FAYETTE SH 95 (0323-02-034)

Items: 125

County: FAYETTE
Length: N/A
Highway: SH 95
District: YOAKUM
Control Number: 0323-02-034
DBE Goal: N/A
Project: STP 1902(163)
Guaranty: N/A
Time: 300 WORKING DAYS
Engineer's Estimate: $16,938,585.15
Date: 07/10/2019 (6 years ago)
Contract Number: N/A
Type: REHABILITATION OF EXISTING ROAD
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$16,938,585.15
$15,550,417.37
Over/Under Est: -8.2% -$1,388,167.78
Over/Under Est: 1.4% $236,650.33
Amt Left: 10.45% $1,624,818.11
$18,230,469.23
Over/Under Est: 7.63% $1,291,884.08
Amt Left: 17.23% $2,680,051.86
Delta: -6.14% -$1,055,233.75

Bid Items & Bid Tabulations

125 Total 0 of 125
FAYETTE  |  SH 95  |  YOAKUM  |  0323-02-034  |  07/10/2019  |  $16,938,585.15  |  STP 1902(163)  |  REHAB OF EXIST ROAD  |  300 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HUNTER INDUSTRIES, LTD.
ANGEL BROTHERS HOLDINGS CORP.
DEAN WORD COMPANY, LTD.
PREPARING ROW
STA 15.000 $2,000.000 $4,470.000 $2,000.000 $1,089.800
PREPARING ROW (TREE) (6" TO 24" DIA)
EA 3.000 $1,000.000 $2,310.000 $2,200.000 $2,184.000
PREPARING ROW(TREE)(24" TO 36" DIA.)
EA 13.000 $1,500.000 $2,782.500 $2,800.000 $2,756.000
PREPARING ROW (TREE) (36" TO 48" DIA)
EA 2.000 $3,000.000 $4,200.000 $4,200.000 $4,160.000
REMOVING CONC (RIPRAP)
SY 45.000 $15.000 $19.980 $16.000 $18.120
REMOVING CONC (CURB)
LF 1,748.000 $3.000 $6.660 $5.000 $3.074
REMOVING CONC (MISC)
SY 658.000 $35.000 $16.650 $17.000 $15.390
REMOVING STAB BASE & ASPH PAV (10"-12")
SY 20,067.000 $3.500 $8.480 $7.000 $9.737
EXCAVATION (ROADWAY)
CY 54,422.000 $12.000 $12.180 $15.000 $9.900
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 29,548.000 $15.000 $11.130 $15.000 $6.398
BACKFILL (TY B)
STA 332.900 $75.000 $111.750 $150.000 $99.056
BLADING
HR 100.000 $100.000 $96.900 $100.000 $98.800
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 359,186.000 $0.150 $0.110 $0.110 $0.109
DRILL SEEDING (TEMP) (WARM)
SY 89,797.000 $0.150 $0.090 $0.080 $0.078
DRILL SEEDING (TEMP) (COOL)
SY 89,797.000 $0.150 $0.090 $0.080 $0.078
VEGETATIVE WATERING
MG 3,023.400 $15.000 $23.310 $17.000 $22.177
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
CY 62,457.000 $70.000 $57.500 $62.000 $75.081
FL BS (RDWY DEL)(TY E GR 1-2)(FNL POS)
CY 13,473.000 $75.000 $57.500 $57.000 $76.420
LIME TRT (EXST MATL)(8")
SY 75,312.000 $3.000 $2.110 $2.500 $2.840
LIME (HYD, COM OR QK)(SLURRY)
TON 718.000 $200.000 $147.000 $160.000 $188.320
CEMENT
TON 2,209.000 $150.000 $141.750 $150.000 $180.316
CEMENT TREAT (MX EXST MTL & NW BS)(8")
SY 181,777.000 $2.500 $1.940 $1.700 $1.522
ASPH (RC-250)
GAL 46,218.000 $3.750 $4.060 $4.300 $4.338
AGGR(TY-E GR-5 SAC-B)
CY 1,651.000 $85.000 $77.210 $120.000 $108.193
AGGR(TY-PE GR-3 SAC-B)
CY 2,719.000 $85.000 $83.830 $105.000 $103.573
AGGR(TY-PE GR-4 SAC-B)
CY 3,302.000 $85.000 $83.840 $95.000 $98.027
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 238,397.000 $3.250 $3.730 $3.800 $3.646
D-GR HMA TY-B PG64-22
TON 20,969.000 $72.500 $69.120 $76.000 $93.845
D-GR HMA TY-D SAC-B PG70-22
TON 22,284.000 $70.000 $80.190 $84.000 $90.270
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 4,618.000 $40.000 $29.660 $40.000 $42.556
CEM STABIL BKFL
CY 610.000 $85.000 $141.760 $130.000 $124.800
CUT & RESTORING PAV
SY 417.000 $100.000 $120.000 $160.000 $156.000
CUT AND RESTORE PAV (FLEX BASE)
SY 125.600 $50.000 $60.000 $50.000 $46.800
TRENCH EXCAVATION PROTECTION
LF 630.000 $3.000 $15.750 $13.000 $12.480
TEMPORARY SPL SHORING
SF 600.000 $15.000 $29.400 $52.000 $52.000
RIPRAP (CONC)(4 IN)
CY 29.900 $400.000 $414.770 $520.000 $558.400
RIPRAP (CONC)(5 IN)
CY 32.800 $450.000 $414.770 $570.000 $610.400
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 76.000 $125.000 $157.510 $105.000 $142.400
