Job Info for 0620-01-019

County: FANNIN Highway: FM 68 Date: 07/10/2024 (4 months ago) Engineer's Estimate: $3,101,166 Control Number: 0620-01-019
Project: BR 2B24(278) District: PARIS Time: 139 WORKING DAYS Type: BRIDGE REPLACEMENT
Bidder's List
Informational:

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,101,166.30
L & N BRIDGE, LLC   $2,823,236.80 1
-8.96% | -$277,929.50
TALBERT COMPANIES LLC   $3,071,967.61 2
-0.94% | -$29,198.69
8.81% | $248,730.81
C. E. BARKER, LTD.   $3,548,109.70 3
14.41% | $446,943.40
25.68% | $724,872.90
15.50% | $476,142.09
HODGES AND SON CONSTRUCTION COMPANY, INC.   $3,974,756.90 4
28.17% | $873,590.60
40.79% | $1,151,520.10
12.02% | $426,647.20
EAST TEXAS BRIDGE, INC.   $4,242,106.10 5
36.79% | $1,140,939.80
50.26% | $1,418,869.30
6.73% | $267,349.20
RAGLE CONSTRUCTION, INC.   $4,493,861.62 6
44.91% | $1,392,695.32
59.17% | $1,670,624.82
5.93% | $251,755.52
Subcontractor Percentage Amount
PEACHTREE CONSTRUCTION, LTD. 11.71% $330,601.03
HODGES AND SON CONSTRUCTION COMPANY, INC. 8.87% $250,421.10
MORRIS COUNTY CONTRACTORS, L.L.C. 1.33% $37,549.05
DIAMOND ELITE BARRICADES, LLC 0.54% $15,245.48
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.52% $14,680.83
ELITE STRIPING, LLC 0.34% $9,599.01
GARY A. CRAIN, INC. 0.27% $7,622.74
Total: 23.58% $665,719.24

