County: ELLIS Highway: VA Date: 06/06/2018 (6 years ago) Engineer's Estimate: $4,614,169 Control Number: 0918-22-157
Project: C 918-22-157 District: DALLAS Time: 246 WORKING DAYS Type: REPLACE TURNDOWNS AND GUARDRAIL

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $4,614,168.52
DBI SERVICES, LLC   $4,527,134.12 1
-1.89% | -$87,034.40
IIPL USA LLC   $4,569,489.00 2
-0.97% | -$44,679.52
0.94% | $42,354.88
FNH CONSTRUCTION, LLC   $5,637,755.50 3
22.18% | $1,023,586.98
24.53% | $1,110,621.38
23.38% | $1,068,266.50

Bid Items

Items: 30, 0 filtered
ELLIS VA  |  DALLAS  |  0918-22-157  |  06/06/2018  |  $4,614,169  |  C 918-22-157  |  REPLACE TURNDOWNS AND GUARDRAIL  |  246 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate DBI SERVICES, LLC IIPL USA LLC FNH CONSTRUCTION, LLC
100 6002 PREPARING ROW STA 492.080 $800.000 $689.000 $500.000 $1,100.000
104 6009 REMOVING CONC (RIPRAP) SY 4.000 $30.000 $59.000 $250.000 $1,000.000
132 6005 EMBANKMENT (FINAL)(ORD COMP)(TY C) CY 20,626.000 $35.000 $28.000 $38.000 $25.000
162 6002 BLOCK SODDING SY 5,494.000 $3.250 $11.000 $5.000 $5.500
164 6023 CELL FBR MLCH SEED(PERM)(RURAL)(CLAY) SY 54,938.000 $0.320 $1.000 $0.500 $0.500
164 6029 CELL FBR MLCH SEED(TEMP)(WARM) SY 27,469.000 $0.340 $1.000 $1.000 $0.500
164 6031 CELL FBR MLCH SEED(TEMP)(COOL) SY 27,469.000 $0.340 $1.000 $1.000 $0.500
168 6001 VEGETATIVE WATERING MG 7,492.000 $18.000 $11.000 $28.000 $38.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 2,136.000 $439.920 $401.000 $400.000 $550.000
500 6001 MOBILIZATION LS 1.000 $384,015.320 $183,063.000 $400,000.000 $560,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 13.000 $30,000.000 $6,973.000 $5,000.000 $12,500.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 200.000 $22.520 $48.000 $20.000 $30.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 200.000 $7.660 $12.000 $10.000 $15.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 4,950.000 $1.450 $7.000 $4.000 $4.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 4,950.000 $0.350 $3.000 $2.000 $2.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 32,325.000 $17.500 $20.000 $20.000 $20.500
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 80.000 $1,000.000 $2,075.000 $1,500.000 $1,850.000
540 6008 MTL BEAM GD FEN TRANS (T101) EA 52.000 $950.000 $2,241.000 $1,000.000 $1,850.000
540 6014 SHORT RADIUS LF 773.000 $27.500 $35.000 $25.000 $35.000
540 6015 DRIVEWAY TERMINAL ANCHOR SECTION EA 4.000 $875.000 $912.000 $1,000.000 $1,850.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 61.000 $850.000 $1,621.000 $1,000.000 $1,850.000
540 6017 MTL BM GD FEN (LONG SPAN SYSTEM) LF 100.000 $30.000 $26.000 $20.000 $35.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 38,683.000 $2.000 $5.000 $1.000 $3.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 322.000 $150.000 $254.000 $300.000 $500.000
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 132.000 $200.000 $254.000 $300.000 $500.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 256.000 $2,100.000 $2,374.000 $2,500.000 $2,550.000
545 6013 CRASH CUSH ATTEN (INSTL)(R)(N)(TL3) EA 5.000 $9,500.000 $16,114.000 $14,000.000 $15,000.000
658 6016 INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI) EA 625.000 $19.000 $17.000 $20.000 $50.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 625.000 $32.380 $17.000 $20.000 $50.000
6185 6002 TMA (STATIONARY) DAY 246.000 $150.000 $351.000 $200.000 $325.000
Totals: $4,614,168.52 $4,527,134.12 $4,569,489.00 $5,637,755.50