PREPARING ROW
|
STA
|
426.000
|
$188.600
|
$16,450.000
|
$390.090
|
$12,525.000
|
$18,065.000
|
|
|
REMOVING CONC (PAV)
|
SY
|
8,674.000
|
$9.900
|
$26.000
|
$33.540
|
$25.000
|
$31.350
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
19,232.000
|
$7.000
|
$14.000
|
$11.560
|
$12.000
|
$10.800
|
|
|
REMOVING CONC (MEDIANS)
|
SY
|
49.000
|
$50.000
|
$33.000
|
$17.370
|
$30.000
|
$16.230
|
|
|
REMOVING CONC (CURB)
|
LF
|
9,489.000
|
$3.150
|
$1.500
|
$3.850
|
$3.000
|
$3.600
|
|
|
REMOVING CONC (CURB AND GUTTER)
|
LF
|
204.000
|
$14.000
|
$6.000
|
$5.410
|
$5.000
|
$5.060
|
|
|
REMOVING CONC (CTB)
|
LF
|
13,591.000
|
$10.000
|
$5.500
|
$8.050
|
$7.650
|
$15.090
|
|
|
REMOVING CONC (RETAINING WALLS)
|
SY
|
2,654.000
|
$6.600
|
$12.000
|
$21.200
|
$10.000
|
$19.810
|
|
|
REMOVING CONC (COPING)
|
LF
|
4,043.000
|
$8.000
|
$8.000
|
$8.970
|
$35.000
|
$8.380
|
|
|
REMOVE CONC (RAIL)
|
LF
|
14,145.000
|
$8.000
|
$12.000
|
$15.040
|
$8.300
|
$14.060
|
|
|
REMOVING CONC (FLUME)
|
SY
|
9.000
|
$23.600
|
$115.000
|
$20.310
|
$50.000
|
$18.980
|
|
|
REMOVING STAB BASE AND ASPH PAV(0"-16")
|
SY
|
19,288.000
|
$3.850
|
$4.500
|
$3.700
|
$5.000
|
$5.870
|
|
|
REMOVING STAB BASE & ASPH PAV(12"-27")
|
SY
|
71,097.000
|
$8.000
|
$4.500
|
$4.450
|
$6.000
|
$8.210
|
|
|
REMOV STAB BASE AND ASPH PAV (0"-12")
|
SY
|
2,178.000
|
$20.000
|
$4.000
|
$3.810
|
$5.500
|
$5.350
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
25,893.000
|
$4.600
|
$3.150
|
$6.990
|
$10.000
|
$25.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY A)
|
CY
|
94,619.000
|
$13.500
|
$7.800
|
$8.820
|
$8.300
|
$9.000
|
|
|
FL BS (CMP IN PLC)(TY A GR 5)(6")
|
SY
|
2,190.000
|
$45.000
|
$7.800
|
$8.180
|
$8.000
|
$8.890
|
|
|
CEMENT
|
TON
|
1,446.000
|
$184.100
|
$150.000
|
$177.620
|
$200.000
|
$169.000
|
|
|
CEMENT TREAT (SUBGRADE) (8")
|
SY
|
215,205.000
|
$2.000
|
$2.150
|
$2.770
|
$4.000
|
$2.200
|
|
|
PRIME COAT (AE-P)
|
GAL
|
32,475.000
|
$4.100
|
$4.300
|
$3.670
|
$5.500
|
$5.780
|
|
|
CONC PVMT (CONT REINF - CRCP) (12")
|
SY
|
197,023.000
|
$68.000
|
$35.000
|
$53.500
|
$56.000
|
$75.000
|
|
|
CEM STABIL BKFL
|
CY
|
7,576.270
|
$88.000
|
$59.500
|
$119.610
|
$95.000
|
$81.270
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
16,015.000
|
$2.600
|
$1.400
|
$3.070
|
$1.000
|
$2.720
|
|
|
TEMPORARY SPL SHORING
|
SF
|
61,448.000
|
$8.000
|
$17.000
|
$19.390
|
$23.000
|
$25.050
|
|
|
FOUNDATON LOADTEST(D4945)(DRILLD SHAFT)
|
EA
|
8.000
|
$20,000.000
|
$20,000.000
|
$26,750.000
|
$25,000.000
|
$30,000.000
|
|
|
SOIL NAIL ANCHORS
|
LF
|
2,748.000
|
$16.500
|
$54.000
|
$42.800
|
$50.000
|
$46.550
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
205.000
|
$175.000
|
$135.000
|
$150.370
|
$125.000
|
$108.900
|
|
|
DRILL SHAFT (24 IN)
|
LF
|
210.000
|
$275.000
|
$405.000
|
$180.710
|
$155.000
|
$140.950
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
6,165.000
|
$185.000
|
$225.000
|
$267.080
|
$250.000
|
$226.400
|
|
|
DRILL SHAFT (42 IN)
|
LF
|
3,262.000
|
$260.000
|
$400.000
|
$362.510
|
$325.000
|
$301.170
|
|
|
DRILL SHAFT (48 IN)
|
LF
|
835.000
|
$420.000
|
$520.000
|
$423.260
|
$425.000
|
$390.690
|
|
|
DRILL SHAFT (54 IN)
|
LF
|
490.000
|
$566.650
|
$605.000
|
$504.180
|
$550.000
|
$464.280
|
|
|
DRILL SHAFT (66 IN)
|
LF
|
1,043.000
|
$795.000
|
$850.000
|
$754.290
|
$800.000
|
$713.410
|
|
|
DRILL SHAFT (84 IN)
|
LF
|
792.000
|
$1,100.000
|
$1,180.000
|
$992.720
|
$1,050.000
|
$948.190
|
|
|
DRILL SHAFT (NON - REINFORCED) (12 IN)
|
LF
|
16.000
|
$225.550
|
$365.000
|
$370.760
|
$346.500
|
$346.500
|
|
|
DRILL SHAFT (SIGN MTS) (48 IN)
|
LF
|
474.670
|
$544.600
|
$605.000
|
$615.250
|
$575.000
|
$575.000
|
|
|
DRILL SHAFT (HIGH MAST POLE) (60 IN)
|
LF
|
1,438.000
|
$500.000
|
$625.000
|
$636.650
|
$595.000
|
$595.000
|
|
|
DRILL SHAFT (SIGN MTS) (60 IN)
|
LF
|
173.090
|
$600.000
|
$646.000
|
$658.050
|
$615.000
|
$615.000
|
|
|
CL A CONC (FLUME)
|
CY
|
459.000
|
$700.000
|
$360.000
|
$411.950
|
$350.000
|
$385.000
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
131.100
|
$893.300
|
$785.000
|
$1,122.060
|
$925.000
|
$800.000
|
|
|
CL C CONC (ABUT)(HPC)(EXTEND)
|
CY
|
418.100
|
$1,250.000
|
$1,000.000
|
$1,395.320
|
$1,500.000
|
$950.000
|
|
|
CL C CONC (CAP)(HPC)
|
CY
|
1,161.700
|
$980.000
|
$960.000
|
$1,224.010
|
$1,450.000
|
$1,200.000
|
|
|
CL C CONC (COLUMN)(HPC)
|
CY
|
793.100
|
$870.000
|
$1,130.000
|
$1,134.110
|
$1,200.000
|
$1,500.000
|
|
|
CL C CONC (FOOTING)(HPC)
|
CY
|
52.400
|
$1,000.000
|
$665.000
|
$1,261.760
|
$800.000
|
$650.000
|
|
|
CL C CONC (CRASHWALL)(HPC)
|
CY
|
189.000
|
$750.000
|
$700.000
|
$744.100
|
$500.000
|
$900.000
|
|
|
CL C CONC (COPING)
|
CY
|
333.000
|
$650.000
|
$0.010
|
$411.120
|
$1,050.000
|
$900.000
|
|
|
CL C CONC (RAIL FOUNDATION)
|
CY
|
1,521.000
|
$350.000
|
$200.000
|
$369.430
|
$345.000
|
$450.000
|
|
|
CL C CONC (RAIL FOUNDATION)(HPC)
|
CY
|
