ELLIS US0077 (6403-16-001)

Items: 12

County: ELLIS
Length: N/A
Highway: US0077
District: DALLAS
Control Number: 6403-16-001
DBE Goal: N/A
Project: BPM - 640316001
Guaranty: N/A
Time: 120 W
Engineer's Estimate: $607,490.00
Date: 03/07/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE PREVENTATIVE MAINTENANCE
Mail/Deliver Bids To: N/A
JUAN PAREDES
MICHAEL ANTHONY
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (9)
E
Engineer's Estimate
$607,490.00
$509,810.00
Over/Under Est: -16.08% -$97,680.00
Over/Under Est: -6.7% -$40,713.00
Amt Left: 11.17% $56,967.00
Over/Under Est: -2.76% -$16,738.00
Amt Left: 15.88% $80,942.00
Delta: -4.23% -$23,975.00
Over/Under Est: 9.11% $55,350.28
Amt Left: 30.02% $153,030.28
Delta: -12.20% -$72,088.28
Over/Under Est: 12.96% $78,710.00
Amt Left: 34.6% $176,390.00
Delta: -3.52% -$23,359.72
Over/Under Est: 19.66% $119,434.00
Amt Left: 42.59% $217,114.00
Delta: -5.93% -$40,724.00
Over/Under Est: 27.67% $168,110.00
Amt Left: 52.14% $265,790.00
Delta: -6.70% -$48,676.00
Over/Under Est: 34.88% $211,910.00
Amt Left: 60.73% $309,590.00
Delta: -5.65% -$43,800.00
Over/Under Est: 39.15% $237,860.00
Amt Left: 65.82% $335,540.00
Delta: -3.17% -$25,950.00

Bid Items & Bid Tabulations

12 Total 0 of 12
ELLIS  |  US0077  |  DALLAS  |  6403-16-001  |  03/07/2023  |  $607,490.00  |  BPM - 640316001  |  BRIDGE PREVENT MAINT  |  120 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
SHALOM SERVICES CORPORATION
BECK-REIT & SONS, LTD.
CROSS PLUS CONSTRUCTION, LLC
SCOUT 5 CONSTRUCTION LLC
GARRET SHIELDS INFRASTRUCTURE
TALBRAN ENTERPRISES LLC
SJ&J CONSTRUCTION, LLC
PATHFIELD INVESTMENTS LLC
FNH CONSTRUCTION, LLC
REMOVING CONC (RIPRAP)
SY 20.000 $60.000 $30.000 $100.000 $275.000 $567.000 $50.000 $230.000 $40.000 $250.000 $100.000
FLOWABLE BACKFILL
CY 2.000 $500.000 $300.000 $400.000 $2,200.000 $3,300.000 $1,000.000 $1,250.000 $250.000 $800.000 $350.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 4.000 $550.000 $600.000 $1,000.000 $2,200.000 $3,600.000 $1,000.000 $1,250.000 $600.000 $1,200.000 $750.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 3,100.000 $165.000 $160.000 $150.000 $165.000 $186.000 $190.000 $220.000 $220.000 $225.000 $220.000
MOBILIZATION
LS 1.000 $54,990.000 $1,000.000 $88,055.000 $27,500.000 $12,000.000 $55,000.000 $25,000.000 $25,000.000 $60,000.000 $70,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $1,500.000 $1,000.000 $1,000.000 $1,100.000 $0.010 $2,000.000 $1,000.000 $7,000.000 $3,500.000 $8,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 50.000 $60.000 $50.000 $1.000 $220.000 $597.000 $50.000 $10.000 $12.000 $20.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 50.000 $20.000 $1.000 $1.000 $55.000 $97.000 $30.000 $10.000 $6.000 $10.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 400.000 $8.000 $1.000 $1.000 $17.000 $12.000 $6.000 $1.000 $4.000 $10.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 400.000 $2.500 $0.500 $1.000 $1.000 $6.000 $2.000 $1.000 $1.000 $5.000 $2.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $7,500.000 $20.000 $1.000 $1.000 $0.010 $5,000.000 $2.000 $8,500.000 $8,000.000 $12,500.000
TMA (STATIONARY)
DAY 20.000 $220.000 $1.000 $1.000 $275.000 $0.010 $300.000 $1.000 $150.000 $300.000 $350.000
Totals: $607,490.000 $509,810.000 $566,777.000 $590,752.000 $662,840.280 $686,200.000 $726,924.000 $775,600.000 $819,400.000 $845,350.000