FISHER CR 305 (0908-23-058)

Items: 49

County: FISHER
Length: 0.0000 MILES
Highway: CR 305
District: ABILENE
Control Number: 0908-23-058
DBE Goal: 0.0%
Project: BR 2024(403)
Guaranty: $50,000.00
Time: 255 WORKING DAYS
Engineer's Estimate: $2,507,178.28
Date: 04/08/2026 (8 weeks ago) Changed
Contract Number: 4263035
Type: BRIDGE REPLACEMENT
Project ID: A00194074
Contract Type: Federal
Project Description: REPLACE BRIDGE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BRYCE TURENTINE
MICHAEL WITTIE
JOSE CABRERA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$2,507,178.28
$1,880,830.34
Over/Under Est: -24.98% -$626,347.94
Over/Under Est: -23.78% -$596,267.38
Amt Left: 1.6% $30,080.56
$1,915,919.44
Over/Under Est: -23.58% -$591,258.84
Amt Left: 1.87% $35,089.10
Delta: -0.26% -$5,008.54
Over/Under Est: -19.9% -$498,979.28
Amt Left: 6.77% $127,368.66
Delta: -4.82% -$92,279.56
Over/Under Est: -11.13% -$279,003.56
Amt Left: 18.47% $347,344.38
Delta: -10.95% -$219,975.72
Over/Under Est: -3.55% -$88,985.48
Amt Left: 28.57% $537,362.46
Delta: -8.53% -$190,018.08
$2,507,699.50
Over/Under Est: 0.02% $521.22
Amt Left: 33.33% $626,869.16
Delta: -3.70% -$89,506.70

