Job Info for 0535-07-050

County: FAYETTE Highway: IH 10 Date: 11/04/2020 (4 years ago) Engineer's Estimate: $13,026,398 Control Number: 0535-07-050
Project: NH 2021(119) District: YOAKUM Time: 225 WORKING DAYS Type: ACP OVERLAY
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $13,026,398.48
HUNTER INDUSTRIES, LTD.   $10,399,532.43 1
-20.17% | -$2,626,866.05
ANGEL BROTHERS HOLDINGS CORP.   $10,780,252.64 2
-17.24% | -$2,246,145.84
3.66% | $380,720.21
LONE STAR PAVING COMPANY   $11,106,267.74 3
-14.74% | -$1,920,130.74
6.8% | $706,735.31
3.02% | $326,015.10
JAMES CONSTRUCTION GROUP, L.L.C.   $11,872,065.27 4
-8.86% | -$1,154,333.21
14.16% | $1,472,532.84
6.90% | $765,797.53
Subcontractor Percentage Amount
CPAVE, INC. 9.55% $993,155.35
INTERSTATE BARRICADES & MARKINGS, INC. 3.49% $362,943.68
BATTERSON, LLP 0.19% $19,759.11
WEST TEXAS ROCK RESOURCES, LLC 0.18% $18,719.16
Total: 13.41% $1,394,577.30

