County: EL PASO Highway: IH 10 Date: 06/02/2023 (1 year ago) Engineer's Estimate: $2,466,921 Control Number: 2121-04-110
Project: BR 2023(885) District: EL PASO Time: 124 WORKING DAYS Type: BRIDGE REPLACEMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,466,921.45
DAN WILLIAMS COMPANY   $2,756,557.25 1
11.74% | $289,635.80
INTERNATIONAL EAGLE ENTERPRISES, INC.   $2,760,856.25 2
11.92% | $293,934.80
0.16% | $4,299.00
SPARTAN CONSTRUCTION OF TEXAS, INC.   $3,279,027.53 3
32.92% | $812,106.08
18.95% | $522,470.28
18.77% | $518,171.28
Subcontractor Percentage Amount
HARDY HOLE DRILLING 6.15% $169,528.27
TRI STATE ELECTRIC, LTD. 5.22% $143,892.29
NATIONWIDE REBAR INC. 4.21% $116,051.06
MAJOR MOTION LOGISTICS, LLC 1.28% $35,283.93
PENHALL COMPANY 0.24% $6,615.74
PMI PAVEMENT MARKING, LLC 0.23% $6,340.08
Total: 17.33% $477,711.37

Bid Items

Items: 86, 0 filtered
EL PASO IH 10  |  EL PASO  |  2121-04-110  |  06/02/2023  |  $2,466,921  |  BR 2023(885)  |  BRIDGE REPL  |  124 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate DAN WILLIAMS COMPANY INTERNATIONAL EAGLE ENTERPRISES, INC. SPARTAN CONSTRUCTION OF TEXAS, INC.
100 6002 PREPARING ROW STA 7.000 $2,000.000 $5,000.000 $1,000.000 $7,919.800
104 6001 REMOVING CONC (PAV) SY 74.000 $10.000 $45.000 $100.000 $43.556
104 6009 REMOVING CONC (RIPRAP) SY 341.000 $10.000 $15.000 $28.000 $29.038
104 6021 REMOVING CONC (CURB) LF 663.000 $5.000 $4.000 $4.000 $9.679
104 6023 REMOVING CONC (CTB) LF 380.000 $20.000 $35.000 $25.000 $48.396
105 6013 REMOVING STAB BASE & ASPH PAV (9") SY 1,312.000 $9.000 $2.500 $10.000 $8.580
110 6001 EXCAVATION (ROADWAY) CY 55.000 $20.000 $35.000 $100.000 $181.485
132 6005 EMBANKMENT (FINAL)(ORD COMP)(TY C) CY 1,197.000 $20.000 $40.000 $12.000 $77.328
247 6203 FL BS (CMP IN PLC)(RAP) (6") SY 1,534.000 $10.000 $7.000 $18.000 $14.217
247 6230 FL BS (CMP IN PLACE)(TY A GR 1-2)(8") SY 1,591.000 $30.000 $20.000 $24.000 $17.613
310 6001 PRIME COAT (MULTI OPTION) GAL 318.000 $10.000 $10.000 $8.000 $12.319
400 6005 CEM STABIL BKFL CY 180.000 $120.000 $175.000 $200.000 $139.690
400 6006 CUT & RESTORING PAV SY 8.000 $150.000 $190.000 $500.000 $608.830
416 6004 DRILL SHAFT (36 IN) LF 639.000 $300.000 $350.000 $400.000 $356.921
416 6005 DRILL SHAFT (42 IN) LF 21.000 $400.000 $530.000 $575.000 $435.564
416 6029 DRILL SHAFT (RDWY ILL POLE) (30 IN) LF 8.000 $320.000 $400.000 $440.000 $362.970
420 6014 CL C CONC (ABUT)(HPC) CY 52.400 $1,100.000 $1,500.000 $1,100.000 $907.425
420 6030 CL C CONC (CAP)(HPC) CY 59.700 $1,200.000 $1,900.000 $1,500.000 $1,330.890
420 6038 CL C CONC (COLUMN)(HPC) CY 55.400 $1,000.000 $1,400.000 $1,100.000 $1,814.850
420 6066 CL C CONC (RAIL FOUNDATION) CY 82.000 $600.000 $500.000 $800.000 $626.980
422 6002 REINF CONC SLAB (HPC) SF 11,730.000 $22.000 $30.000 $24.000 $33.163
422 6016 APPROACH SLAB (HPC) CY 71.000 $600.000 $700.000 $600.000 $670.140
