PREPARING ROW
|
STA
|
15.000
|
$2,000.000
|
$4,470.000
|
$2,000.000
|
$1,089.800
|
|
|
PREPARING ROW (TREE) (6" TO 24" DIA)
|
EA
|
3.000
|
$1,000.000
|
$2,310.000
|
$2,200.000
|
$2,184.000
|
|
|
PREPARING ROW(TREE)(24" TO 36" DIA.)
|
EA
|
13.000
|
$1,500.000
|
$2,782.500
|
$2,800.000
|
$2,756.000
|
|
|
PREPARING ROW (TREE) (36" TO 48" DIA)
|
EA
|
2.000
|
$3,000.000
|
$4,200.000
|
$4,200.000
|
$4,160.000
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
45.000
|
$15.000
|
$19.980
|
$16.000
|
$18.120
|
|
|
REMOVING CONC (CURB)
|
LF
|
1,748.000
|
$3.000
|
$6.660
|
$5.000
|
$3.074
|
|
|
REMOVING CONC (MISC)
|
SY
|
658.000
|
$35.000
|
$16.650
|
$17.000
|
$15.390
|
|
|
REMOVING STAB BASE & ASPH PAV (10"-12")
|
SY
|
20,067.000
|
$3.500
|
$8.480
|
$7.000
|
$9.737
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
54,422.000
|
$12.000
|
$12.180
|
$15.000
|
$9.900
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY C)
|
CY
|
29,548.000
|
$15.000
|
$11.130
|
$15.000
|
$6.398
|
|
|
BACKFILL (TY B)
|
STA
|
332.900
|
$75.000
|
$111.750
|
$150.000
|
$99.056
|
|
|
BLADING
|
HR
|
100.000
|
$100.000
|
$96.900
|
$100.000
|
$98.800
|
|
|
DRILL SEEDING (PERM) (RURAL) (SANDY)
|
SY
|
359,186.000
|
$0.150
|
$0.110
|
$0.110
|
$0.109
|
|
|
DRILL SEEDING (TEMP) (WARM)
|
SY
|
89,797.000
|
$0.150
|
$0.090
|
$0.080
|
$0.078
|
|
|
DRILL SEEDING (TEMP) (COOL)
|
SY
|
89,797.000
|
$0.150
|
$0.090
|
$0.080
|
$0.078
|
|
|
VEGETATIVE WATERING
|
MG
|
3,023.400
|
$15.000
|
$23.310
|
$17.000
|
$22.177
|
|
|
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
|
CY
|
62,457.000
|
$70.000
|
$57.500
|
$62.000
|
$75.081
|
|
|
FL BS (RDWY DEL)(TY E GR 1-2)(FNL POS)
|
CY
|
13,473.000
|
$75.000
|
$57.500
|
$57.000
|
$76.420
|
|
|
LIME TRT (EXST MATL)(8")
|
SY
|
75,312.000
|
$3.000
|
$2.110
|
$2.500
|
$2.840
|
|
|
LIME (HYD, COM OR QK)(SLURRY)
|
TON
|
718.000
|
$200.000
|
$147.000
|
$160.000
|
$188.320
|
|
|
CEMENT
|
TON
|
2,209.000
|
$150.000
|
$141.750
|
$150.000
|
$180.316
|
|
|
CEMENT TREAT (MX EXST MTL & NW BS)(8")
|
SY
|
181,777.000
|
$2.500
|
$1.940
|
$1.700
|
$1.522
|
|
|
ASPH (RC-250)
|
GAL
|
46,218.000
|
$3.750
|
$4.060
|
$4.300
|
$4.338
|
|
|
AGGR(TY-E GR-5 SAC-B)
|
CY
|
1,651.000
|
$85.000
|
$77.210
|
$120.000
|
$108.193
|
|
|
AGGR(TY-PE GR-3 SAC-B)
|
CY
|
2,719.000
|
$85.000
|
$83.830
|
$105.000
|
$103.573
|
|
|
AGGR(TY-PE GR-4 SAC-B)
|
CY
|
3,302.000
|
$85.000
|
$83.840
|
$95.000
|
$98.027
|
|
|
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
|
GAL
|
238,397.000
|
$3.250
|
$3.730
|
$3.800
|
$3.646
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
20,969.000
|
$72.500
|
$69.120
|
$76.000
|
$93.845
|
|
|
D-GR HMA TY-D SAC-B PG70-22
|
TON
|
22,284.000
|
$70.000
|
$80.190
|
$84.000
|
$90.270
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
|
SY
|
4,618.000
|
$40.000
|
$29.660
|
$40.000
|
$42.556
|
|
|
CEM STABIL BKFL
|
CY
|
610.000
|
$85.000
|
$141.760
|
$130.000
|
$124.800
|
|
|
CUT & RESTORING PAV
|
SY
|
417.000
|
$100.000
|
$120.000
|
$160.000
|
$156.000
|
|
|
CUT AND RESTORE PAV (FLEX BASE)
|
SY
|
125.600
|
$50.000
|
$60.000
|
$50.000
|
$46.800
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
