Job Info for 6309-55-001

County: EL PASO Highway: IH0010 Date: 01/05/2017 (7 years ago) Engineer's Estimate: $623,933 Control Number: 6309-55-001
Project: RMC - 630955001 District: EL PASO Time: 365 CALENDAR DAYS Type: TRAFFIC CONTROL

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $623,932.80
LESNA CONSTRUCTION, INC.   $659,645.00 1
5.72% | $35,712.20
NIXON ENGINEERING   $751,694.00 2
20.48% | $127,761.20
13.95% | $92,049.00
ALLIED PAVING CO.   $823,326.58 3
31.96% | $199,393.78
24.81% | $163,681.58
9.53% | $71,632.58
TOTAL HIGHWAY MAINTENANCE, LLC   $1,672,950.00 4
168.13% | $1,049,017.20
153.61% | $1,013,305.00
103.19% | $849,623.42

Bid Items

Items: 43, 0 filtered
EL PASO IH0010  |  EL PASO  |  6309-55-001  |  01/05/2017  |  $623,933  |  RMC - 630955001  |  TRAF CONTROL  |  365 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate LESNA CONSTRUCTION, INC. NIXON ENGINEERING ALLIED PAVING CO. TOTAL HIGHWAY MAINTENANCE, LLC
500 6001 MOBILIZATION LS 1.000 $23,612.800 $10,000.000 $100,000.000 $60,000.000 $150,000.000
502 6025 BARR, SIGNS, TRAFFIC HANDLING EA 1.000 $10,000.000 $2,000.000 $1,000.000 $6,240.000 $500.000
512 6061 PORT CONC TRAF BAR (STKPL,INSTL&RETRN) LF 600.000 $30.000 $50.000 $1.000 $19.760 $50.000
545 6001 CRASH CUSH ATTEN (INSTL) EA 2.000 $12,000.000 $9,700.000 $1.000 $8,840.000 $15,000.000
545 6002 CRASH CUSH ATTEN (DES SOURCE) EA 2.000 $950.000 $800.000 $1,000.000 $1,560.000 $2,800.000
6055 6001 TMSP RADAR SPEED CONTROL MONITOR EA 5.000 $150.000 $4,500.000 $100.000 $3,000.000 $11,500.000
6185 6001 TMA (STATIONARY) EA 200.000 $100.000 $200.000 $250.000 $287.500 $125.000
6185 6003 TMA (MOBILE OPERATION) HR 1,750.000 $75.000 $58.000 $50.000 $56.350 $85.000
7052 6042 LANE CLOSURE (SETUP AND REMOV)(TY 1) EA 50.000 $80.000 $175.000 $500.000 $260.000 $500.000
7052 6043 LANE CLOSURE (SETUP AND REMOV)(TY 2) EA 125.000 $80.000 $175.000 $400.000 $260.000 $500.000
7052 6044 LANE CLOSURE (SETUP AND REMOV)(TY 3) EA 40.000 $100.000 $175.000 $750.000 $260.000 $550.000
7052 6045 LANE CLOSURE (SETUP AND REMOV)(TY 4) EA 15.000 $120.000 $225.000 $1.000 $286.000 $550.000
7052 6046 LANE CLOSURE (SETUP AND REMOV)(TY 5) EA 105.000 $300.000 $275.000 $500.000 $312.000 $700.000
7052 6047 LANE CLOSURE (SETUP AND REMOV)(TY 6) EA 15.000 $150.000 $400.000 $1.000 $416.000 $750.000
7052 6048 LANE CLOSURE (SETUP AND REMOV)(TY 7) EA 3.000 $200.000 $900.000 $1.000 $624.000 $1,000.000
7052 6049 LANE CLOSURE (SETUP AND REMOV)(TY 8) EA 3.000 $250.000 $1,200.000 $1.000 $832.000 $1,250.000
7052 6050 LANE CLOSURE (SETUP AND REMOV)(TY 9) EA 20.000 $800.000 $150.000 $1.000 $83.200 $500.000
