Job Info for 0913-28-083

County: FAYETTE Highway: CR Date: 03/08/2023 (1 year ago) Engineer's Estimate: $2,563,920 Control Number: 0913-28-083
Project: BR 2021(903) District: YOAKUM Time: 300 WORKING DAYS Type: BRIDGE REPLACEMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,563,919.50
TREVWAY, INC.   $2,596,559.22 1
1.27% | $32,639.72
CROSS PLUS CONSTRUCTION, LLC   $2,618,693.80 2
2.14% | $54,774.30
0.85% | $22,134.58
ACME BRIDGE COMPANY, INC.   $2,650,858.71 3
3.39% | $86,939.21
2.09% | $54,299.49
1.23% | $32,164.91
A GREATER AUSTIN DEVELOPMENT COMPANY, LTD.   $2,915,628.55 4
13.72% | $351,709.05
12.29% | $319,069.33
9.99% | $264,769.84
HODGES AND SON CONSTRUCTION COMPANY, INC.   $3,025,067.80 5
17.99% | $461,148.30
16.5% | $428,508.58
3.75% | $109,439.25
TEXAS MATERIALS GROUP, INC.   $3,211,749.00 6
25.27% | $647,829.50
23.69% | $615,189.78
6.17% | $186,681.20
CAPITAL EXCAVATION COMPANY   $3,416,247.52 7
33.24% | $852,328.02
31.57% | $819,688.30
6.37% | $204,498.52
FUQUA CONSTRUCTION CO., INC.   $3,643,693.70 8
42.11% | $1,079,774.20
40.33% | $1,047,134.48
6.66% | $227,446.18
Subcontractor Percentage Amount
JH CONTRACT FIELD SERVICES, LLC 8.64% $224,342.72
SYLVA CONSTRUCTION, LLC 5.10% $132,424.52
LONESTAR TRAFFIC SAFETY, LLC 0.54% $14,021.42
HOUSTON SAWING & DRILLING 0.24% $6,231.74
Total: 14.52% $377,020.40