43.000
|
$50.000
|
$460.000
|
$547.470
|
$400.000
|
$750.000
|
|
|
REINF CONC SLAB (HPC)
|
SF
|
107,621.000
|
$15.000
|
$18.100
|
$15.830
|
$18.000
|
$15.000
|
|
|
REINF CONC SLAB (EXTEND SLAB)(HPC)
|
SF
|
91,841.000
|
$15.000
|
$27.000
|
$20.620
|
$27.000
|
$22.000
|
|
|
APPROACH SLAB (HPC)
|
CY
|
188.600
|
$467.600
|
$600.000
|
$360.990
|
$525.000
|
$600.000
|
|
|
APPROACH SLAB (EXTEND) (HPC)
|
CY
|
1,011.000
|
$467.600
|
$450.000
|
$361.050
|
$750.000
|
$500.000
|
|
|
RETAINING WALL (MSE)
|
SF
|
74,770.760
|
$40.700
|
$42.000
|
$39.860
|
$41.000
|
$55.000
|
|
|
RETAINING WALL (CONC BLOCK)
|
SF
|
40,968.000
|
$30.000
|
$40.000
|
$32.880
|
$30.000
|
$29.290
|
|
|
RETAINING WALL (SOIL NAIL)(FACIA)
|
SF
|
4,585.000
|
$51.700
|
$65.000
|
$45.170
|
$46.000
|
$65.000
|
|
|
PRESTR CONC U - BEAM (U54)
|
LF
|
4,688.380
|
$200.000
|
$230.000
|
$204.620
|
$225.000
|
$213.460
|
|
|
PRESTR CONC GIRDER (TX28)
|
LF
|
2,634.150
|
$170.000
|
$205.000
|
$214.910
|
$205.000
|
$213.160
|
|
|
PRESTR CONC GIRDER (TX46)
|
LF
|
2,292.870
|
$150.000
|
$210.000
|
$208.610
|
$210.000
|
$219.820
|
|
|
PRESTR CONC GIRDER (TX54)
|
LF
|
14,374.380
|
$140.000
|
$200.000
|
$184.390
|
$215.000
|
$195.590
|
|
|
CONCRETE PAINT FINISH
|
SF
|
25,982.000
|
$0.800
|
$0.320
|
$0.450
|
$0.300
|
$0.310
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
2,381.990
|
$275.100
|
$370.000
|
$347.750
|
$450.000
|
$325.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
1.000
|
$550.150
|
$1,000.000
|
$3,531.000
|
$1,100.000
|
$3,300.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
5.000
|
$800.000
|
$425.000
|
$2,675.000
|
$550.000
|
$2,500.000
|
|
|
RIPRAP (CONC) (CHANNEL) (4IN)
|
CY
|
27.000
|
$700.000
|
$360.000
|
$588.500
|
$700.000
|
$550.000
|
|
|
STR STEEL (MISC NON - BRIDGE)
|
LB
|
350.000
|
$9.900
|
$12.500
|
$10.700
|
$11.500
|
$10.190
|
|
|
RAIL (TY T551)
|
LF
|
60,816.000
|
$44.000
|
$44.000
|
$46.970
|
$45.000
|
$47.250
|
|
|
RAIL (TY T551)(HPC)
|
LF
|
9,795.300
|
$55.000
|
$64.000
|
$51.980
|
$65.000
|
$52.050
|
|
|
RAIL (TY T552)
|
LF
|
2,023.000
|
$75.000
|
$42.000
|
$49.120
|
$55.000
|
$48.800
|
|
|
RAIL (TY C221)
|
LF
|
4,180.000
|
$49.500
|
$64.000
|
$55.740
|
$95.000
|
$80.050
|
|
|
RAIL (TY C221)(HPC)
|
LF
|
2,137.200
|
$52.800
|
$85.000
|
$59.590
|
$105.000
|
$83.200
|
|
|
RAIL (TY T551)(MOD)
|
LF
|
201.000
|
$88.000
|
$545.000
|
$374.720
|
$260.000
|
$369.020
|
|
|
RAIL (TY PR11)
|
LF
|
468.000
|
$150.000
|
$80.000
|
$107.000
|
$70.000
|
$124.580
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
|
LF
|
245.000
|
$104.550
|
$91.000
|
$75.200
|
$115.000
|
$85.490
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
|
LF
|
1,160.000
|
$120.100
|
$102.000
|
$81.110
|
$130.000
|
$99.490
|
|
|
CONC BOX CULV (6 FT X 3 FT)
|
LF
|
1,747.000
|
$339.250
|
$370.000
|
$341.190
|
$365.000
|
$351.960
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
252.000
|
$65.000
|
$36.000
|
$62.430
|
$80.000
|
$300.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
11,545.000
|
$62.000
|
$77.000
|
$80.920
|
$100.000
|
$95.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
669.000
|
$112.450
|
$115.000
|
$132.340
|
$130.000
|
$150.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
244.000
|
$142.850
|
$210.000
|
$158.470
|
$170.000
|
$175.000
|
|
|
RC PIPE (CL III)(48 IN)
|
LF
|
1,225.000
|
$226.550
|
$220.000
|
$219.740
|
$225.000
|
$290.000
|
|
|
RC PIPE (CL V)(24 IN)
|
LF
|
577.000
|
$96.250
|
$135.000
|
$108.610
|
$122.000
|
$200.000
|
|
|
RC PIPE (CL V)(30 IN)
|
LF
|
14.000
|
$129.050
|
$275.000
|
$173.640
|
$175.000
|
$250.000
|
|
|
RC PIPE (ARCH)(CL V)(DES 3)
|
LF
|
383.000
|
$500.000
|
$155.000
|
$239.300
|
$240.000
|
$204.810
|
|
|
MANH (COMPL)(PRM)(48IN)
|
EA
|
10.000
|
$5,000.000
|
$7,700.000
|
$3,435.080
|
$5,200.000
|
$4,000.000
|
|
|
MANH (COMPL)(PRM)(60IN)
|
EA
|
15.000
|
$5,000.000
|
$4,700.000
|
$5,358.730
|
$6,800.000
|
$4,684.340
|
|
|
MANH (COMPL)(PRM)(72IN)
|
EA
|
3.000
|
$8,000.000
|
$4,700.000
|
$7,971.990
|
$9,000.000
|
$5,768.390
|
|
|
JCTBOX(COMPL)(PJB)(3FTX3FT)
|
EA
|
10.000
|
$4,069.750
|
$2,900.000
|
$3,729.310
|
$5,000.000
|
$3,740.570
|
|
|
JCTBOX(COMPL)(PJB)(4FTX4FT)
|
EA
|
1.000
|
$5,019.850
|
$3,600.000
|
$4,059.750
|
$5,500.000
|
$4,528.020
|
|
|
INLET (COMPL)(PCO)(3FT)(LEFT)
|
EA
|
1.000
|
$6,000.000
|
$5,300.000
|
$5,238.570
|
$7,000.000
|
$5,424.530
|
|
|
INLET (COMPL)(PCO)(3FT)(BOTH)
|
EA
|
1.000
|
$6,900.000
|
$5,800.000
|
$5,666.570
|
$7,500.000
|
$5,619.280
|
|
|
INLET (COMPL)(PCO)(4FT)(NONE)
|
EA
|
2.000
|
$5,100.000
|
$5,700.000
|
$5,604.670
|
$7,500.000
|
$6,888.300
|
|
|
INLET (COMPL)(PCO)(4FT)(LEFT)
|
EA
|
6.000
|
$5,700.000
|
$6,200.000
|
$6,080.060
|
$7,800.000
|
$6,496.200
|
|
|
INLET (COMPL)(PCO)(6FT)(RIGHT)
|
EA
|
1.000
|
$7,057.700
|
$8,400.000
|
$8,000.240
|
$10,000.000
|
$9,257.600
|
|
|
INLET (COMPL)(PCO)(6FT)(BOTH)
|
EA
|
3.000
|
$6,871.000
|
$8,900.000