Bid Items

Items: 51, 0 filtered
FANNIN FM 68  |  PARIS  |  0620-01-019  |  07/10/2024  |  $3,101,166  |  BR 2B24(278)  |  BRIDGE REPL  |  139 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate L & N BRIDGE, LLC TALBERT COMPANIES LLC C. E. BARKER, LTD. HODGES AND SON CONSTRUCTION COMPANY, INC. EAST TEXAS BRIDGE, INC. RAGLE CONSTRUCTION, INC.
100 6002 PREPARING ROW STA 13.160 $2,000.000 $850.000 $2,737.500 $12,500.000 $4,000.000 $5,500.000 $33,000.000
110 6001 EXCAVATION (ROADWAY) CY 270.000 $25.000 $30.000 $54.750 $24.190 $40.000 $35.000 $299.000
110 6002 EXCAVATION (CHANNEL) CY 302.000 $25.000 $13.000 $54.750 $24.190 $40.000 $35.000 $299.000
132 6003 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 1,922.000 $30.000 $10.000 $54.750 $48.380 $40.000 $40.000 $50.000
164 6009 BROADCAST SEED (TEMP) (WARM) SY 2,304.000 $0.350 $0.780 $1.950 $1.210 $3.000 $1.200 $0.300
164 6011 BROADCAST SEED (TEMP) (COOL) SY 2,304.000 $0.350 $0.780 $1.950 $1.210 $3.000 $1.200 $0.310
164 6015 STRAW/HAY MLCH SEED(PERM)(RURAL)(CLAY) SY 4,608.000 $0.750 $0.690 $1.640 $1.210 $3.000 $1.750 $0.510
168 6001 VEGETATIVE WATERING MG 28.000 $25.000 $71.000 $54.750 $48.380 $1.000 $50.000 $129.000
251 6034 REWORK BS MTL (TY C) (8") (ORD COMP) SY 2,215.000 $8.000 $2.250 $7.660 $4.230 $15.000 $35.000 $9.400
400 6005 CEM STABIL BKFL CY 150.000 $325.000 $225.000 $279.660 $241.920 $300.000 $375.000 $133.000
416 6001 DRILL SHAFT (18 IN) LF 236.000 $150.000 $110.000 $104.020 $122.880 $100.000 $135.000 $117.000
416 6004 DRILL SHAFT (36 IN) LF 590.000 $300.000 $235.000 $197.100 $239.000 $200.000 $260.000 $222.000
416 6005 DRILL SHAFT (42 IN) LF 508.000 $350.000 $315.000 $262.800 $375.260 $300.000 $350.000 $305.000
420 6013 CL C CONC (ABUT) CY 64.800 $1,400.000 $1,300.000 $1,423.500 $1,498.850 $2,500.000 $2,000.000 $1,093.000
420 6029 CL C CONC (CAP) CY 84.000 $1,500.000 $1,400.000 $1,533.000 $1,709.680 $2,800.000 $2,700.000 $1,200.000
420 6037 CL C CONC (COLUMN) CY 71.500 $800.000 $1,300.000 $1,314.000 $1,757.150 $2,800.000 $2,600.000 $1,220.000
422 6001 REINF CONC SLAB SF 17,220.000 $28.000 $30.000 $27.370 $20.830 $35.000 $40.000 $29.100
422 6015 APPROACH SLAB CY 101.200 $700.000 $600.000 $547.500 $821.170 $1,000.000 $1,150.000 $781.000
425 6038 PRESTR CONC GIRDER (TX46) LF 2,039.620 $250.000 $273.000 $184.670 $310.980 $295.000 $295.000 $234.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 90.000 $165.000 $135.000 $230.430 $258.850 $250.000 $225.000 $251.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 50.000 $500.000 $475.000 $617.540 $464.490 $700.000 $750.000 $669.000
450 6097 RAIL (TY T222) LF 876.000 $200.000 $105.000 $163.300 $112.310 $120.000 $200.000 $109.000
454 6018 SEALED EXPANSION JOINT (4 IN) (SEJ - M) LF 144.000 $200.000 $240.000 $229.950 $260.060 $250.000 $325.000 $251.000
496 6010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) EA 1.000 $80,000.000 $75,000.000 $76,650.000 $151,375.390 $350,000.000 $200,000.000 $720,000.000
500 6001 MOBILIZATION LS 1.000 $281,924.000 $280,000.000 $265,000.000 $330,000.000 $385,000.000 $375,000.000 $450,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 9.000 $7,500.000 $1,273.220 $2,737.500 $934.200 $4,000.000 $20,000.000 $31,500.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 80.000 $40.000 $55.000 $71.170 $60.480 $1.000 $75.000 $46.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 80.000 $10.000 $10.000 $27.370 $12.100 $1.000 $30.000 $20.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 333.000 $30.000 $25.000 $49.270 $18.140 $1.000 $50.000 $39.500
506 6024 CONSTRUCTION EXITS (REMOVE) SY 333.000 $10.000 $5.000 $14.230 $6.050 $1.000 $15.000 $18.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 2,011.000 $4.000 $3.050 $4.100 $4.840 $1.000 $4.500 $3.250
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 2,011.000 $1.500 $1.000 $1.090 $1.210 $1.000 $1.100 $1.150
530 6016 DRIVEWAYS (BASE) SY 49.000 $40.000 $28.000 $37.170 $36.290 $80.000 $100.000 $45.100
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 550.000 $30.000 $27.500 $33.940 $37.500 $26.000 $32.000 $31.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $2,100.000 $2,100.000 $2,682.750 $2,963.520 $1,800.000 $2,400.000 $3,550.530
542 6001 REMOVE METAL BEAM GUARD FENCE LF 140.000 $3.000 $3.000 $2.730 $3.020 $5.000 $5.000 $2.500
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 4.000 $300.000 $200.000 $273.750 $302.400 $500.000 $300.000 $250.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $3,000.000 $3,000.000 $3,394.500 $3,749.760 $3,000.000 $3,500.000 $3,100.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 10.000 $40.000 $20.000 $24.090 $26.610 $50.000 $30.000 $22.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 12.000 $30.000 $25.000 $26.280 $29.030 $50.000 $35.000 $24.000
666 6225 PAVEMENT SEALER 6" LF 1,640.000 $1.000 $0.500 $1.090 $0.600 $1.000 $1.000 $0.500
666 6308 RE PM W/RET REQ TY I (W)6"(SLD)(090MIL) LF 2,632.000 $2.000 $1.500 $3.170 $1.810 $5.000 $2.000 $1.500
666 6320 RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL) LF 2,632.000 $2.000 $1.500 $3.170 $1.810 $5.000 $2.000 $1.500
672 6009 REFL PAV MRKR TY II-A-A EA 66.000 $10.000 $10.000 $21.900 $12.100 $20.000 $15.000 $10.000
678 6002 PAV SURF PREP FOR MRK (6") LF 1,640.000 $1.000 $0.250 $1.090 $0.300 $2.000 $1.000 $0.250
3076 6003 D-GR HMA TY-B PG64-22 (EXEMPT) TON 1,587.000 $170.000 $141.500 $246.370 $272.160 $150.000 $160.000 $141.500
3076 6067 D-GR HMA TY-C SAC-A PG64-22(EXEMPT) TON 596.000 $170.000 $163.500 $273.750 $302.400 $180.000 $185.000 $163.500
3084 6001 BONDING COURSE GAL 215.000 $10.000 $4.000 $21.900 $24.190 $6.000 $5.000 $4.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 4.000 $16,000.000 $12,500.000 $14,439.100 $7,257.600 $30,000.000 $25,000.000 $13,250.000
6185 6002 TMA (STATIONARY) DAY 10.000 $500.000 $325.000 $551.150 $332.640 $300.000 $500.000 $346.000
6185 6003 TMA (MOBILE OPERATION) HR 40.000 $100.000 $75.000 $138.290 $108.860 $40.000 $50.000 $81.000
Totals: $3,101,166.30 $2,823,236.80 $3,071,967.62 $3,548,109.72 $3,974,756.90 $4,242,106.10 $4,493,861.62