630.000
|
$3.000
|
$15.750
|
$13.000
|
$12.480
|
|
|
TEMPORARY SPL SHORING
|
SF
|
600.000
|
$15.000
|
$29.400
|
$52.000
|
$52.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
29.900
|
$400.000
|
$414.770
|
$520.000
|
$558.400
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
32.800
|
$450.000
|
$414.770
|
$570.000
|
$610.400
|
|
|
RIPRAP (STONE COMMON)(DRY)(12 IN)
|
CY
|
76.000
|
$125.000
|
$157.510
|
$105.000
|
$142.400
|
|
|
RETROFIT RAIL (TY T631)
|
LF
|
412.000
|
$100.000
|
$120.000
|
$75.000
|
$66.560
|
|
|
CMP (GAL STL 12 IN)
|
LF
|
8.000
|
$50.000
|
$132.890
|
$62.000
|
$62.400
|
|
|
CMP (GAL STL 18 IN)
|
LF
|
216.000
|
$55.000
|
$65.520
|
$52.000
|
$52.000
|
|
|
CMP (GAL STL 24 IN)
|
LF
|
44.000
|
$65.000
|
$82.380
|
$100.000
|
$95.680
|
|
|
CMP (GAL STL 30 IN)
|
LF
|
12.000
|
$75.000
|
$139.240
|
$210.000
|
$208.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
520.000
|
$60.000
|
$74.090
|
$60.000
|
$60.320
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
994.000
|
$65.000
|
$84.380
|
$110.000
|
$109.200
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
250.000
|
$75.000
|
$108.050
|
$135.000
|
$135.200
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
304.000
|
$100.000
|
$147.150
|
$180.000
|
$176.800
|
|
|
RC PIPE (CL III)(42 IN)
|
LF
|
368.000
|
$150.000
|
$190.370
|
$210.000
|
$203.840
|
|
|
SET (TY I)(S= 8 FT)(HW= 8 FT)(3:1) (C)
|
EA
|
4.000
|
$20,000.000
|
$9,609.990
|
$15,000.000
|
$14,560.000
|
|
|
SET (TY I)(S= 9 FT)(HW= 7 FT)(3:1) (C)
|
EA
|
4.000
|
$20,000.000
|
$6,634.170
|
$16,000.000
|
$15,600.000
|
|
|
SET (TY II) (12 IN) (CMP) (6: 1) (P)
|
EA
|
2.000
|
$850.000
|
$1,126.170
|
$800.000
|
$780.000
|
|
|
SET (TY II) (18 IN) (CMP) (6: 1) (P)
|
EA
|
70.000
|
$900.000
|
$1,139.820
|
$900.000
|
$884.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
32.000
|
$1,000.000
|
$1,173.950
|
$900.000
|
$884.000
|
|
|
SET (TY II) (24 IN) (CMP) (6: 1) (P)
|
EA
|
12.000
|
$1,200.000
|
$1,167.120
|
$1,000.000
|
$988.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
30.000
|
$1,200.000
|
$1,173.950
|
$950.000
|
$936.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$1,300.000
|
$1,173.950
|
$1,000.000
|
$988.000
|
|
|
SET (TY II) (30 IN) (CMP) (6: 1) (P)
|
EA
|
2.000
|
$1,500.000
|
$1,289.980
|
$3,100.000
|
$3,120.000
|
|
|
SET (TY II) (30 IN) (RCP) (3: 1) (C)
|
EA
|
2.000
|
$1,750.000
|
$1,337.750
|
$2,100.000
|
$2,080.000
|
|
|
SET (TY II) (30 IN) (RCP) (4: 1) (C)
|
EA
|
8.000
|
$1,750.000
|
$1,337.750
|
$2,600.000
|
$2,600.000
|
|
|
SET (TY II) (36 IN) (RCP) (4: 1) (C)
|
EA
|
12.000
|
$2,500.000
|
$1,747.270
|
$3,600.000
|
$3,640.000
|
|
|
SET (TY II) (42 IN) (RCP) (3: 1) (C)
|
EA
|
4.000
|
$3,000.000
|
$2,519.890
|
$4,600.000
|
$4,680.000
|
|
|
SET (TY II) (42 IN) (RCP) (4: 1) (C)
|
EA
|
4.000
|
$4,000.000
|
$2,519.890
|
$5,100.000
|
$5,200.000
|
|
|
ADJUSTING MANHOLES (SANITARY)
|
EA
|
2.000
|
$1,500.000
|
$945.040
|
$2,600.000
|
$2,600.000
|
|
|
ADJUSTING MANHOLES (WATER VALVE BOX)
|
EA
|
14.000
|
$450.000
|
$840.030
|
$1,600.000
|
$1,560.000
|
|
|
CLEAN EXIST CULVERTS
|
CY
|
15.000
|
$100.000
|