|
$8,439.410
|
$10,500.000
|
$9,330.390
|
|
|
INLET (COMPL)(PMBD)(4FT)
|
EA
|
16.000
|
$6,930.500
|
$7,200.000
|
$6,956.430
|
$8,800.000
|
$7,349.530
|
|
|
INLET (COMPL)(PMBD)(5FT)
|
EA
|
1.000
|
$6,799.000
|
$7,400.000
|
$7,122.840
|
$9,000.000
|
$8,115.600
|
|
|
INLET (COMPL)(POD)(SFG)(4FTX4FT)
|
EA
|
3.000
|
$5,361.650
|
$5,700.000
|
$6,873.410
|
$6,800.000
|
$5,044.940
|
|
|
INLET (COMPL)(POD)(SFG)(3FTX5FT)
|
EA
|
2.000
|
$4,020.250
|
$6,000.000
|
$5,859.330
|
$7,600.000
|
$5,229.600
|
|
|
INLET (COMPL)(PSL)(RC)(3FTX3FT)
|
EA
|
11.000
|
$4,049.800
|
$4,000.000
|
$4,095.150
|
$5,800.000
|
$4,904.680
|
|
|
INLET (COMPL)(PSL)(RC)(4FTX4FT)
|
EA
|
5.000
|
$5,674.950
|
$4,500.000
|
$4,578.720
|
$6,500.000
|
$6,201.990
|
|
|
INLET (COMPL)(PSL)(RC)(5FTX6FT)
|
EA
|
2.000
|
$5,802.650
|
$6,000.000
|
$5,894.640
|
$7,700.000
|
$8,486.200
|
|
|
INLET (COMPL)(PSL)(RC)(8FTX8FT)
|
EA
|
6.000
|
$13,593.600
|
$13,500.000
|
$13,346.590
|
$15,000.000
|
$16,230.590
|
|
|
INLET (COMPL)(PSL)(FG)(4FTX4FT-4FTX4FT)
|
EA
|
2.000
|
$4,472.000
|
$4,900.000
|
$5,063.590
|
$6,800.000
|
$6,523.500
|
|
|
INLET (COMPL)(PSL)(FG)(3FTX5FT-3FTX5FT)
|
EA
|
10.000
|
$4,601.000
|
$6,200.000
|
$6,260.930
|
$8,000.000
|
$7,475.640
|
|
|
INLET(COMPL)(PSL)(SFG)(3FTX3FT-3FTX3FT)
|
EA
|
3.000
|
$3,844.750
|
$4,600.000
|
$4,842.110
|
$6,500.000
|
$6,565.290
|
|
|
INLET(COMPL)(PSL)(SFG)(4FTX4FT-4FTX4FT)
|
EA
|
48.000
|
$5,200.000
|
$5,200.000
|
$5,334.310
|
$7,000.000
|
$5,691.540
|
|
|
INLET(COMPL)(PSL)(SFG)(3FTX5FT-3FTX5FT)
|
EA
|
3.000
|
$4,141.200
|
$6,600.000
|
$6,455.630
|
$8,500.000
|
$6,838.890
|
|
|
SET (TY II) (30 IN) (RCP) (3: 1) (P)
|
EA
|
1.000
|
$2,355.000
|
$7,000.000
|
$3,536.200
|
$3,400.000
|
$2,501.620
|
|
|
GRATE AND FRAME (BRIDGE DRAIN)
|
EA
|
2.000
|
$2,260.400
|
$1,650.000
|
$3,327.550
|
$3,200.000
|
$2,086.510
|
|
|
JACK BOR OR TUN PIPE(24 IN)(RC)(CL V)
|
LF
|
48.000
|
$1,200.000
|
$975.000
|
$1,303.910
|
$1,400.000
|
$1,090.670
|
|
|
ADJUSTING MANHOLES & INLETS
|
EA
|
3.000
|
$1,000.000
|
$2,885.000
|
$1,037.450
|
$3,300.000
|
$888.370
|
|
|
PIPE (PVC) (SCH 40) (6 IN)
|
LF
|
110.000
|
$37.300
|
$25.600
|
$50.120
|
$20.000
|
$3.950
|
|
|
REMOV STR (INLET)
|
EA
|
23.000
|
$660.200
|
$650.000
|
$517.220
|
$800.000
|
$421.230
|
|
|
REMOV STR (MANHOLE)
|
EA
|
6.000
|
$990.250
|
$875.000
|
$532.710
|
$800.000
|
$842.470
|
|
|
REMOV STR (HEADWALL)
|
EA
|
1.000
|
$1,800.000
|
$1,470.000
|
$1,065.210
|
$700.000
|
$4,212.330
|
|
|
REMOV STR (PIPE)
|
LF
|
1,384.000
|
$29.700
|
$11.500
|
$21.490
|
$25.000
|
$32.000
|
|
|
REMOVE STR (JUNCTION BOX)
|
EA
|
17.000
|
$700.000
|
$735.000
|
$1,403.480
|
$610.000
|
$781.290
|
|
|
REMOV STR (DRILL SHAFT)
|
EA
|
2.000
|
$2,500.000
|
$2,100.000
|
$1,024.690
|
$1,500.000
|
$5,169.970
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$6,428,450.000
|
$3,800,000.000
|
$7,256,000.000
|
$8,900,000.000
|
$9,399,669.430
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
40.000
|
$13,000.000
|
$35,000.000
|
$19,927.140
|
$70,000.000
|
$65,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
20.000
|
$31.850
|
$71.000
|
$29.790
|
$45.000
|
$29.040
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
20.000
|
$8.500
|
$29.000
|
$9.130
|
$17.000
|
$10.550
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
400.000
|
$16.300
|
$32.500
|
$18.890
|
$28.000
|
$22.110
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
400.000
|
$6.600
|
$8.400
|
$6.890
|
$6.250
|
$7.370
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
20,022.000
|
$2.600
|
$3.400
|
$2.570
|
$4.750
|
$2.710
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
20,022.000
|
$0.700
|
$1.550
|
$0.640
|
$1.300
|
$0.710
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
1,192.000
|
$4.100
|
$2.800
|
$5.650
|
$5.150
|
$9.960
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
288.000
|
$4.550
|
$4.800
|
$5.910
|
$5.550
|
$2.640
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (18")
|
LF
|
4,178.000
|
$5.800
|
$5.400
|
$6.450
|
$6.000
|
$5.150
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
5,658.000
|
$1.200
|
$0.550
|
$0.960
|
$2.000
|
$1.460
|
|
|
CONSTRUCTING DETOURS
|
SY
|
5,506.000
|
$35.000
|
$40.000
|
$41.070
|
$45.000
|
$44.270
|
|
|
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
|
LF
|
28,230.000
|
$8.500
|
$3.750
|
$5.440
|
$2.750
|
$7.850
|
|
|
PORT CTB (DES SOURCE)(LOW PROF)(TY 1)
|
LF
|
5,320.000
|
$8.000
|
$5.500
|
$5.360
|
$6.000
|
$12.480
|
|
|
PORT CTB (DES SOURCE)(LOW PROF)(TY 2)
|
LF
|
520.000
|
$20.000
|
$20.000
|
$5.360
|
$5.000
|
$17.180
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
104,687.000
|
$4.900
|
$4.750
|
$4.360
|
$1.700
|
$1.640
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
10,380.000
|
$4.900
|
$4.700
|
$4.350
|
$2.000
|
$2.540
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
320.000
|
$4.900
|
$29.500
|
$5.110
|
$1.850
|
$8.300