Bid Items & Bid Tabulations

49 Total 0 of 49
FISHER  |  CR 305  |  ABILENE  |  0908-23-058  |  04/08/2026  |  $2,507,178.28  |  BR 2024(403)  |  BRIDGE REPL  |  255 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TUCAN CONTRACTING, LLC
DELGADO'S CONTRACTORS, LLC
SKYLINE BRIDGE LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
J. H. STRAIN & SONS, INC.
COPPELL CONSTRUCTION CO., INC.
ALTUS CONSTRUCTION LLC
PREPARING ROW
STA 11.600 $5,000.000 $2,750.000 $1,000.000 $1,500.000 $2,500.000 $1,500.000 $3,000.000 $10,809.108
EXCAV (ROADWAY)
CY 400.000 $17.000 $27.500 $20.000 $16.000 $15.000 $30.000 $35.000 $39.276
EXCAV (CHANNEL)
CY 232.000 $32.500 $33.000 $20.000 $16.000 $15.000 $40.000 $33.000 $17.564
EMBANK (FNL)(DC)(TY B)
CY 276.000 $30.000 $27.500 $31.000 $40.000 $30.000 $30.000 $37.000 $19.797
DRILL SEED (PERM_RURAL_SAND)
SY 2,220.000 $0.500 $1.100 $2.000 $4.600 $2.000 $5.000 $1.350 $0.305
VEGETATIVE WATERING
TGL 31.000 $55.000 $55.000 $40.100 $1.000 $1.000 $100.000 $50.000 $38.758
FL BS (CMP IN PLC)(TY A OR B GR 4)(6")
SY 2,892.000 $40.000 $27.500 $22.500 $35.000 $20.000 $33.000 $25.000 $26.153
PRIME COAT (MC-30)
GAL 228.000 $10.000 $16.500 $20.000 $42.500 $20.000 $25.000 $25.000 $10.636
ASPH (AC-20-5TR)
GAL 610.000 $10.000 $22.000 $30.000 $42.100 $20.000 $20.000 $40.000 $3.576
AGGR (TY-PB, GR-3)(SAC-B)
CY 7.000 $750.000 $1,100.000 $1,500.000 $2,970.000 $1,500.000 $1,000.000 $100.000 $51.682
AGGR (TY-PB, GR-4)(SAC-B)
CY 7.000 $500.000 $1,100.000 $1,500.000 $2,970.000 $1,500.000 $1,000.000 $200.000 $42.494
CEM STABIL BKFL
CY 187.000 $160.000 $220.000 $255.000 $272.750 $230.000 $300.000 $333.000 $245.978
DRILL SHAFT (24 IN)
LF 474.000 $260.000 $247.500 $280.000 $225.000 $240.000 $330.000 $345.000 $375.483
DRILL SHAFT (30 IN)
LF 300.000 $320.000 $341.000 $310.000 $235.000 $300.000 $370.000 $410.000 $456.416
CL C CONC (ABUT)
CY 75.400 $1,815.000 $1,430.000 $1,350.000 $1,000.000 $1,400.000 $1,300.000 $1,400.000 $1,343.588
CL C CONC (CAP)
CY 36.800 $1,900.000 $1,540.000 $1,350.000 $1,350.000 $1,600.000 $1,300.000 $1,200.000 $2,272.763
CL C CONC (COLUMN)
CY 8.100 $1,800.000 $1,485.000 $1,350.000 $1,975.000 $2,000.000 $1,150.000 $1,900.000 $2,654.415
CL C CONC (MISC)
CY 15.200 $1,900.000 $1,100.000 $1,300.000 $1,286.650 $1,200.000 $1,100.000 $900.000 $664.807
REINF CONC SLAB (BOX BEAM)
SF 4,042.000 $34.000 $25.300 $25.000 $26.000 $28.000 $31.000 $25.000 $22.457
REINF CONC SLAB (SLAB BEAM)
SF 3,380.000 $35.000 $23.100 $25.000 $26.000 $28.000 $31.000 $31.000 $26.126
APPROACH SLAB
CY 49.000 $850.000 $935.000 $1,000.000 $675.000 $1,000.000 $1,000.000 $1,000.000 $747.908
PRESTR CONC SLAB BEAM (5SB12)
LF 392.120 $300.000 $221.790 $315.000 $328.000 $300.000 $293.500 $315.000 $338.985
PRESTR CONC SLAB BEAM (5SB15)
LF 247.500 $300.000 $221.790 $315.000 $400.000 $325.000 $321.000 $352.000 $396.078
PRESTR CONC BOX BEAM (4B20)
LF 370.500 $295.950 $332.570 $335.000 $292.000 $395.000 $324.000 $350.000 $390.494
PRESTR CONC BOX BEAM (5B20)
LF 494.000 $295.950 $332.570 $335.000 $346.000 $395.000 $325.000 $345.000 $379.059
RIPRAP (STONE PROTECTION)(15 IN)
CY 257.000 $230.000 $220.000 $210.000 $165.000 $190.000 $200.000 $320.000 $169.605
RIPRAP (STONE PROTECTION)(18 IN)
CY 286.000 $280.000 $220.000 $210.000 $160.000 $185.000 $220.000 $240.000 $164.951
RAIL (TY T223)
LF 598.000 $155.000 $209.000 $120.000 $115.000 $150.000 $132.000 $215.000 $145.300
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 65.000 $215.000 $220.000 $200.000 $262.000 $225.000 $260.000 $275.000 $234.344
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $50,000.000 $8,800.000 $15,000.000 $10,400.000 $15,000.000 $26,000.000 $45,000.000 $15,013.035
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $65,000.000 $11,000.000 $25,000.000 $19,915.000 $40,000.000 $80,000.000 $35,000.000 $31,993.886
MOBILIZATION
LS 1.000 $230,000.000 $150,000.000 $125,000.000 $150,000.000 $180,000.000 $177,500.000 $200,000.000 $249,517.462
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $15,000.000 $1,100.000 $3,000.000 $2,800.000 $2,000.000 $5,000.000 $9,500.000 $16,634.497
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,500.000 $8,800.000 $8,000.000 $11,000.000 $12,000.000 $9,500.000 $13,000.000 $7,404.290
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 130.000 $55.000 $55.000 $55.000 $45.000 $1.000 $85.000 $49.000 $46.536
ROCK FILTER DAMS (REMOVE)
LF 130.000 $25.000 $16.500 $10.000 $10.000 $1.000 $2.500 $22.000 $14.093
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,661.000 $5.000 $3.300 $8.500 $4.000 $1.000 $6.500 $6.000 $5.318
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,661.000 $2.000 $1.100 $1.000 $1.500 $1.000 $1.000 $2.000 $1.329
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 360.000 $12.000 $5.500 $10.000 $8.000 $1.000 $7.000 $8.000 $10.636
BIODEG EROSN CONT LOGS (REMOVE)
LF 360.000 $2.500 $1.100 $1.000 $2.000 $1.000 $2.000 $2.000 $1.329
MTL W-BEAM GD FEN (TIM POST)
LF 287.500 $35.000 $27.500 $29.000 $31.500 $26.000 $37.000 $30.000 $29.623
MTL BEAM GD FEN TRANS (TL2)
EA 12.000 $1,500.000 $1,540.000 $1,350.000 $1,225.000 $1,300.000 $1,380.000 $1,669.000 $1,451.566
GUARDRAIL END TREATMENT (INSTALL)
EA 12.000 $3,350.000 $3,300.000 $3,250.000 $3,525.000 $3,500.000 $4,600.000 $4,400.000 $3,532.120
WIRE FENCE (TY C)
LF 1,553.000 $30.000 $16.500 $25.000 $14.000 $18.000 $33.000 $25.000 $29.916
GATE (TY 1)
EA 1.000 $2,250.000 $3,300.000 $1,500.000 $3,500.000 $2,000.000 $2,500.000 $1,500.000 $1,266.457
WIRE FENCE (WATER GAP)
LF 165.000 $55.000 $55.000 $50.000 $150.000 $45.000 $60.000 $45.000 $49.860
REMOVE SM RD SN SUP&AM
EA 2.000 $40.000 $110.000 $255.000 $100.000 $50.000 $200.000 $99.000 $132.961
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 18.000 $45.000 $38.500 $32.000 $47.750 $45.000 $60.000 $55.000 $24.930
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 36.000 $35.000 $44.000 $31.000 $47.750 $45.000 $50.000 $55.000 $34.902
Totals: $2,507,178.275 $1,880,830.335 $1,910,910.900 $1,915,919.440 $2,008,199.000 $2,228,174.720 $2,418,192.800 $2,507,699.463
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $3,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $3,000.00
Total: $6,000.00