Job Info for 0027-08-182

County: FORT BEND Highway: UA 90 Date: 01/04/2024 (10 months ago) Engineer's Estimate: $751,913 Control Number: 0027-08-182
Project: C 27-8-182 District: HOUSTON Time: 60 WORKING DAYS Type: ADVANCED TRAFFIC MANAGEMENT SYSTEM
Bidder's List
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $751,913.45
THIRD COAST SERVICES LLC   $572,449.20 1
-23.87% | -$179,464.25
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC   $680,756.01 2
-9.46% | -$71,157.44
18.92% | $108,306.81
TRAF-TEX, INC.   $688,278.50 3
-8.46% | -$63,634.95
20.23% | $115,829.30
1.11% | $7,522.49
FLORIDA TRAFFIC CONTROL DEVICES, INC.   $745,392.56 4
-0.87% | -$6,520.89
30.21% | $172,943.36
8.30% | $57,114.06
CREACOM, INC.   $832,809.50 5
10.76% | $80,896.05
45.48% | $260,360.30
11.73% | $87,416.94

Bid Items

Items: 18, 0 filtered
FORT BEND UA 90  |  HOUSTON  |  0027-08-182  |  01/04/2024  |  $751,913  |  C 27-8-182  |  ADVANCED TRAF MGT SYSTEM  |  60 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate THIRD COAST SERVICES LLC HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC TRAF-TEX, INC. FLORIDA TRAFFIC CONTROL DEVICES, INC. CREACOM, INC.
500 6001 MOBILIZATION LS 1.000 $85,000.000 $57,000.000 $71,176.840 $36,472.000 $39,347.220 $59,200.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 $10,000.000 $1,729.000 $4,468.800 $1,389.000 $3,170.040 $7,900.000
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 120.000 $6.000 $31.800 $0.710 $9.950 $29.380 $10.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 120.000 $1.500 $8.800 $0.710 $3.630 $16.970 $6.000
528 6006 REMOVE AND RELAY PAVERS SY 15.000 $150.000 $130.000 $17.630 $1,880.400 $1,724.030 $102.000
618 6053 CONDT (PVC) (SCH 80) (3") LF 9,545.000 $20.000 $13.310 $14.210 $18.060 $18.700 $21.000
618 6054 CONDT (PVC) (SCH 80) (3") (BORE) LF 7,620.000 $22.000 $16.390 $19.330 $21.350 $29.800 $22.000
618 6074 CONDT (RM) (3") LF 365.000 $62.000 $58.720 $74.970 $121.000 $52.460 $140.000
620 6002 ELEC CONDR (NO.14) INSULATED LF 17,335.000 $1.000 $0.620 $1.090 $0.760 $1.050 $0.600
6007 6011 FIBER OPTIC CBL (SNGLE-MODE)(12 FIBER) LF 945.000 $2.390 $2.190 $9.470 $4.280 $8.520 $3.900
6007 6013 FIBER OPTIC CBL (SNGLE-MODE)(36 FIBER) LF 18,140.000 $2.880 $2.510 $2.640 $1.630 $2.100 $2.600
6007 6021 FIBER OPTIC SPLICE ENCLOSURE EA 6.000 $1,681.820 $1,625.000 $732.850 $1,065.000 $719.530 $1,784.000
6007 6023 FIBER OPTIC PATCH PANEL (12 POSITION) EA 6.000 $1,006.750 $1,444.000 $574.610 $462.000 $628.120 $1,546.000
6007 6094 FIBER OPTIC FUSION SPLICE EA 72.000 $50.000 $45.000 $54.980 $30.000 $47.010 $16.000
6027 6008 GROUND BOX (PREPARE) EA 2.000 $420.000 $273.000 $282.000 $131.400 $1,591.360 $1,254.000
6185 6002 TMA (STATIONARY) DAY 66.000 $221.900 $250.000 $84.000 $170.000 $164.830 $195.000
6186 6002 ITS GND BOX(PCAST) TY 1 (243636)W/APRN EA 30.000 $3,600.000 $3,567.000 $5,214.600 $4,586.000 $4,040.550 $6,087.000
6186 6008 ITS GND BOX(PCAST) TY 2 (366036)W/APRN EA 4.000 $6,884.970 $6,071.000 $7,723.200 $7,502.000 $6,532.890 $9,751.000
Totals: $751,913.45 $572,449.20 $680,756.01 $688,278.50 $745,392.56 $832,809.50