Job Info for 0334-08-037

County: FAYETTE Highway: FM 154 Date: 06/02/2023 (1 year ago) Engineer's Estimate: $2,167,131 Control Number: 0334-08-037
Project: BR 2023(900) District: YOAKUM Time: 0 X Type: BRIDGE REPLACEMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,167,130.80
TREVWAY, INC.   $1,628,762.24 1
-24.84% | -$538,368.56
JOHN REED AND COMPANY, LLC   $1,838,380.65 2
-15.17% | -$328,750.15
12.87% | $209,618.41
ACME BRIDGE COMPANY, INC.   $2,037,104.63 3
-6% | -$130,026.17
25.07% | $408,342.39
10.81% | $198,723.98
E-Z BEL CONSTRUCTION, LLC   $2,090,255.90 4
-3.55% | -$76,874.90
28.33% | $461,493.66
2.61% | $53,151.27
CONSTAR CONSTRUCTION   $2,205,808.00 5
1.78% | $38,677.20
35.43% | $577,045.76
5.53% | $115,552.10
TEXAS MATERIALS GROUP, INC.   $2,295,144.55 6
5.91% | $128,013.75
40.91% | $666,382.31
4.05% | $89,336.55
CROSS PLUS CONSTRUCTION, LLC   $2,394,615.00 7
10.5% | $227,484.20
47.02% | $765,852.76
4.33% | $99,470.45
Subcontractor Percentage Amount
LONE STAR PAVING COMPANY 18.91% $253,447.37
JH CONTRACT FIELD SERVICES, LLC 3.26% $43,693.20
DUSTROL, INC. 1.68% $22,516.74
DIIBS SPECIALISTS, LLC 1.17% $15,681.30
A K FUQUAY CONSTRUCTION 0.51% $6,835.44
SUPERIOR TRAFFIC CONTROL, LLC 0.45% $6,031.27
HOUSTON SAWING & DRILLING 0.38% $5,093.07
Total: 26.36% $353,298.39