|
|
|
PORT CTB (STKPL)(F-SHAPE)(TY 1)
|
LF
|
25,830.000
|
$8.000
|
$4.500
|
$5.220
|
$4.000
|
$6.240
|
|
|
PORT CTB (STKPL)(LOW PROF)(TY 1)
|
LF
|
7,640.000
|
$8.000
|
$4.000
|
$5.150
|
$4.250
|
$7.230
|
|
|
PORT CTB (STKPL)(LOW PROF)(TY 2)
|
LF
|
620.000
|
$8.000
|
$16.000
|
$5.150
|
$4.000
|
$10.290
|
|
|
PERM CTB (F-SHAPE) (TY 1)
|
LF
|
7,299.000
|
$100.000
|
$75.000
|
$55.640
|
$90.000
|
$61.580
|
|
|
PERM CTB (F-SHAPE) (TY 3)
|
LF
|
507.000
|
$350.000
|
$110.000
|
$257.870
|
$180.000
|
$90.490
|
|
|
CONC CURB (MONO) (TY II)
|
LF
|
5,652.000
|
$6.400
|
$8.000
|
$9.630
|
$6.000
|
$9.000
|
|
|
CONC CURB & GUTTER (TY II)
|
LF
|
1,006.000
|
$30.000
|
$12.800
|
$22.470
|
$18.000
|
$21.000
|
|
|
DRIVEWAYS (CONC) (FAST TRACK)
|
SY
|
1,284.000
|
$70.000
|
$75.000
|
$80.250
|
$73.000
|
$75.000
|
|
|
CONC SIDEWALKS (5")
|
SY
|
4,197.000
|
$53.000
|
$54.000
|
$42.800
|
$56.000
|
$40.000
|
|
|
CURB RAMPS (TY 1)
|
EA
|
1.000
|
$1,117.500
|
$1,940.000
|
$2,247.000
|
$1,100.000
|
$2,100.000
|
|
|
CURB RAMPS (TY 2)
|
EA
|
6.000
|
$1,540.600
|
$2,100.000
|
$2,247.000
|
$1,500.000
|
$2,100.000
|
|
|
CURB RAMPS (TY 3)
|
EA
|
2.000
|
$1,047.550
|
$2,100.000
|
$3,424.000
|
$1,300.000
|
$3,200.000
|
|
|
CONC MEDIAN
|
SY
|
211.000
|
$80.000
|
$79.000
|
$67.950
|
$51.000
|
$63.500
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
150.000
|
$40.000
|
$26.000
|
$57.250
|
$26.000
|
$53.500
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
1,405.000
|
$45.000
|
$31.000
|
$37.450
|
$31.000
|
$35.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
5.000
|
$2,145.550
|
$2,050.000
|
$2,675.000
|
$2,100.000
|
$2,500.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
6.000
|
$1,500.000
|
$1,575.000
|
$1,926.000
|
$1,550.000
|
$1,800.000
|
|
|
MTL THRIE-BEAM GD FEN (STEEL POST)
|
EA
|
6.000
|
$2,500.000
|
$2,625.000
|
$2,568.000
|
$2,600.000
|
$2,400.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
6,928.000
|
$2.000
|
$4.200
|
$6.420
|
$4.250
|
$6.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
29.000
|
$291.600
|
$525.000
|
$451.250
|
$525.000
|
$421.730
|
|
|
REMOVE DOWNSTREAM ANCHOR TERMINAL
|
EA
|
3.000
|
$40.000
|
$420.000
|
$451.250
|
$425.000
|
$421.730
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
2.000
|
$275.100
|
$525.000
|
$435.490
|
$525.000
|
$294.630
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
13.000
|
$3,520.900
|
$3,150.000
|
$3,531.000
|
$3,050.000
|
$3,300.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
26.000
|
$400.000
|
$525.000
|
$428.000
|
$525.000
|
$704.320
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
59.000
|
$1,500.000
|
$850.000
|
$1,284.000
|
$900.000
|
$1,200.000
|
|
|
CRASH CUSH ATTEN (STKPL)
|
EA
|
29.000
|
$1,000.000
|
$360.000
|
$1,177.000
|
$1,500.000
|
$1,100.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
1.000
|
$800.000
|
$600.000
|
$3,210.000
|
$1,225.000
|
$3,000.000
|
|
|
CRASH CUSH ATTEN (INSTL)(R)(N)(TL3)
|
EA
|
5.000
|
$9,900.000
|
$22,000.000
|
$24,610.000
|
$20,500.000
|
$23,000.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
27.000
|
$8,500.000
|
$7,800.000
|
$10,700.000
|
$6,600.000
|
$10,000.000
|
|
|
PIPE UNDERDRAINS (TY 6) (6")
|
LF
|
8,846.000
|
$17.500
|
$10.000
|
$15.730
|
$17.000
|
$14.040
|
|
|
PIPE UNDERDRAINS (TY 9)(4")
|
LF
|
2,950.000
|
$18.200
|
$8.750
|
$13.710
|
$11.000
|
$14.670
|
|
|
REMOVE RD IL ASM (BRIDGE MOUNT)
|
EA
|
12.000
|
$425.000
|
$420.000
|
$428.000
|
$400.000
|
$400.000
|
|
|
REMOVE RD IL ASM (TRANS-BASE)
|
EA
|
155.000
|
$350.000
|
$1,150.000
|
$1,177.000
|
$1,100.000
|
$1,100.000
|
|
|
REMOVE RD IL ASM (U/P)
|
EA
|
64.000
|
$300.000
|
$310.000
|
$315.650
|
$295.000
|
$295.000
|
|
|
REPLACE LUMINAIRE W/LED (150W EQ)
|
EA
|
2.000
|
$1,705.450
|
$2,150.000
|
$2,193.500
|
$2,050.000
|
$2,050.000
|
|
|
IN RD IL (U/P) (TY 1) (150W EQ) LED
|
EA
|
3.000
|
$3,288.750
|
$3,400.000
|
$3,477.500
|
$3,250.000
|
$3,250.000
|
|
|
IN RD IL (U/P) (TY 2) (150W EQ) LED
|
EA
|
69.000
|
$2,100.000
|
$3,450.000
|
$3,541.700
|
$3,310.000
|
$3,310.000
|
|
|
HI MST IL POLE (125 FT)( 80 MPH)
|
EA
|
1.000
|
$30,000.000
|
$39,500.000
|
$40,615.060
|
$38,000.000
|
$37,958.000
|
|
|
HI MST IL POLE (150 FT)( 80 MPH)
|
EA
|
44.000
|
$24,000.000
|
$44,000.000
|
$44,933.260
|
$42,000.000
|
$41,993.700
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
29,670.000
|
$15.000
|
$16.200
|
$16.590
|
$15.500
|
$15.500
|
|
|
CONDT (PVC) (SCH 40) (2") (BORE)
|
LF
|
7,080.000
|
$25.000
|
$30.000
|
$30.500
|
$28.500
|
$28.500
|
|
|
CONDT (PVC) (SCH 40) (3")
|
LF
|
350.000
|
$25.000
|
$30.000
|
$19.800
|
$28.650
|
$28.650
|
|
|
CONDT (PVC) (SCH 80) (2") (BORE)
|
LF
|
1,925.000
|
$25.000
|
$36.000
|
$37.450
|
$35.000
|
$35.000
|
|
|
CONDT (PVC) (SCH 80) (3") (BORE)
|
LF
|
430.000
|
$35.000
|
$40.000
|
$41.200
|
$38.500
|
$38.500
|
|
|
CONDT (RM) (3/4")
|
LF
|
4,240.000
|
$30.100
|
$15.500
|
$16.050
|