RETROFIT RAIL (TY T631)
LF 412.000 $100.000 $120.000 $75.000 $66.560
CMP (GAL STL 12 IN)
LF 8.000 $50.000 $132.890 $62.000 $62.400
CMP (GAL STL 18 IN)
LF 216.000 $55.000 $65.520 $52.000 $52.000
CMP (GAL STL 24 IN)
LF 44.000 $65.000 $82.380 $100.000 $95.680
CMP (GAL STL 30 IN)
LF 12.000 $75.000 $139.240 $210.000 $208.000
RC PIPE (CL III)(18 IN)
LF 520.000 $60.000 $74.090 $60.000 $60.320
RC PIPE (CL III)(24 IN)
LF 994.000 $65.000 $84.380 $110.000 $109.200
RC PIPE (CL III)(30 IN)
LF 250.000 $75.000 $108.050 $135.000 $135.200
RC PIPE (CL III)(36 IN)
LF 304.000 $100.000 $147.150 $180.000 $176.800
RC PIPE (CL III)(42 IN)
LF 368.000 $150.000 $190.370 $210.000 $203.840
SET (TY I)(S= 8 FT)(HW= 8 FT)(3:1) (C)
EA 4.000 $20,000.000 $9,609.990 $15,000.000 $14,560.000
SET (TY I)(S= 9 FT)(HW= 7 FT)(3:1) (C)
EA 4.000 $20,000.000 $6,634.170 $16,000.000 $15,600.000
SET (TY II) (12 IN) (CMP) (6: 1) (P)
EA 2.000 $850.000 $1,126.170 $800.000 $780.000
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 70.000 $900.000 $1,139.820 $900.000 $884.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 32.000 $1,000.000 $1,173.950 $900.000 $884.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 12.000 $1,200.000 $1,167.120 $1,000.000 $988.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 30.000 $1,200.000 $1,173.950 $950.000 $936.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 4.000 $1,300.000 $1,173.950 $1,000.000 $988.000
SET (TY II) (30 IN) (CMP) (6: 1) (P)
EA 2.000 $1,500.000 $1,289.980 $3,100.000 $3,120.000
SET (TY II) (30 IN) (RCP) (3: 1) (C)
EA 2.000 $1,750.000 $1,337.750 $2,100.000 $2,080.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 8.000 $1,750.000 $1,337.750 $2,600.000 $2,600.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 12.000 $2,500.000 $1,747.270 $3,600.000 $3,640.000
SET (TY II) (42 IN) (RCP) (3: 1) (C)
EA 4.000 $3,000.000 $2,519.890 $4,600.000 $4,680.000
SET (TY II) (42 IN) (RCP) (4: 1) (C)
EA 4.000 $4,000.000 $2,519.890 $5,100.000 $5,200.000
ADJUSTING MANHOLES (SANITARY)
EA 2.000 $1,500.000 $945.040 $2,600.000 $2,600.000
ADJUSTING MANHOLES (WATER VALVE BOX)
EA 14.000 $450.000 $840.030 $1,600.000 $1,560.000
CLEAN EXIST CULVERTS
CY 15.000 $100.000 $1,260.050 $2,600.000 $2,600.000
REMOV STR (SMALL)
EA 22.000 $1,000.000 $1,260.050 $800.000 $780.000
MOBILIZATION
LS 1.000 $1,250,000.000 $1,443,718.920 $1,400,000.000 $1,584,314.495
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 20.000 $7,500.000 $3,432.060 $5,000.000 $4,202.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 300.000 $30.000 $30.970 $27.000 $28.080
ROCK FILTER DAMS (REMOVE)
LF 300.000 $10.000 $8.530 $9.000 $19.500
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,960.000 $3.000 $4.630 $4.000 $2.548
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,960.000 $1.000 $0.480 $1.000 $1.196
CONSTRUCTING DETOURS
SY 18,716.000 $50.000 $20.350 $35.000 $28.355
DRIVEWAYS (CONC)
SY 142.100 $75.000 $68.250 $130.000 $130.000
DRIVEWAYS (ACP)
SY 336.700 $30.000 $34.080 $60.000 $33.705
DRIVEWAYS (SURF TREAT)
SY 6,535.600 $30.000 $20.850 $40.000 $23.979
RUMBLE STRIPS (SHOULDER)
LF 73,850.000 $0.200 $0.190 $0.250 $0.159
RUMBLE STRIPS (CENTERLINE)
LF 36,925.000 $0.250 $0.230 $0.250 $0.180
MTL W-BEAM GD FEN (TIM POST)
LF 3,057.000 $22.000 $16.670 $23.000 $16.640
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $1,900.000 $2,709.450 $2,000.000 $2,622.700
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 68.000 $60.000 $47.940 $67.000 $47.840
REMOVE METAL BEAM GUARD FENCE
LF 5,570.000 $2.000 $1.560 $1.000 $1.560
REMOVE TERMINAL ANCHOR SECTION
EA 18.000 $175.000 $104.210 $160.000 $104.000
GUARDRAIL END TREATMENT (INSTALL)
