ELLIS IH 45 (0092-03-050)
Items: 56
County: ELLIS
Length: N/A
Highway: IH 45
District: DALLAS
Control Number: 0092-03-050
DBE Goal: N/A
Project: C 92-3-50
Guaranty: N/A
Time: 113 WORKING DAYS
Engineer's Estimate: $3,261,978.00
Date: 06/05/2018 (8 years ago)
Contract Number: N/A
Type: SLOPE FAILURE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,261,978.00 | |||
| $2,877,641.20 |
-11.78%
-$384,336.80
|
|||
| $3,038,817.26 |
-6.84%
-$223,160.74
|
5.6%
$161,176.06
|
||
| $3,098,362.90 |
-5.02%
-$163,615.10
|
7.67%
$220,721.70
|
-1.96%
-$59,545.64
|
|
| $3,751,185.19 |
15%
$489,207.19
|
30.36%
$873,543.99
|
-21.07%
-$652,822.29
|
|
| $3,943,760.00 |
20.9%
$681,782.00
|
37.05%
$1,066,118.80
|
-5.13%
-$192,574.81
|
|
| $4,623,325.50 |
41.73%
$1,361,347.50
|
60.66%
$1,745,684.30
|
-17.23%
-$679,565.50
|
E
Engineer's Estimate
$3,261,978.00
1
Awarded
$2,877,641.20
Over/Under Est:
-11.78%
-$384,336.80
$3,038,817.26
Over/Under Est:
-6.84%
-$223,160.74
Amt Left:
5.6%
$161,176.06
$3,098,362.90
Over/Under Est:
-5.02%
-$163,615.10
Amt Left:
7.67%
$220,721.70
Delta:
-1.96%
-$59,545.64
$3,751,185.19
Over/Under Est:
15%
$489,207.19
Amt Left:
30.36%
$873,543.99
Delta:
-21.07%
-$652,822.29
$3,943,760.00
Over/Under Est:
20.9%
$681,782.00
Amt Left:
37.05%
$1,066,118.80
Delta:
-5.13%
-$192,574.81
$4,623,325.50
Over/Under Est:
41.73%
$1,361,347.50
Amt Left:
60.66%
$1,745,684.30
Delta:
-17.23%
-$679,565.50
Bid Items & Bid Tabulations
56
Total
0 of 56