$15.000
|
$15.000
|
|
|
CONDT (RM) (2")
|
LF
|
45.000
|
$22.000
|
$31.000
|
$31.620
|
$29.550
|
$29.550
|
|
|
ELEC CONDR (NO.14) INSULATED
|
LF
|
5,018.000
|
$1.500
|
$1.650
|
$1.660
|
$1.550
|
$1.550
|
|
|
ELEC CONDR (NO.12) INSULATED
|
LF
|
13,605.000
|
$2.000
|
$1.950
|
$1.980
|
$1.850
|
$1.850
|
|
|
ELEC CONDR (NO.8) INSULATED
|
LF
|
87,720.000
|
$1.800
|
$3.500
|
$3.600
|
$3.360
|
$3.360
|
|
|
ELEC CONDR (NO.6) INSULATED
|
LF
|
47,335.000
|
$2.300
|
$4.100
|
$4.230
|
$3.950
|
$3.950
|
|
|
ELEC CONDR (NO.4) INSULATED
|
LF
|
2,385.000
|
$2.300
|
$4.500
|
$4.550
|
$4.250
|
$4.250
|
|
|
ELEC CONDR (NO.2) INSULATED
|
LF
|
6,345.000
|
$2.900
|
$5.300
|
$5.510
|
$5.150
|
$5.150
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
201.000
|
$950.000
|
$1,550.000
|
$1,581.460
|
$1,478.000
|
$1,478.000
|
|
|
GROUND BOX TY 1 (122422)W/APRON
|
EA
|
18.000
|
$1,000.000
|
$5,800.000
|
$5,983.440
|
$5,592.000
|
$5,592.000
|
|
|
GROUND BOX TY 2 (243636)W/APRON
|
EA
|
2.000
|
$1,200.000
|
$7,900.000
|
$8,214.390
|
$7,677.000
|
$7,677.000
|
|
|
REMOVE GROUND BOX
|
EA
|
32.000
|
$160.000
|
$210.000
|
$208.650
|
$195.000
|
$195.000
|
|
|
REMOVE ELECTRICAL SERVICES
|
EA
|
7.000
|
$1,375.400
|
$1,340.000
|
$1,337.500
|
$1,250.000
|
$1,250.000
|
|
|
ELC SRV TY A 240/480 060(NS)SS(E)GC(O)
|
EA
|
8.000
|
$7,000.000
|
$8,100.000
|
$8,476.540
|
$7,922.000
|
$7,922.000
|
|
|
ELC SRV TY A 240/480 100(NS)SS(E)GC(O)
|
EA
|
3.000
|
$8,000.000
|
$7,700.000
|
$8,068.870
|
$7,541.000
|
$7,541.000
|
|
|
ELC SRV TY D 120/240 060(NS)GS(N)GC(O)
|
EA
|
2.000
|
$7,250.000
|
$7,160.000
|
$7,491.070
|
$7,001.000
|
$7,001.000
|
|
|
ELC SRV TY D 120/240 100(NS)GS(N)GC(O)
|
EA
|
1.000
|
$8,000.000
|
$7,160.000
|
$7,491.070
|
$7,001.000
|
$7,001.000
|
|
|
ELC SRV TY D 120/240 125(NS)GS(N)GC(O)
|
EA
|
1.000
|
$8,500.000
|
$9,150.000
|
$9,580.780
|
$8,954.000
|
$8,954.000
|
|
|
ELC SRV TY D 120/240 125(NS)GS(N)GC(U)
|
EA
|
1.000
|
$5,000.000
|
$12,950.000
|
$13,555.830
|
$12,669.000
|
$12,669.000
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
123.000
|
$35.000
|
$39.900
|
$41.430
|
$38.720
|
$38.720
|
|
|
ALUMINUM SIGNS (TY G)
|
SF
|
82.500
|
$43.550
|
$42.900
|
$44.600
|
$41.680
|
$41.680
|
|
|
ALUMINUM SIGNS (TY O)
|
SF
|
5,935.000
|
$25.000
|
$47.300
|
$49.120
|
$45.910
|
$45.910
|
|
|
REPLACE EXISTING ALUMINUM SIGNS(TY A)
|
SF
|
9.000
|
$70.000
|
$46.350
|
$48.150
|
$45.000
|
$45.000
|
|
|
REPLACE EXISTING ALUMINUM SIGNS(TY O)
|
SF
|
1,361.250
|
$40.000
|
$47.300
|
$49.120
|
$45.910
|
$45.910
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
15.000
|
$878.000
|
$738.000
|
$767.190
|
$717.000
|
$717.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
11.000
|
$961.650
|
$918.000
|
$954.440
|
$892.000
|
$892.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
1.000
|
$750.000
|
$1,190.000
|
$1,236.920
|
$1,156.000
|
$1,156.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P)
|
EA
|
4.000
|
$1,026.550
|
$1,010.000
|
$1,048.600
|
$980.000
|
$980.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
5.000
|
$1,159.700
|
$717.000
|
$744.720
|
$696.000
|
$696.000
|
|
|
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
|
EA
|
6.000
|
$2,500.000
|
$4,100.000
|
$2,530.550
|
$3,981.000
|
$3,981.000
|
|
|
IN BRIDGE MNT CLEARANCE SGN ASSM(TY S)
|
EA
|
7.000
|
$3,286.550
|
$4,115.000
|
$2,859.040
|
$3,997.000
|
$3,997.000
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
1.000
|
$700.000
|
$612.000
|
$636.650
|
$595.000
|
$595.000
|
|
|
RELOCATE SM RD SN SUP&AM TY S80
|
EA
|
1.000
|
$385.000
|
$630.000
|
$654.840
|
$612.000
|
$612.000
|
|
|
RELOCATE SM RD SN SUP&AM(RAIL MOUNT)
|
EA
|
1.000
|
$3,645.000
|
$3,140.000
|
$3,263.500
|
$3,050.000
|
$3,050.000
|
|
|
RELOCATE SM RD SN SUP&AM(SIGN ONLY)
|
EA
|
2.000
|
$300.000
|
$540.000
|
$561.750
|
$525.000
|
$525.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
25.000
|
$137.500
|
$129.000
|
$133.750
|
$125.000
|
$125.000
|
|
|
REMOVE BRDG MNT CLEARANCE SIGN ASSM
|
EA
|
2.000
|
$250.000
|
$995.000
|
$1,033.620
|
$966.000
|
$966.000
|
|
|
REMOVE SM RD SN SUP&AM (SIGN ONLY)
|
EA
|
1.000
|
$70.000
|
$98.000
|
$101.650
|
$95.000
|
$95.000
|
|
|
INSTALL LRSS (STRUCT STEEL)
|
LB
|
632.800
|
$8.050
|
$9.950
|
$10.400
|
$9.720
|
$9.720
|
|
|
REMOVE LRSA
|
EA
|
3.000
|
$2,000.000
|
$3,030.000
|
$3,174.200
|
$2,966.540
|
$2,966.540
|
|
|
RELOCATE LRSS (SIGN ONLY)
|
EA
|
2.000
|
$1,600.000
|
$1,590.000
|
$1,663.100
|
$1,544.300
|
$1,554.300
|
|
|
INS OH SN SUP(30 FT BAL TEE)
|
EA
|
4.000
|
$25,000.000
|
$32,250.000
|
$33,758.500
|
$31,550.000
|
$31,550.000
|
|
|
INS OH SN SUP(35 FT CANT)(CIRC TUBE)
|
EA
|
1.000
|
$70,000.000
|
$102,000.000
|
$106,144.000
|
$99,200.000
|
$99,200.000
|
|
|
INS OH SN SUP(40 FT CANT)(CIRC TUBE)
|
EA
|
3.000
|
$80,000.000
|
$140,000.000
|
$145,991.870
|
$136,441.000
|
$136,441.000
|
|
|
INS OH SN SUP(80 FT BRDG)(CIRC TUBE)
|
EA
|
2.000
|