EA 32.000 $2,400.000 $2,188.400 $2,900.000 $2,184.000
GUARDRAIL END TREATMENT (REMOVE)
EA 16.000 $250.000 $104.210 $160.000 $104.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 1.000 $350.000 $350.000 $370.000 $364.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 26.000 $200.000 $110.000 $120.000 $114.400
MAILBOX INSTALL-D (WC-POST) TY 3
EA 2.000 $250.000 $150.000 $160.000 $156.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 3.000 $400.000 $390.000 $400.000 $405.600
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 8.000 $550.000 $460.000 $480.000 $478.400
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 4.000 $600.000 $585.000 $600.000 $608.400
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $600.000 $610.000 $630.000 $634.400
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $700.000 $685.000 $700.000 $712.400
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
EA 3.000 $800.000 $840.000 $870.000 $873.600
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 41.000 $350.000 $275.000 $300.000 $286.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 18.000 $400.000 $305.000 $320.000 $317.200
REMOVE SM RD SN SUP&AM
EA 79.000 $70.000 $45.000 $125.000 $46.800
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 20.000 $20.000 $25.000 $27.000 $26.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 62.000 $20.000 $28.000 $30.000 $29.120
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
EA 40.000 $60.000 $56.000 $60.000 $58.240
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 4,200.000 $0.250 $0.220 $0.250 $0.385
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 496,020.000 $0.200 $0.210 $0.240 $0.333
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 1,130.000 $0.300 $0.400 $0.450 $1.040
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 39,133.000 $0.250 $0.220 $0.250 $0.385
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 296,475.000 $0.200 $0.220 $0.250 $0.354
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,374.000 $1.200 $1.780 $1.000 $1.419
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 26,568.000 $1.200 $1.780 $1.000 $1.288
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 725.000 $0.750 $0.600 $0.650 $0.655
REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL)
LF 61,240.000 $0.750 $0.770 $0.850 $0.624
REF PROF PAV MRK TY I(Y)4"(BRK)(090MIL)
LF 8,219.000 $0.750 $0.770 $0.850 $0.624
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
LF 1,473.000 $0.350 $0.310 $0.350 $0.291
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 87,430.000 $0.300 $0.310 $0.350 $0.281
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 102,850.000 $0.300 $0.340 $0.380 $0.343
RE PM W/RET REQ TY I (Y)4"(BRK)(060MIL)
LF 8,219.000 $0.350 $0.270 $0.300 $0.156
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 6,538.000 $0.350 $0.310 $0.350 $0.291
RE PM W/RET REQ TY I (Y)4"(SLD)(060MIL)
LF 61,240.000 $0.350 $0.270 $0.310 $0.156
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 52,110.000 $0.350 $0.310 $0.350 $0.281
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 1,108.000 $15.000 $17.520 $20.000 $13.520
PREFAB PAV MRK TY C (W) (ARROW)
EA 2.000 $200.000 $228.000 $250.000 $395.200
PREFAB PAV MRK TY C (W) (WORD)
EA 2.000 $250.000 $300.000 $350.000 $395.200
REFL PAV MRKR TY I-C
EA 98.000 $3.750 $3.250 $3.800 $4.680
REFL PAV MRKR TY II-A-A
EA 2,155.000 $3.500 $3.250 $3.800 $3.640
PORTABLE CHANGEABLE MESSAGE SIGN
EA 6.000 $8,000.000 $7,500.000 $15,000.000 $11,646.667
TMA (STATIONARY)
EA 2.000 $8,000.000 $7,500.000 $20,000.000 $13,900.000
TMA (MOBILE OPERATION)
DAY 36.000 $500.000 $900.000 $300.000 $1,404.000
Totals: $16,938,585.150 $15,550,417.399 $17,175,235.480 $18,230,469.367