Bid Items

Items: 47, 0 filtered
FAYETTE CR  |  YOAKUM  |  0913-28-083  |  03/08/2023  |  $2,563,920  |  BR 2021(903)  |  BRIDGE REPL  |  300 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate TREVWAY, INC. CROSS PLUS CONSTRUCTION, LLC ACME BRIDGE COMPANY, INC. A GREATER AUSTIN DEVELOPMENT COMPANY, LTD. HODGES AND SON CONSTRUCTION COMPANY, INC. TEXAS MATERIALS GROUP, INC. CAPITAL EXCAVATION COMPANY FUQUA CONSTRUCTION CO., INC.
100 6002 PREPARING ROW STA 14.870 $3,000.000 $1,700.000 $1,100.000 $6,620.000 $5,555.000 $7,500.000 $11,000.000 $10,000.000 $10,674.030
110 6001 EXCAVATION (ROADWAY) CY 509.000 $30.000 $10.000 $33.000 $33.600 $22.050 $30.000 $50.000 $121.700 $12.870
110 6002 EXCAVATION (CHANNEL) CY 1,505.000 $25.000 $10.000 $33.000 $32.700 $24.150 $30.000 $25.000 $53.590 $13.110
132 6005 EMBANKMENT (FINAL)(ORD COMP)(TY C) CY 904.000 $30.000 $22.000 $33.000 $34.600 $15.750 $50.000 $45.000 $180.000 $11.100
150 6002 BLADING HR 30.000 $100.000 $100.000 $83.000 $131.000 $75.000 $1.000 $90.000 $141.340 $251.055
164 6003 BROADCAST SEED (PERM) (RURAL) (CLAY) SY 3,182.000 $2.000 $2.000 $2.000 $0.690 $1.400 $2.000 $2.000 $0.650 $0.345
164 6009 BROADCAST SEED (TEMP) (WARM) SY 796.000 $2.000 $1.000 $2.000 $2.100 $2.400 $2.000 $1.750 $2.000 $0.210
164 6011 BROADCAST SEED (TEMP) (COOL) SY 796.000 $2.000 $1.000 $2.000 $2.100 $2.400 $2.000 $1.750 $2.000 $0.195
168 6001 VEGETATIVE WATERING MG 31.800 $50.000 $20.000 $11.000 $57.700 $250.000 $1.000 $40.000 $45.920 $15.615
247 6366 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) CY 815.000 $125.000 $142.000 $66.000 $116.000 $141.000 $210.000 $155.000 $180.000 $81.885
316 6029 ASPH (RC-250) GAL 714.000 $10.000 $29.000 $11.000 $16.200 $23.950 $25.000 $18.000 $50.510 $7.050
316 6202 AGGR(TY-E GR-5 SAC-B) CY 29.000 $200.000 $1,957.000 $193.000 $1,100.000 $1,630.000 $1,500.000 $1,000.000 $2,702.020 $194.640
316 6249 AGGR(TY-PE GR-4 SAC-B) CY 29.000 $200.000 $2,021.000 $193.000 $1,130.000 $1,675.000 $1,500.000 $1,000.000 $2,424.240 $153.525
316 6400 ASPH (AC-15P OR AC-10-2TR OR CRS-2P) GAL 1,214.000 $10.000 $27.000 $39.000 $14.700 $21.700 $25.000 $11.000 $50.510 $5.955
400 6005 CEM STABIL BKFL CY 156.000 $175.000 $175.000 $165.000 $213.000 $288.850 $250.000 $300.000 $352.480 $119.175
416 6002 DRILL SHAFT (24 IN) LF 726.000 $275.000 $292.000 $220.000 $192.000 $233.550 $275.000 $215.000 $319.190 $455.742
416 6003 DRILL SHAFT (30 IN) LF 228.000 $300.000 $323.560 $231.000 $288.000 $284.000 $320.000 $330.000 $373.590 $447.888
416 6004 DRILL SHAFT (36 IN) LF 390.000 $340.000 $343.340 $253.000 $406.000 $322.300 $320.000 $440.000 $384.970 $448.168
420 6013 CL C CONC (ABUT) CY 101.800 $1,250.000 $976.000 $1,870.000 $1,330.000 $1,192.000 $1,500.000 $1,900.000 $1,405.040 $1,684.710
420 6029 CL C CONC (CAP) CY 38.100 $1,400.000 $1,100.000 $1,870.000 $1,920.000 $1,410.000 $1,500.000 $3,200.000 $1,578.620 $1,861.245
420 6037 CL C CONC (COLUMN) CY 20.500 $1,500.000 $1,200.000 $1,870.000 $1,940.000 $2,240.000 $1,500.000 $3,400.000 $1,606.950 $1,717.365
422 6001 REINF CONC SLAB SF 2,730.000 $25.000 $25.000 $25.000 $33.500 $33.750 $38.000 $40.000 $50.000 $26.835
422 6005 REINF CONC SLAB (BOX BEAM) SF 1,701.000 $25.000 $22.000 $31.000 $22.800 $25.250 $30.000 $37.000 $45.000 $20.100
422 6007 REINF CONC SLAB (SLAB BEAM) SF 5,200.000 $25.000 $22.000 $39.000 $22.200 $23.700 $30.000 $36.000 $35.000 $26.685
422 6023 SHEAR KEY CY 8.600 $400.000 $200.000 $715.000 $909.000 $795.000 $800.000 $400.000 $1,034.180 $376.095
425 6001 PRESTR CONC BOX BEAM (4B20) LF 258.000 $250.000 $308.370 $253.000 $352.000 $297.000 $300.000 $300.000 $330.000 $345.510
425 6002 PRESTR CONC BOX BEAM (5B20) LF 129.000 $255.000 $352.420 $253.000 $357.000 $297.000 $300.000 $300.000 $330.000 $304.695
425 6010 PRESTR CONC SLAB BEAM (5SB12) LF 467.500 $260.000 $258.000 $253.000 $280.000 $253.000 $300.000 $240.000 $247.660 $333.060
425 6012 PRESTR CONC SLAB BEAM (5SB15) LF 517.500 $275.000 $247.000 $253.000 $274.000 $239.000 $300.000 $240.000 $250.000 $321.210
425 6035 PRESTR CONC GIRDER (TX28) LF 416.000 $190.000 $319.000 $330.000 $330.000 $293.000 $320.000 $290.000 $283.990 $232.110
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 1,405.000 $170.000 $180.000 $165.000 $132.000 $175.000 $160.000 $200.000 $135.000 $225.315
450 6006 RAIL (TY T223) LF 868.000 $150.000 $86.000 $154.000 $108.000 $150.000 $130.000 $170.000 $152.790 $171.930
454 6004 ARMOR JOINT (SEALED) LF 178.000 $160.000 $70.000 $33.000 $148.000 $165.000 $100.000 $100.000 $117.610 $168.870
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 4.000 $25,000.000 $25,000.000 $27,500.000 $10,600.000 $51,000.000 $30,000.000 $20,000.000 $20,939.000 $38,199.315
496 6043 REMOV STR (SMALL FENCE) LF 1,544.000 $3.500 $1.000 $1.000 $1.700 $3.500 $5.000 $3.000 $6.680 $5.160
500 6001 MOBILIZATION LS 1.000 $225,000.000 $260,000.000 $220,000.000 $249,000.000 $291,500.000 $250,000.000 $320,000.000 $290,000.000 $500,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 20.000 $3,500.000 $1,000.000 $2,200.000 $3,060.000 $3,530.000 $3,500.000 $1,100.000 $1,670.920 $13,258.155
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,879.000 $4.000 $5.000 $17.000 $2.900 $7.750 $5.000 $6.000 $2.750 $4.200
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,879.000 $1.000 $1.000 $1.000 $0.530 $3.300 $2.000 $2.000 $1.000 $1.035
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 50.000 $29.000 $322.000 $39.000 $31.500 $32.800 $30.000 $30.000 $31.250 $40.485
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 16.000 $2,300.000 $2,300.000 $3,300.000 $2,460.000 $2,222.000 $2,000.000 $3,000.000 $1,866.000 $3,376.785
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 16.000 $3,500.000 $3,500.000 $4,235.000 $3,860.000 $3,255.000 $3,500.000 $3,200.000 $3,101.000 $4,857.210
552 6001 WIRE FENCE (TY A) LF 1,286.000 $20.000 $13.000 $6.000 $10.600 $12.600 $15.000 $18.000 $15.210 $23.145
552 6003 WIRE FENCE (TY C) LF 1,544.000 $20.000 $13.000 $6.000 $12.700 $5.250 $15.000 $18.000 $15.210 $25.980
552 6008 WIRE FENCE (WATER GAP) LF 120.000 $75.000 $126.000 $6.000 $42.500 $130.000 $25.000 $75.000 $101.380 $104.145
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 12.000 $25.000 $15.000 $33.000 $21.600 $30.000 $30.000 $25.000 $25.000 $35.430
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 32.000 $35.000 $15.000 $33.000 $34.600 $40.000 $30.000 $35.000 $35.000 $48.345
Totals: $2,563,919.50 $2,596,559.22 $2,618,693.80 $2,650,858.71 $2,915,628.55 $3,025,067.80 $3,211,749.00 $3,416,247.54 $3,643,693.77