Bid Items

Items: 50, 0 filtered
FAYETTE IH 10  |  YOAKUM  |  0535-07-050  |  11/04/2020  |  $13,026,398  |  NH 2021(119)  |  ACP OVERLAY  |  225 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate HUNTER INDUSTRIES, LTD. ANGEL BROTHERS HOLDINGS CORP. LONE STAR PAVING COMPANY JAMES CONSTRUCTION GROUP, L.L.C.
134 6002 BACKFILL (TY B) STA 1,174.340 $150.000 $90.300 $50.000 $100.000 $202.000
150 6002 BLADING HR 60.000 $100.000 $91.200 $50.000 $75.000 $95.000
316 6224 AGGR(TY-PB GR-4 SAC-B) CY 4,336.000 $100.000 $74.810 $50.000 $104.000 $105.000
316 6400 ASPH (AC-15P OR AC-10-2TR OR CRS-2P) GAL 191,635.000 $3.500 $2.990 $2.850 $2.650 $2.550
342 6002 PFC (ASPHALT) PG76-22 TON 1,859.000 $115.000 $101.490 $110.000 $108.000 $119.000
342 6006 PFC-C (AGGREGATE)(PG76 MIX) SAC-A TON 29,119.000 $110.000 $101.490 $110.000 $108.000 $119.000
351 6008 FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") SY 500.000 $50.000 $72.940 $60.000 $95.000 $90.000
351 6013 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") SY 14,323.000 $50.000 $20.540 $24.000 $27.000 $25.000
354 6041 PLANE ASPH CONC PAV (1.5") SY 206,773.000 $1.400 $1.280 $1.100 $1.650 $1.400
354 6045 PLANE ASPH CONC PAV (2") SY 312,915.000 $1.400 $1.280 $1.100 $1.600 $1.400
354 6105 PLANE ASPH CONC PAV (2"-3 1/2") SY 34,620.000 $1.500 $2.330 $1.800 $2.750 $1.800
361 6002 FULL - DEPTH REPAIR CRCP (8") SY 1,500.000 $300.000 $335.000 $315.000 $325.000 $315.000
429 6004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) SF 150.000 $250.000 $110.240 $105.000 $110.000 $105.000
438 6001 CLEANING AND SEALING EXISTING JOINTS LF 4,151.450 $25.000 $6.750 $6.750 $7.000 $6.750
454 6008 HEADER TYPE EXPANSION JOINT CF 1,631.000 $300.000 $255.000 $270.000 $280.000 $270.000
454 6009 JOINT SEALANT LF 3,536.000 $13.000 $10.500 $10.500 $11.000 $10.500
500 6001 MOBILIZATION LS 1.000 $1,270,000.000 $750,000.000 $750,000.000 $150,000.000 $710,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 15.000 $3,000.000 $3,400.000 $6,800.000 $4,700.000 $5,500.000
533 6001 RUMBLE STRIPS (SHOULDER) LF 240,708.000 $0.200 $0.100 $0.130 $0.100 $0.190
662 6001 WK ZN PAV MRK NON-REMOV (W)4"(BRK) LF 105,393.000 $0.250 $0.200 $0.200 $0.290 $0.280
662 6002 WK ZN PAV MRK NON-REMOV (W)4"(DOT) LF 2,058.000 $0.230 $2.000 $2.000 $0.890 $0.860
662 6004 WK ZN PAV MRK NON-REMOV (W)4"(SLD) LF 362,338.000 $0.200 $0.200 $0.200 $0.290 $0.280
662 6010 WK ZN PAV MRK NON-REMOV (W)8"(DOT) LF 4,512.000 $0.500 $5.000 $5.000 $0.930 $0.900
662 6012 WK ZN PAV MRK NON-REMOV (W)8"(SLD) LF 27,510.000 $0.450 $0.400 $0.400 $0.410 $0.400
662 6014 WK ZN PAV MRK NON-REMOV (W)12"(SLD) LF 860.000 $1.250 $2.500 $2.500 $1.290 $1.250
662 6034 WK ZN PAV MRK NON-REMOV (Y)4"(SLD) LF 366,277.000 $0.220 $0.200 $0.200 $0.290 $0.280
666 6005 REFL PAV MRK TY I (W)4"(DOT)(090MIL) LF 686.000 $0.880 $2.500 $2.500 $1.030 $1.000
666 6029 REFL PAV MRK TY I (W)8"(DOT)(090MIL) LF 1,504.000 $1.230 $5.000 $5.000 $1.030 $1.000
666 6035 REFL PAV MRK TY I (W)8"(SLD)(090MIL) LF 5,336.000 $0.750 $0.750 $0.750 $0.780 $0.750
666 6283 REF PROF PAV MRK TY I(W)4"(SLD)(090MIL) LF 19,694.000 $0.500 $0.500 $0.500 $0.470 $0.450
666 6287 REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL) LF 82,766.000 $0.500 $0.420 $0.420 $0.470 $0.450
666 6302 RE PM W/RET REQ TY I (W)4"(SLD)(090MIL) LF 82,766.000 $0.300 $0.300 $0.300 $0.260 $0.250
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 2,815.000 $0.500 $0.300 $0.300 $0.310 $0.300
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 3,415.000 $0.500 $0.300 $0.300 $0.310 $0.300
668 6074 PREFAB PAV MRK TY C (W) (12") (SLD) LF 678.000 $11.000 $5.000 $5.000 $6.200 $6.000
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 120.000 $15.000 $10.000 $10.000 $13.440 $13.000
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 4.000 $195.000 $200.000 $200.000 $235.000 $225.000
668 6084 PREFAB PAV MRK TY C (W) (NUMBER) EA 18.000 $200.000 $210.000 $210.000 $240.000 $230.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 4.000 $226.000 $210.000 $210.000 $260.000 $250.000
668 6090 PREFAB PAV MRK TY C (W) (SYMBOL) EA 8.000 $250.000 $225.000 $225.000 $415.000 $400.000
668 6108 PREFAB PAV MRK TY C (Y) (24") (SLD) LF 123.000 $15.000 $10.000 $10.000 $13.500 $13.000
672 6010 REFL PAV MRKR TY II-C-R EA 3,512.000 $3.400 $3.000 $3.000 $3.500 $3.250
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 82,194.000 $0.400 $0.150 $0.150 $0.350 $0.300
3076 6050 D-GR HMA TY-D SAC-B PG76-22 TON 39,625.000 $95.000 $72.090 $80.000 $87.250 $85.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 3.000 $10,000.000 $7,691.780 $5,000.000 $10,000.000 $6,500.000
6024 6009 HPPM W/RET REQ TY I(W)6"(BRK)(100MIL) LF 35,131.000 $0.500 $0.450 $0.450 $0.500 $0.480
6024 6012 HPPM W/RET REQ TY I(W)6"(SLD)(100MIL) LF 120,354.000 $0.500 $0.450 $0.450 $0.500 $0.480
6024 6024 HPPM W/RET REQ TY I(Y)6"(SLD)(100MIL) LF 120,354.000 $0.500 $0.450 $0.450 $0.500 $0.480
6185 6002 TMA (STATIONARY) DAY 60.000 $350.000 $153.840 $300.000 $150.000 $625.000
6185 6005 TMA (MOBILE OPERATION) DAY 60.000 $250.000 $82.050 $150.000 $80.000 $625.000
Totals: $13,026,398.48 $10,399,532.44 $10,780,252.65 $11,106,267.74 $11,872,065.28