7052 6051 LANE CLOSURE (SETUP AND REMOV)(TY 10) EA 2.000 $1,000.000 $1,200.000 $1.000 $1,144.000 $2,500.000
7052 6052 LANE CLOSURE (SETUP AND REMOV)(TY 11) EA 45.000 $1,000.000 $1,200.000 $300.000 $1,352.000 $3,000.000
7052 6053 LANE CLOSURE (SETUP AND REMOV)(TY 12) EA 45.000 $600.000 $150.000 $300.000 $260.000 $500.000
7052 6054 LANE CLOSURE (SETUP AND REMOV)(TY 13) EA 35.000 $800.000 $200.000 $1.000 $286.000 $550.000
7052 6055 LANE CLOSURE (SETUP AND REMOV)(TY 14) EA 1.000 $800.000 $200.000 $1.000 $286.000 $600.000
7052 6056 LANE CLOSURE (SETUP AND REMOV)(TY 15) EA 1.000 $900.000 $250.000 $1.000 $286.000 $700.000
7052 6057 LANE CLOSURE (SETUP AND REMOV)(TY 16) EA 100.000 $60.000 $75.000 $300.000 $176.800 $500.000
7052 6058 LANE CLOSURE (SETUP AND REMOV)(TY 17) EA 1.000 $800.000 $75.000 $1.000 $176.800 $1,000.000
7052 6059 LANE CLOSURE (MAINTENANCE) (TY 1) HR 300.000 $20.000 $45.000 $100.000 $51.000 $125.000
7052 6060 LANE CLOSURE (MAINTENANCE) (TY 2) HR 750.000 $20.000 $45.000 $100.000 $51.000 $125.000
7052 6061 LANE CLOSURE (MAINTENANCE) (TY 3) HR 240.000 $20.000 $45.000 $50.000 $51.000 $125.000
7052 6062 LANE CLOSURE (MAINTENANCE) (TY 4) HR 90.000 $20.000 $45.000 $1.000 $56.100 $150.000
7052 6063 LANE CLOSURE (MAINTENANCE) (TY 5) HR 630.000 $20.000 $45.000 $50.000 $61.200 $125.000
7052 6064 LANE CLOSURE (MAINTENANCE) (TY 6) HR 90.000 $20.000 $45.000 $1.000 $81.600 $150.000
7052 6065 LANE CLOSURE (MAINTENANCE) (TY 7) HR 18.000 $20.000 $45.000 $1.000 $122.400 $200.000
7052 6066 LANE CLOSURE (MAINTENANCE) (TY 8) HR 18.000 $20.000 $45.000 $1.000 $163.200 $225.000
7052 6067 LANE CLOSURE (MAINTENANCE) (TY 9) HR 120.000 $20.000 $45.000 $50.000 $16.320 $225.000
7052 6068 LANE CLOSURE (MAINTENANCE) (TY 10) HR 12.000 $20.000 $45.000 $1.000 $224.400 $850.000
7052 6069 LANE CLOSURE (MAINTENANCE) (TY 11) HR 270.000 $20.000 $45.000 $50.000 $265.200 $500.000
7052 6070 LANE CLOSURE (MAINTENANCE) (TY 12) HR 270.000 $20.000 $45.000 $50.000 $51.000 $125.000
7052 6071 LANE CLOSURE (MAINTENANCE) (TY 13) HR 225.000 $20.000 $45.000 $50.000 $56.100 $150.000
7052 6072 LANE CLOSURE (MAINTENANCE) (TY 14) HR 6.000 $20.000 $45.000 $1.000 $56.100 $550.000
7052 6073 LANE CLOSURE (MAINTENANCE) (TY 15) HR 6.000 $20.000 $45.000 $1.000 $56.100 $650.000
7052 6074 LANE CLOSURE (MAINTENANCE) (TY 16) HR 600.000 $20.000 $45.000 $25.000 $34.680 $125.000
7052 6075 LANE CLOSURE (MAINTENANCE) (TY 17) HR 6.000 $20.000 $45.000 $1.000 $34.680 $125.000
7052 6076 MOBILE OPERATIONS HR 1,750.000 $80.000 $60.000 $50.000 $56.350 $100.000
Totals: $623,932.80 $659,645.00 $751,694.00 $823,326.58 $1,672,950.00