425 6035 PRESTR CONC GIRDER (TX28) LF 1,518.120 $250.000 $240.000 $250.000 $373.203
432 6001 RIPRAP (CONC)(4 IN) CY 1.500 $1,650.000 $850.000 $2,000.000 $2,325.040
432 6008 RIPRAP (CONC)(CL B)(RR8&RR9) CY 104.000 $450.000 $725.000 $400.000 $577.485
450 6024 RAIL (TY SSTR)(HPC) LF 558.000 $80.000 $75.000 $80.000 $124.297
450 6027 RAIL (TY T80SS) LF 510.000 $90.000 $125.000 $75.000 $126.497
454 6018 SEALED EXPANSION JOINT (4 IN) (SEJ - M) LF 137.000 $200.000 $210.000 $250.000 $291.478
496 6010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) EA 1.000 $150,000.000 $150,000.000 $150,000.000 $108,891.000
496 6025 REMOV STR (APPROACH SLAB) EA 2.000 $9,000.000 $1,750.000 $30,000.000 $5,142.075
500 6001 MOBILIZATION LS 1.000 $200,000.000 $205,000.000 $150,000.000 $244,238.500
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 7.000 $10,000.000 $15,000.000 $8,000.000 $7,864.350
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 90.000 $40.000 $33.250 $50.000 $48.947
506 6011 ROCK FILTER DAMS (REMOVE) LF 90.000 $15.000 $12.000 $15.000 $18.424
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 623.000 $20.000 $24.500 $20.000 $42.622
506 6024 CONSTRUCTION EXITS (REMOVE) SY 623.000 $10.000 $12.750 $10.000 $18.424
512 6005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) LF 1,320.000 $68.000 $35.000 $96.000 $104.658
512 6053 PORT CTB (REMOVE)(F-SHAPE)(TY 1) LF 1,320.000 $20.000 $10.000 $8.000 $18.975
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 500.000 $30.000 $30.000 $28.000 $36.297
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 512.500 $40.000 $35.000 $35.000 $50.816
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $2,500.000 $3,200.000 $2,650.000 $3,024.750
540 6013 TRANSITION ADJUSTMENT EA 1.000 $2,000.000 $1,400.000 $5,000.000 $483.960
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 2.000 $3,300.000 $1,400.000 $1,500.000 $2,056.830
542 6001 REMOVE METAL BEAM GUARD FENCE LF 1,487.500 $4.000 $4.000 $1.500 $8.469
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 7.000 $350.000 $350.000 $400.000 $302.475
543 6020 CABLE BARRIER TERMINAL SECTION (TL-4) EA 2.000 $3,000.000 $4,500.000 $5,000.000 $604.950
543 6021 REMOVE CABLE BARRIER LF 200.000 $4.000 $5.000 $4.000 $8.469
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 5.000 $3,500.000 $3,400.000 $3,200.000 $3,629.700
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 2.000 $400.000 $350.000 $500.000 $802.965
545 6005 CRASH CUSH ATTEN (REMOVE) EA 6.000 $1,000.000 $1,000.000 $1,000.000 $1,127.480
545 6007 CRASH CUSH ATTEN (INSTL)(L)(N)(TL3) EA 2.000 $30,000.000 $30,000.000 $30,000.000 $31,146.555
545 6019 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 4.000 $10,000.000 $10,000.000 $25,000.000 $10,064.325
610 6004 RELOCATE RD IL ASM (TRANS-BASE) EA 1.000 $2,500.000 $2,600.000 $2,860.000 $5,928.510