$1,260.050
|
$2,600.000
|
$2,600.000
|
|
|
REMOV STR (SMALL)
|
EA
|
22.000
|
$1,000.000
|
$1,260.050
|
$800.000
|
$780.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,250,000.000
|
$1,443,718.920
|
$1,400,000.000
|
$1,584,314.495
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
20.000
|
$7,500.000
|
$3,432.060
|
$5,000.000
|
$4,202.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
300.000
|
$30.000
|
$30.970
|
$27.000
|
$28.080
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
300.000
|
$10.000
|
$8.530
|
$9.000
|
$19.500
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
1,960.000
|
$3.000
|
$4.630
|
$4.000
|
$2.548
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
1,960.000
|
$1.000
|
$0.480
|
$1.000
|
$1.196
|
|
|
CONSTRUCTING DETOURS
|
SY
|
18,716.000
|
$50.000
|
$20.350
|
$35.000
|
$28.355
|
|
|
DRIVEWAYS (CONC)
|
SY
|
142.100
|
$75.000
|
$68.250
|
$130.000
|
$130.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
336.700
|
$30.000
|
$34.080
|
$60.000
|
$33.705
|
|
|
DRIVEWAYS (SURF TREAT)
|
SY
|
6,535.600
|
$30.000
|
$20.850
|
$40.000
|
$23.979
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
73,850.000
|
$0.200
|
$0.190
|
$0.250
|
$0.159
|
|
|
RUMBLE STRIPS (CENTERLINE)
|
LF
|
36,925.000
|
$0.250
|
$0.230
|
$0.250
|
$0.180
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
3,057.000
|
$22.000
|
$16.670
|
$23.000
|
$16.640
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$1,900.000
|
$2,709.450
|
$2,000.000
|
$2,622.700
|
|
|
MTL W - BEAM GD FEN (LOW FILL CULVERT)
|
LF
|
68.000
|
$60.000
|
$47.940
|
$67.000
|
$47.840
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
5,570.000
|
$2.000
|
$1.560
|
$1.000
|
$1.560
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
18.000
|
$175.000
|
$104.210
|
$160.000
|
$104.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
32.000
|
$2,400.000
|
$2,188.400
|
$2,900.000
|
$2,184.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
16.000
|
$250.000
|
$104.210
|
$160.000
|
$104.000
|
|
|
MAILBOX INSTALL-M (TWG-POST) TY 1
|
EA
|
1.000
|
$350.000
|
$350.000
|
$370.000
|
$364.000
|
|
|
MAILBOX INSTALL-S (WC-POST) TY 3
|
EA
|
26.000
|
$200.000
|
$110.000
|
$120.000
|
$114.400
|
|
|
MAILBOX INSTALL-D (WC-POST) TY 3
|
EA
|
2.000
|
$250.000
|
$150.000
|
$160.000
|
$156.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
3.000
|
$400.000
|
$390.000
|
$400.000
|
$405.600
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
8.000
|
$550.000
|
$460.000
|
$480.000
|
$478.400
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P)
|
EA
|
4.000
|
$600.000
|
$585.000
|
$600.000
|
$608.400
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
1.000
|
$600.000
|
$610.000
|
$630.000
|
$634.400
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
1.000
|
$700.000
|
$685.000
|
$700.000
|
$712.400
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
|
EA
|
3.000
|
$800.000
|
$840.000
|
$870.000
|
$873.600
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
41.000
|
$350.000
|
$275.000
|
$300.000
|
$286.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(T)
|
EA
|
18.000
|
$400.000
|
$305.000
|