$125,000.000
|
$244,000.000
|
$255,137.600
|
$238,447.000
|
$238,446.350
|
|
|
INS OH SN SUP(95 FT BRDG)(CIRC TUBE)
|
EA
|
1.000
|
$135,000.000
|
$294,000.000
|
$306,380.590
|
$286,337.000
|
$286,337.000
|
|
|
INS OH SN SUP(145 FT BRDG (CIRC TUBE)
|
EA
|
1.000
|
$360,000.000
|
$339,000.000
|
$354,043.740
|
$330,882.000
|
$330,882.000
|
|
|
INS OH SN SUP(155 FT BRDG)(CIRC TUBE)
|
EA
|
1.000
|
$380,000.000
|
$400,000.000
|
$418,964.710
|
$391,556.000
|
$391,555.800
|
|
|
REMOVE OVERHD SIGN SUP
|
EA
|
9.000
|
$13,812.900
|
$12,750.000
|
$13,375.000
|
$12,500.000
|
$12,500.000
|
|
|
REMOVE OVERHD SIGN SUP (SIGN ONLY)
|
EA
|
2.000
|
$810.000
|
$1,050.000
|
$1,096.750
|
$1,025.000
|
$1,025.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
|
EA
|
130.000
|
$27.400
|
$22.250
|
$19.770
|
$50.000
|
$26.770
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
|
EA
|
116.000
|
$23.500
|
$20.700
|
$19.780
|
$20.000
|
$35.950
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
|
EA
|
21.000
|
$33.900
|
$28.950
|
$19.770
|
$30.000
|
$44.380
|
|
|
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
|
EA
|
3.000
|
$35.200
|
$24.400
|
$19.740
|
$35.000
|
$50.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
|
LF
|
3,580.000
|
$0.350
|
$0.460
|
$0.270
|
$0.480
|
$0.250
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
34,000.000
|
$0.650
|
$0.460
|
$0.270
|
$0.480
|
$0.250
|
|
|
WK ZN PAV MRK NON-REMOV (W)8"(DOT)
|
LF
|
385.000
|
$0.950
|
$0.670
|
$0.540
|
$0.680
|
$0.500
|
|
|
WK ZN PAV MRK NON-REMOV (W)(ARROW)
|
EA
|
22.000
|
$60.000
|
$77.250
|
$48.150
|
$80.000
|
$45.000
|
|
|
WK ZN PAV MRK NON-REMOV(W)(WORD)
|
EA
|
13.000
|
$60.000
|
$77.250
|
$48.150
|
$80.000
|
$45.000
|
|
|
WK ZN PAV MRK NON-REMOV(W)36"(YLD TRI)
|
EA
|
6.000
|
$40.000
|
$20.600
|
$23.540
|
$22.000
|
$22.000
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
29,985.000
|
$0.650
|
$0.510
|
$0.270
|
$0.550
|
$0.250
|
|
|
WK ZN PAV MRK REMOV (W)4"(BRK)
|
LF
|
27,550.000
|
$1.100
|
$0.950
|
$1.410
|
$1.000
|
$1.320
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
147,919.000
|
$1.100
|
$0.950
|
$1.410
|
$1.000
|
$1.320
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
121,350.000
|
$1.300
|
$0.950
|
$1.410
|
$1.000
|
$1.320
|
|
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
|
LF
|
120.000
|
$2.000
|
$1.550
|
$0.800
|
$1.550
|
$0.750
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
2,208.000
|
$1.000
|
$0.880
|
$0.910
|
$0.900
|
$0.850
|
|
REFL PAV MRK TY I (W)12"(LNDP)(100MIL)
|
LF
|
3,189.000
|
$3.000
|
$3.150
|
$2.410
|
$3.100
|
$2.250
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
4,517.000
|
$3.000
|
$3.650
|
$2.510
|
$3.600
|
$2.350
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
50.000
|
$6.350
|
$7.350
|
$4.550
|
$7.150
|
$4.250
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
7.000
|
$104.200
|
$142.000
|
$77.040
|
$140.000
|
$72.000
|
|
REFL PAV MRK TY I(W)(DBL ARROW)(100MIL)
|
EA
|
2.000
|
$187.000
|
$184.000
|
$101.650
|
$180.000
|
$95.000
|
|
REFL PAV MRK TY I(W)(UTURN ARW)(100MIL)
|
EA
|
2.000
|
$177.000
|
$263.000
|
$133.750
|
$260.000
|
$125.000
|
|
REFL PAV MRK TY I(W)(LNDP ARW)(100MIL)
|
EA
|
10.000
|
$100.000
|
$347.000
|
$133.750
|
$340.000
|
$125.000
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
14.000
|
$150.000
|
$142.000
|
$77.040
|
$140.000
|
$72.000
|
|
REFL PAV MRK TY I(W)(ENTR GORE)(100MIL)
|
EA
|
14.000
|
$863.000
|
$762.000
|
$1,605.000
|
$740.000
|
$1,500.000
|
|
REFL PAV MRK TY I(W)(EXIT GORE)(100MIL)
|
EA
|
15.000
|
$854.900
|
$660.000
|
$1,284.000
|
$640.000
|
$1,200.000
|
|
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
|
EA
|
8.000
|
$46.550
|
$42.000
|
$37.450
|
$41.000
|
$35.000
|
|
REFL PAV MRK TY I (W)(BIKE ARW)(100MIL)
|
EA
|
2.000
|
$200.000
|
$142.000
|
$133.750
|
$140.000
|
$12.000
|
|
REFL PAV MRK TY I(W)(BIKE SYML)(100MIL)
|
EA
|
2.000
|
$300.000
|
$205.000
|
$240.750
|
$200.000
|
$225.000
|
|
REFL PAV MRK TY I (W)(BIKE DOT)(100MIL)
|
EA
|
64.000
|
$300.000
|
$3.150
|
$1.130
|
$3.100
|
$1.050
|
|
RE PV MRK TY I(BLACK)6"(SHADOW)(100MIL)
|
LF
|
36,280.000
|
$0.500
|
$0.790
|
$1.020
|
$0.800
|
$0.950
|
|
REFL PAV MRK TY II (W) 4" (DOT)
|
LF
|
120.000
|
$1.500
|
$1.050
|
$0.190
|
$1.050
|
$0.180
|
|
REFL PAV MRK TY II (W) 4" (SLD)
|
LF
|
56,154.000
|
$0.150
|
$0.260
|
$0.190
|
$0.280
|
$0.180
|
|
REFL PAV MRK TY II (W) 6" (BRK)
|
LF
|
41,900.000
|
$0.300
|
$0.360
|
$0.320
|
$0.380
|
$0.300
|
|
REFL PAV MRK TY II (W) 8" (SLD)
|
LF
|
2,208.000
|
$1.500
|
$0.470
|
$0.430
|
$0.480
|
$0.400
|
|
REFL PAV MRK TY II (W) 12" (LNDP)
|
LF
|
3,189.000
|
$1.300
|
$1.480
|
$0.700
|
$1.450
|
$0.650
|
|
REFL PAV MRK TY II (W) 12" (SLD)
|
LF
|
4,517.000
|
$1.700
|
$1.700
|
$1.180
|
$1.700
|
$1.100
|
|
REFL PAV MRK TY II (W) 24" (SLD)
|
LF
|
50.000
|
$3.400
|
$3.700
|
$3.210
|
$3.600
|
$3.000
|
|
REFL PAV MRK TY II (W) (ARROW)
|
EA
|
