV (1.5")
SY 16,008.000 $2.000 $2.500 $1.300 $1.500 $4.250
STRUCT EXCAV
CY 94.000 $9.000 $60.000 $40.000 $70.000 $83.000
CEM STABIL BKFL
CY 94.000 $75.000 $70.000 $80.000 $60.000 $105.000
CL C CONC (COLLAR)
EA 1.000 $1,500.000 $4,000.000 $1,500.000 $1,500.000 $4,400.000
RIPRAP (CONC)(CL B)(5 IN)
CY 67.000 $75.000 $800.000 $750.000 $850.000 $800.000
RC PIPE (CL III)(36 IN)
LF 12.000 $160.000 $350.000 $350.000 $300.000 $640.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 1.000 $4,300.000 $8,000.000 $5,200.000 $5,000.000 $6,000.000
REMOV STR (SET)
EA 1.000 $450.000 $700.000 $2,000.000 $500.000 $3,000.000
MOBILIZATION
LS 1.000 $41,703.970 $60,000.000 $55,000.000 $60,000.000 $60,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $1,000.000 $6,000.000 $6,000.000 $5,000.000 $3,000.000
TMA (STATIONARY)
DAY 30.000 $180.000 $250.000 $300.000 $250.000 $750.000
TMA (MOBILE OPERATION)
DAY 30.000 $150.000 $150.000 $150.000 $50.000 $750.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 120.000 $40.000 $50.000 $55.000 $45.000 $55.000
ROCK FILTER DAMS (REMOVE)
LF 120.000 $10.000 $20.000 $15.000 $20.000 $23.000
CONC CURB (DOWEL)(SLOTTED)
LF 340.000 $25.000 $20.000 $35.000 $25.000 $35.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 5,382.000 $0.100 $0.300 $1.000 $2.600 $1.000
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 1,580.000 $0.200 $0.720 $4.000 $3.000 $2.500
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 6.000 $500.000 $700.000 $1,100.000 $1,000.000 $800.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 12,420.000 $0.250 $0.410 $0.300 $0.300 $0.500
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 1,036.000 $0.500 $0.810 $0.480 $0.480 $1.000
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 102.000 $3.500 $4.560 $6.000 $6.000 $5.500
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 10.000 $60.000 $157.000 $75.000 $75.000 $185.000
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 8.000 $65.000 $157.000 $75.000 $75.000 $185.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 16,878.000 $0.250 $0.420 $0.300 $0.300 $0.500
RE PM TY II (W) 6" (SLD)
LF 6,210.000 $0.020 $0.510 $0.450 $0.450 $0.600
RE PM TY II (W) 8" (SLD)
LF 518.000 $0.500 $0.810 $1.000 $1.000 $1.000
RE PM TY II (W) 24" (SLD)
LF 68.000 $4.000 $4.560 $10.000 $10.000 $5.500
RE PM TY II (Y) 6" (SLD)
LF 8,439.000 $0.200 $0.510 $0.450 $0.450 $0.600
PREFAB PM TY C (W)(ARROW)
EA 5.000 $200.000 $255.000 $250.000 $250.000 $300.000
PREFAB PM TY C (W)(WORD)
EA 4.000 $225.000 $300.000 $250.000 $250.000 $350.000
REFL PAV MRKR TY I-C
EA 30.000 $3.000 $5.220 $6.000 $6.000 $6.000
REFL PAV MRKR TY II-A-A
EA 318.000 $4.000 $5.220 $6.000 $6.000 $6.000
Totals: $425,243.670 $637,103.650 $639,148.530 $649,810.930 $782,581.400
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (PART) $10,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $800.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $2,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
Total: $13,800.00