$320.000
|
$317.200
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
79.000
|
$70.000
|
$45.000
|
$125.000
|
$46.800
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
20.000
|
$20.000
|
$25.000
|
$27.000
|
$26.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
62.000
|
$20.000
|
$28.000
|
$30.000
|
$29.120
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
|
EA
|
40.000
|
$60.000
|
$56.000
|
$60.000
|
$58.240
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
|
LF
|
4,200.000
|
$0.250
|
$0.220
|
$0.250
|
$0.385
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
496,020.000
|
$0.200
|
$0.210
|
$0.240
|
$0.333
|
|
|
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
|
LF
|
1,130.000
|
$0.300
|
$0.400
|
$0.450
|
$1.040
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
|
LF
|
39,133.000
|
$0.250
|
$0.220
|
$0.250
|
$0.385
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
296,475.000
|
$0.200
|
$0.220
|
$0.250
|
$0.354
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
1,374.000
|
$1.200
|
$1.780
|
$1.000
|
$1.419
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
26,568.000
|
$1.200
|
$1.780
|
$1.000
|
$1.288
|
|
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
|
LF
|
725.000
|
$0.750
|
$0.600
|
$0.650
|
$0.655
|
|
|
REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL)
|
LF
|
61,240.000
|
$0.750
|
$0.770
|
$0.850
|
$0.624
|
|
|
REF PROF PAV MRK TY I(Y)4"(BRK)(090MIL)
|
LF
|
8,219.000
|
$0.750
|
$0.770
|
$0.850
|
$0.624
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
|
LF
|
1,473.000
|
$0.350
|
$0.310
|
$0.350
|
$0.291
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
|
LF
|
87,430.000
|
$0.300
|
$0.310
|
$0.350
|
$0.281
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
102,850.000
|
$0.300
|
$0.340
|
$0.380
|
$0.343
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(060MIL)
|
LF
|
8,219.000
|
$0.350
|
$0.270
|
$0.300
|
$0.156
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
|
LF
|
6,538.000
|
$0.350
|
$0.310
|
$0.350
|
$0.291
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(060MIL)
|
LF
|
61,240.000
|
$0.350
|
$0.270
|
$0.310
|
$0.156
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
|
LF
|
52,110.000
|
$0.350
|
$0.310
|
$0.350
|
$0.281
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
1,108.000
|
$15.000
|
$17.520
|
$20.000
|
$13.520
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
2.000
|
$200.000
|
$228.000
|
$250.000
|
$395.200
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
2.000
|
$250.000
|
$300.000
|
$350.000
|
$395.200
|
|
REFL PAV MRKR TY I-C
|
EA
|
98.000
|
$3.750
|
$3.250
|
$3.800
|
$4.680
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
2,155.000
|
$3.500
|
$3.250
|
$3.800
|
$3.640
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
6.000
|
$8,000.000
|
$7,500.000
|
$15,000.000
|
$11,646.667
|
|
|
TMA (STATIONARY)
|
EA
|
2.000
|
$8,000.000
|
$7,500.000
|
$20,000.000
|
$13,900.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
36.000
|
$500.000
|
$900.000
|
$300.000
|
$1,404.000
|
|
Totals: |
$16,938,585.150
|
$15,550,417.399
|
$17,175,235.480
|
$18,230,469.367
|