Bid Items

Items: 48, 0 filtered
FAYETTE FM 154  |  YOAKUM  |  0334-08-037  |  06/02/2023  |  $2,167,131  |  BR 2023(900)  |  BRIDGE REPL  |  0 X
Item code Description Unit Quantity Engineer's Estimate TREVWAY, INC. JOHN REED AND COMPANY, LLC ACME BRIDGE COMPANY, INC. E-Z BEL CONSTRUCTION, LLC CONSTAR CONSTRUCTION TEXAS MATERIALS GROUP, INC. CROSS PLUS CONSTRUCTION, LLC
100 6002 PREPARING ROW STA 10.000 $5,000.000 $5,500.000 $15,000.000 $5,377.870 $2,130.000 $5,000.000 $18,000.000 $3,300.000
105 6037 REMOVING STAB BASE AND ASPH PAV(0"-16") SY 2,277.000 $20.000 $21.520 $20.000 $6.530 $6.000 $20.000 $11.000 $17.000
110 6001 EXCAVATION (ROADWAY) CY 813.000 $35.000 $15.000 $20.000 $30.320 $19.000 $25.000 $50.000 $44.000
110 6002 EXCAVATION (CHANNEL) CY 411.000 $35.000 $7.000 $20.000 $28.300 $19.000 $26.000 $50.000 $55.000
132 6005 EMBANKMENT (FINAL)(ORD COMP)(TY C) CY 361.000 $35.000 $9.000 $25.000 $26.420 $17.000 $30.000 $50.000 $55.000
150 6002 BLADING HR 10.000 $150.000 $100.000 $40.000 $147.920 $80.000 $130.000 $100.000 $110.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 203.000 $3.000 $10.000 $4.000 $13.680 $10.000 $16.000 $5.000 $11.000
164 6023 CELL FBR MLCH SEED(PERM)(RURAL)(CLAY) SY 4,347.000 $1.000 $1.500 $0.750 $2.010 $0.600 $1.000 $0.750 $6.000
164 6029 CELL FBR MLCH SEED(TEMP)(WARM) SY 1,088.000 $1.000 $0.500 $0.650 $2.010 $1.000 $1.000 $0.650 $6.000
164 6031 CELL FBR MLCH SEED(TEMP)(COOL) SY 1,088.000 $1.000 $0.500 $0.650 $2.010 $1.000 $1.000 $0.650 $6.000
168 6001 VEGETATIVE WATERING MG 36.600 $75.000 $10.000 $20.000 $82.060 $150.000 $140.000 $40.000 $110.000
169 6001 SOIL RETENTION BLANKETS (CL 1) (TY A) SY 174.000 $3.000 $3.000 $1.750 $4.020 $3.000 $2.000 $1.750 $11.000
169 6002 SOIL RETENTION BLANKETS (CL 1) (TY B) SY 116.000 $3.000 $3.000 $1.750 $6.710 $3.000 $2.000 $1.750 $17.000
169 6003 SOIL RETENTION BLANKETS (CL 1) (TY C) SY 333.000 $3.000 $3.000 $2.500 $4.020 $3.000 $3.000 $2.500 $17.000
260 6012 LIME(HYD,COM OR QK)(SLRY)OR QK(DRY) TON 29.000 $295.000 $175.000 $300.000 $431.540 $328.000 $400.000 $380.000 $440.000
260 6027 LIME TRT (EXST MATL)(8") SY 1,182.000 $12.000 $13.000 $3.000 $10.330 $7.000 $20.000 $17.000 $17.000
400 6005 CEM STABIL BKFL CY 42.000 $200.000 $150.000 $100.000 $244.700 $350.000 $130.000 $300.000 $275.000
416 6002 DRILL SHAFT (24 IN) LF 296.000 $275.000 $262.000 $300.000 $233.980 $315.000 $350.000 $500.000 $248.000
420 6013 CL C CONC (ABUT) CY 24.400 $1,600.000 $1,136.000 $1,800.000 $1,387.570 $1,350.000 $1,150.000 $2,100.000 $1,980.000
420 6029 CL C CONC (CAP) CY 11.300 $1,750.000 $1,397.000 $1,800.000 $1,695.830 $1,800.000 $1,500.000 $2,900.000 $4,400.000
420 6037 CL C CONC (COLUMN) CY 3.800 $1,750.000 $2,200.000 $1,800.000 $2,839.920 $5,000.000 $950.000 $3,900.000 $2,750.000
422 6001 REINF CONC SLAB SF 3,071.000 $28.000 $55.000 $20.000 $23.930 $36.000 $28.000 $31.000 $28.000
425 6011 PRESTR CONC SLAB BEAM (4SB15) LF 534.000 $265.000 $223.000 $240.000 $265.830 $305.000 $280.000 $240.000 $220.000
425 6012 PRESTR CONC SLAB BEAM (5SB15) LF 178.000 $280.000 $221.000 $240.000 $270.000 $298.000 $280.000 $240.000 $220.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 996.000 $200.000 $35.000 $120.000 $163.460 $170.000 $220.000 $200.000 $248.000
450 6006 RAIL (TY T223) LF 204.000 $200.000 $150.000 $120.000 $139.750 $280.000 $160.000 $190.000 $275.000
454 6004 ARMOR JOINT (SEALED) LF 67.000 $180.000 $90.000 $80.000 $180.580 $150.000 $90.000 $125.000 $165.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 1.000 $40,000.000 $100,000.000 $120,000.000 $37,140.530 $50,000.000 $37,000.000 $100,000.000 $44,000.000
500 6001 MOBILIZATION LS 1.000 $129,262.800 $160,000.000 $130,000.000 $102,260.810 $125,000.000 $130,000.000 $180,000.000 $165,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 7.000 $3,800.000 $1,100.000 $2,000.000 $4,321.100 $5,000.000 $1,400.000 $10,000.000 $5,500.000
506 6001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 50.000 $50.000 $15.000 $40.000 $67.070 $43.000 $50.000 $38.000 $110.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 50.000 $15.000 $10.000 $15.000 $13.410 $20.000 $20.000 $15.000 $1.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,123.000 $4.000 $3.000 $4.000 $4.020 $3.950 $6.000 $4.800 $17.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,123.000 $1.000 $1.000 $1.000 $0.670 $0.950 $2.000 $1.500 $1.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 550.000 $25.000 $24.190 $24.000 $30.510 $25.000 $30.000 $24.000 $44.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $2,300.000 $2,598.350 $1,900.000 $2,900.510 $2,000.000 $3,600.000 $2,300.000 $4,235.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 557.000 $4.000 $5.000 $4.000 $5.370 $2.500 $3.000 $3.000 $6.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $3,300.000 $3,000.000 $3,400.000 $4,504.780 $2,950.000 $4,400.000 $3,100.000 $4,235.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 4.000 $300.000 $200.000 $400.000 $536.600 $250.000 $460.000 $200.000 $275.000
658 6073 INSTL OM ASSM (OM-2Y)(WC)GND(BI) EA 12.000 $50.000 $33.000 $66.000 $88.470 $66.000 $150.000 $65.000 $55.000
672 6009 REFL PAV MRKR TY II-A-A EA 12.000 $6.000 $31.580 $20.000 $13.420 $10.000 $150.000 $10.000 $28.000
800 6001 NO. OF WORKING DAYS $/D 4,808.000 $155.000 $60.000 $96.000 $150.000 $150.000 $145.000 $100.000 $145.000
3076 6001 D-GR HMA TY-B PG64-22 TON 1,479.000 $150.000 $161.680 $124.000 $134.150 $121.000 $170.000 $150.000 $165.000
3076 6042 D-GR HMA TY-D SAC-B PG70-22 TON 351.000 $170.000 $194.000 $160.000 $167.690 $158.000 $200.000 $165.000 $165.000
3076 6066 TACK COAT GAL 673.000 $5.000 $5.000 $4.000 $5.370 $3.500 $5.000 $6.000 $6.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $9,200.000 $3,500.000 $12,000.000 $15,456.130 $13,000.000 $11,000.000 $15,000.000 $22,000.000
6439 6008 HPPM-RIB W/RET REQ TYI(W)6"(SLD)100MIL LF 1,746.000 $1.000 $8.840 $2.000 $10.060 $5.000 $13.000 $3.000 $11.000
6439 6014 HPPM-RIB W/RET REQ TYI(Y)6"(BRK)100MIL LF 219.000 $1.000 $16.420 $2.000 $10.060 $8.000 $13.000 $3.000 $11.000
Totals: $2,167,130.80 $1,628,762.24 $1,838,380.65 $2,037,104.66 $2,090,255.90 $2,205,808.00 $2,295,144.55 $2,394,615.00