15.000
|
$80.000
|
$68.500
|
$40.660
|
$70.000
|
$38.000
|
|
REFL PAV MRK TY II (W) (DBL ARROW)
|
EA
|
2.000
|
$138.000
|
$90.000
|
$85.600
|
$90.000
|
$80.000
|
|
REFL PAV MRK TY II (W) (UTURN ARROW)
|
EA
|
2.000
|
$110.000
|
$126.000
|
$85.600
|
$125.000
|
$80.000
|
|
REFL PAV MRK TY II (W) (LNDP ARW)
|
EA
|
2.000
|
$35.000
|
$147.000
|
$90.950
|
$145.000
|
$85.000
|
|
REFL PAV MRK TY II (W) (WORD)
|
EA
|
14.000
|
$66.200
|
$79.000
|
$42.800
|
$80.000
|
$40.000
|
|
REFL PAV MRK TY II (W) (ENTR GORE)
|
EA
|
14.000
|
$273.200
|
$520.000
|
$508.250
|
$510.000
|
$475.000
|
|
REFL PAV MRK TY II (W) (EXIT GORE)
|
EA
|
15.000
|
$275.000
|
$415.000
|
$358.450
|
$405.000
|
$335.000
|
|
REFL PAV MRK TY II (W) 36" (YLD TRI)
|
EA
|
8.000
|
$18.950
|
$26.250
|
$19.260
|
$26.000
|
$18.000
|
|
REFL PAV MRK TY II (W) (BIKE ARROW)
|
EA
|
2.000
|
$125.000
|
$52.500
|
$58.850
|
$55.000
|
$55.000
|
|
REFL PAV MRK TY II (W) (BIKE SYMBOL)
|
EA
|
2.000
|
$125.000
|
$68.250
|
$54.570
|
$70.000
|
$51.000
|
|
REFL PAV MRK TY II (W) (BIKE DOT)
|
EA
|
64.000
|
$200.000
|
$2.100
|
$1.340
|
$2.100
|
$1.250
|
|
REFL PAV MRK TY II (Y) 4" (SLD)
|
LF
|
81,504.000
|
$0.150
|
$0.320
|
$0.270
|
$0.320
|
$0.250
|
|
REFL PAV MRK TY II (BLACK) 6"(SHADOW)
|
LF
|
36,280.000
|
$0.500
|
$0.230
|
$0.320
|
$0.240
|
$0.300
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
794.000
|
$3.000
|
$0.580
|
$0.590
|
$0.600
|
$0.550
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
|
LF
|
41,900.000
|
$0.500
|
$0.740
|
$0.800
|
$0.750
|
$0.750
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
1,335.000
|
$2.500
|
$0.680
|
$0.590
|
$0.700
|
$0.550
|
|
|
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
|
LF
|
55,360.000
|
$0.600
|
$0.880
|
$0.730
|
$0.880
|
$0.680
|
|
|
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
|
LF
|
81,006.000
|
$0.800
|
$0.840
|
$0.730
|
$0.850
|
$0.680
|
|
REFL PAV MRKR TY I-R
|
EA
|
56.000
|
$6.050
|
$2.900
|
$3.160
|
$2.850
|
$2.950
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
3,004.000
|
$3.300
|
$2.900
|
$3.160
|
$2.850
|
$2.950
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
108,294.000
|
$0.500
|
$0.680
|
$0.510
|
$0.700
|
$0.480
|
|
|
ELIM EXT PAV MRK & MRKS (6")
|
LF
|
20,945.000
|
$0.500
|
$0.780
|
$0.590
|
$0.800
|
$0.550
|
|
|
ELIM EXT PAV MRK & MRKS (8")
|
LF
|
1,445.000
|
$1.000
|
$0.900
|
$0.700
|
$0.900
|
$0.650
|
|
|
ELIM EXT PAV MRK & MRKS (12")
|
LF
|
148.000
|
$2.250
|
$2.100
|
$2.300
|
$2.100
|
$2.150
|
|
|
ELIM EXT PAV MRK & MRKS (24")
|
LF
|
100.000
|
$3.750
|
$3.700
|
$4.550
|
$3.600
|
$4.250
|
|
|
ELIM EXT PAV MRK & MRKS (ARROW)
|
EA
|
4.000
|
$92.700
|
$105.000
|
$85.600
|
$105.000
|
$80.000
|
|
|
ELIM EXT PAV MRK & MRKS (DBL ARROW)
|
EA
|
2.000
|
$150.000
|
$132.000
|
$133.750
|
$130.000
|
$125.000
|
|
|
ELIM EXT PAV MRK & MRKS (WORD)
|
EA
|
3.000
|
$29.100
|
$105.000
|
$85.600
|
$105.000
|
$80.000
|
|
|
ELIM EXT PAV MRK & MRKS (ENTR GORE)
|
EA
|
10.000
|
$600.000
|
$710.000
|
$1,070.000
|
$700.000
|
$1,000.000
|
|
|
ELIM EXT PAV MRK & MRKS (EXIT GORE)
|
EA
|
10.000
|
$600.000
|
$578.000
|
$856.000
|
$575.000
|
$800.000
|
|
|
ELIM EXT PAV MRK & MRKS (UTURN ARROW)
|
EA
|
2.000
|
$75.000
|
$158.000
|
$214.000
|
$160.000
|
$200.000
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
136,197.000
|
$0.100
|
$0.130
|
$0.160
|
$0.130
|
$0.150
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
78,180.000
|
$0.100
|
$0.160
|
$0.160
|
$0.160
|
$0.150
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
1,863.000
|
$0.150
|
$0.210
|
$0.210
|
$0.210
|
$0.200
|
|
|
PAV SURF PREP FOR MRK (12")
|
LF
|
7,412.000
|
$0.300
|
$0.320
|
$0.770
|
$0.320
|
$0.720
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
50.000
|
$0.550
|
$1.050
|
$3.870
|
$1.050
|
$3.620
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
16.000
|
$22.000
|
$21.000
|
$48.150
|
$22.000
|
$45.000
|
|
|
PAV SURF PREP FOR MRK (DBL ARROW)
|
EA
|
2.000
|
$88.000
|
$26.250
|
$64.200
|
$26.000
|
$60.000
|
|
|
PAV SURF PREP FOR MRK (UTURN ARR)
|
EA
|
2.000
|
$121.050
|
$26.250
|
$74.900
|
$26.000
|
$70.000
|
|
|
PAV SURF PREP FOR MRK (WORD)
|
EA
|
13.000
|
$22.000
|
$21.000
|
$42.800
|
$22.000
|
$40.000
|
|
|
PAV SURF PREP FOR MRK (ENTR GORE)
|
EA
|
12.000
|
$253.100
|
$157.500
|
$326.350
|
$155.000
|
$305.000
|
|
|
PAV SURF PREP FOR MRK (EXIT GORE)
|
EA
|
15.000
|
$187.100
|
$194.250
|
$262.150
|
$190.000
|
$245.000
|
|
|
PAV SURF PREP FOR MRK (36")(YLD TRI)
|
EA
|
8.000
|
$33.000
|
$5.250
|
$16.050
|
$5.150
|
$15.000
|
|
|
PAV SURF PREP FOR MRK (BIKE SYMBOL)
|
EA
|
1.000
|
$50.000
|
$15.750
|
$55.640
|
$16.000
|
$52.000
|
|
|
PAV SURF PREP FOR MRK (BIKE WORD)
|
EA
|
1.000
|
$25.000
|
$15.750
|
$55.640
|
$16.000
|
$52.000
|
|
|
PAV SURF PREP FOR MRK (BIKE DOT)
|
EA
|
32.000
|
$5.000
|
$5.250
|
$0.640
|
$5.250
|
$0.600
|
|
|
LOOSE AGGR FOR GROUNDCOVER (TYPE II)
|
CY
|
3,322.000
|
$90.000
|
$20.000
|
$80.250
|
$65.000
|
$56.060
|
|
|
RMV, STCKPL, CLEAN, RELAY LOOSE AGGRGT
|
STA
|
58.000
|
$278.150
|
$2,950.000
|
$557.600
|
$5,000.000
|
$361.020
|
|
|
D-GR HMA TY-D PG64-22
|
TON
|
46,347.000
|
$78.000
|
$56.000
|
$75.480
|
$67.400
|
$69.590
|
|
|
TACK COAT
|
GAL
|
31,437.000
|
$3.000
|
$3.650
|
$4.260
|
$4.500
|
$4.210
|
|
|
SP MIXES SP-B PG64-22
|
TON
|
3,474.000
|
$80.000
|
$80.000
|
$74.700
|
$70.000
|
$74.500
|
|
|
SP MIXES SP-C SAC-A PG70-22
|
TON
|
645.000
|
$85.000
|
$120.000
|
$79.270
|
$98.000
|
$98.430
|
|
|
TACK COAT
|
GAL
|
2,813.000
|
$3.000
|
$8.500
|
$4.260
|
$4.500
|
$4.250
|
|
|
TIP TESTING(DRILL SHAFT)
|
EA
|
16.000
|
$8,000.000
|
$4,935.000
|
$5,029.000
|
$8,000.000
|
$7,500.000
|
|
|
ASBESTOS ABATEMENT (OTHER)
|
LF
|
858.000
|
$58.000
|
$23.500
|
$16.350
|
$15.000
|
$15.280
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$8,700.000
|
$7,500.000
|
$10,700.000
|
$15,000.000
|
$17,500.000
|
|
|
ITS SYSTEM SUPPORT EQUIPMENT
|
LS
|
1.000
|
$100,000.000
|
$132,000.000
|
$133,750.000
|
$125,000.000
|
$125,000.000
|
|
|
FIBER OPTIC PIGTAIL (12 FIBER)
|
LF
|
10,637.000
|
$5.000
|
$12.500
|
$13.080
|
$12.220
|
$12.220
|
|
|
FIBER OPTIC SPLICE ENCLOSURE
|
EA
|
6.000
|
$2,000.000
|
$4,450.000
|
$4,659.850
|
$4,355.000
|
$4,355.000
|
|
|
FIBER OPTIC PATCH PANEL (12 POSITION)
|
EA
|
20.000
|
$2,000.000
|
$3,860.000
|
$4,048.880
|
$3,784.000
|
$3,784.000
|
|
|
FIBER OPTIC CABLE ROAD MARKER
|
EA
|
21.000
|
$200.000
|
$435.000
|
$454.750
|
$425.000
|
$425.000
|
|
|
FIBER OPTIC PATCH PANEL (144 POSITION)
|
EA
|
4.000
|
$8,000.000
|
$5,915.000
|
$6,187.810
|
$5,783.000
|
$5,738.000
|
|
|
FIBER OPTIC FUSION SPLICE
|
EA
|
150.000
|
$75.000
|
$67.600
|
$70.730
|
$66.100
|
$66.100
|
|
|
RELOCATE FIBER OPTIC CABLE
|
LF
|
125.000
|
$10.000
|
$10.000
|
$10.460
|
$9.780
|
$9.780
|
|
|
REMOVE FIBER OPTIC CABLE
|
LF
|
2,822.000
|
$3.000
|
$2.050
|
$2.160
|
$2.020
|
$2.020
|
|
|
FO CBL (24 SMF)(PIGTAIL)
|
LF
|
1,050.000
|
$8.000
|
$14.650
|
$15.320
|
$14.320
|
$14.320
|
|
|
ITS GRND MNT CAB (TY 6) (CONF 2) (REM)
|
EA
|
1.000
|
$1,800.000
|
$3,050.000
|
$3,195.020
|
$2,986.000
|
$2,986.000
|
|
|
RELOCATE EXISTING COMMUNICATION CABINET
|
EA
|
1.000
|
$30,000.000
|
$12,700.000
|
$13,322.570
|
$12,451.000
|
$12,451.000
|
|
|
CCTV FIELD EQUIP (DIGITAL) (INSTL ONLY)
|
EA
|
7.000
|
$1,500.000
|
$2,170.000
|
$2,270.540
|
$2,122.000
|
$2,122.000
|
|
|
REMOVE CCTV FIELD EQUIPMENT
|
EA
|
2.000
|
$4,500.000
|
$2,390.000
|
$2,502.730
|
$2,339.000
|
$2,339.000
|
|
|
CONDUIT (PREPARE)
|
LF
|
3,693.000
|
$3.000
|
$9.300
|
$9.760
|
$9.120
|
$9.120
|
|
|
GROUND BOX (PREPARE)
|
EA
|
36.000
|
$750.000
|
$3,185.000
|
$3,331.980
|
$3,114.000
|
$3,114.000
|
|
|
INSTALL DMS (POLE MTD CABINET)
|
EA
|
4.000
|
$15,000.000
|
$30,680.000
|
$17,112.510
|
$30,000.000
|
$30,000.000
|
|
|
ITS POLE (55 FT)(90 MPH)
|
EA
|
3.000
|
$22,000.000
|
$22,600.000
|
$23,707.990
|
$22,157.000
|
$22,157.000
|
|
|
ITS POLE MNT CAB (TY 2)(CONF 2)
|
EA
|
4.000
|
$8,000.000
|
$8,150.000
|
$8,535.990
|
$7,978.000
|
$7,977.560
|
|
|
REMOVE DYNAMIC MESSAGE SIGN SYSTEM
|
EA
|
3.000
|
$8,000.000
|
$21,700.000
|
$11,277.800
|
$21,255.000
|
$21,255.000
|
|
|
INSTALLATION OF FES
|
EA
|
17.000
|
$4,000.000
|
$2,300.000
|
$2,407.500
|
$2,250.000
|
$2,250.000
|
|
|
REMOVE RVSD POLE STRUCTURE
|
EA
|
10.000
|
$1,500.000
|
$2,650.000
|
$2,728.500
|
$2,550.000
|
$2,550.000
|
|
|
LED HI MST IL ASM (6 FIXT) (ASYM)(TY B)
|
EA
|
44.000
|
$25,000.000
|
$23,000.000
|
$24,075.000
|
$22,500.000
|
$22,500.000
|
|
|
TMA (STATIONARY)
|
DAY
|
629.000
|
$154.800
|
$100.000
|
$176.550
|
$300.000
|
$300.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
109.000
|
$66.000
|
$375.000
|
$347.750
|
$410.000
|
$600.000
|
|
|
HIGH MAST ASSEMBLY FOR ITS
|
EA
|
1.000
|
$60,000.000
|
$71,000.000
|
$61,546.400
|
$68,774.000
|
$68,773.240
|
|
|
ITS RVSD (DC ONLY) (INSTALL ONLY)
|
EA
|
5.000
|
$15,000.000
|
$2,365.000
|
$2,477.050
|
$2,315.000
|
$2,315.000
|
|
|
COLOR DMS (POLE MNT CABINET)
|
EA
|
4.000
|
$175,000.000
|
$210,000.000
|
$212,921.440
|
$198,922.000
|
$198,992.000
|
|
|
SYSTEM INTEGRATION
|
LS
|
1.000
|
$100,000.000
|
$230,000.000
|
$237,008.210
|
$221,503.000
|
$221,503.000
|
|
|
SMART WORK ZONE ITS SYSTEM
|
LS
|
1.000
|
$1,094,861.000
|
$280,000.000
|
$214,000.000
|
$280,000.000
|
$540,000.000
|
|
|
REMOVE EXISTING LANE CONTROL SIG SYS
|
EA
|
4.000
|
$1,000.000
|
$2,200.000
|
$1,043.250
|
$2,122.000
|
$2,122.000
|
|
|
ENVIRONMENTALLY CONTROLLED COMM BLDG
|
EA
|
3.000
|
$100,000.000
|
$175,000.000
|
$181,186.310
|
$169,333.000
|
$169,333.000
|
|
|
REMOVE HUB BUILDING
|
EA
|
1.000
|
$10,000.000
|
$3,050.000
|
$3,191.810
|
$2,983.000
|
$2,983.000
|
|
|
REMOVE ECUV
|
EA
|
1.000
|
$2,000.000
|
$65,000.000
|
$16,050.000
|
$63,557.000
|
$63,557.000
|
|
Totals: |
$72,014,801.888
|
$75,428,369.430
|
$76,380,439.030
|
$88,270,145.654
|
$93,996,694.308
|