618 6023 CONDT (PVC) (SCH 40) (2") LF 595.000 $20.000 $32.000 $35.000 $36.297
618 6024 CONDT (PVC) (SCH 40) (2") (BORE) LF 605.000 $40.000 $40.000 $43.500 $48.396
620 6008 ELEC CONDR (NO.8) INSULATED LF 2,355.000 $2.000 $3.200 $3.750 $3.146
620 6012 ELEC CONDR (NO.4) INSULATED LF 1,275.000 $3.000 $5.700 $6.250 $4.840
624 6002 GROUND BOX TY A (122311)W/APRON EA 7.000 $1,000.000 $1,725.000 $1,895.000 $1,935.840
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 1.000 $825.000 $915.000 $1,200.000 $1,107.059
644 6064 IN BRIDGE MNT CLEARANCE SGN ASSM(TY N) EA 2.000 $3,000.000 $5,000.000 $5,485.000 $6,033.771
644 6068 RELOCATE SM RD SN SUP&AM TY 10BWG EA 1.000 $750.000 $825.000 $480.000 $982.439
644 6070 RELOCATE SM RD SN SUP&AM TY S80 EA 1.000 $800.000 $825.000 $480.000 $990.908
644 6076 REMOVE SM RD SN SUP&AM EA 3.000 $150.000 $450.000 $150.000 $544.455
658 6027 INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI) EA 6.000 $20.000 $60.000 $22.000 $26.618
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 10.000 $20.000 $60.000 $30.000 $48.396
666 6174 REFL PAV MRK TY II (W) 6" (SLD) LF 1,321.000 $0.400 $0.600 $1.750 $1.210
666 6210 REFL PAV MRK TY II (Y) 6" (SLD) LF 1,321.000 $0.400 $0.600 $1.750 $1.210
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 731.000 $0.750 $1.450 $2.750 $1.210
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 731.000 $1.000 $1.450 $2.750 $1.210
672 6009 REFL PAV MRKR TY II-A-A EA 14.000 $6.000 $8.850 $35.000 $24.198
678 6002 PAV SURF PREP FOR MRK (6") LF 2,642.000 $0.200 $0.600 $2.000 $0.605
690 6001 REMOVAL OF CONDUIT LF 211.000 $10.000 $9.000 $10.000 $10.889
3076 6024 D-GR HMA TY-C SAC-A PG70-22 TON 425.000 $185.000 $155.000 $140.000 $149.096
3076 6066 TACK COAT GAL 232.000 $10.000 $10.000 $8.000 $36.297
6000 6016 INSTALL ELECTRICAL SPLICE EA 1.000 $200.000 $295.000 $325.000 $72.594
6000 6098 INSTALL CIRCUIT BREAKER EA 1.000 $500.000 $440.000 $485.000 $725.940
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 8.000 $8,000.000 $10,000.000 $15,000.000 $18,148.500
6010 6011 CCTV FIELD EQUIP (DIGITAL) (INSTL ONLY) EA 1.000 $2,500.000 $1,950.000 $2,145.000 $2,419.800
6010 6013 REMOVE CCTV FIELD EQUIPMENT EA 1.000 $300.000 $1,250.000 $1,375.000 $1,209.900
6027 6003 CONDUIT (PREPARE) LF 10.000 $3.000 $25.000 $28.000 $12.099
6027 6008 GROUND BOX (PREPARE) EA 2.000 $400.000 $650.000 $715.000 $846.930
6064 6046 ITS POLE (55 FT)(90 MPH) EA 1.000 $20,000.000 $28,000.000 $29,600.000 $30,247.500
6064 6084 ITS POLE MNT CAB (TY 2)(CONF 2) EA 1.000 $4,000.000 $8,000.000 $8,620.000 $9,679.200
6064 6087 ITS POLE MNT CAB (TY 2)(CONF 2)(REM) EA 1.000 $500.000 $600.000 $660.000 $3,629.700
6185 6002 TMA (STATIONARY) DAY 40.000 $300.000 $285.000 $200.000 $423.465
6386 6001 INSTALLATION OF CELLULAR MODEM EA 1.000 $2,500.000 $950.000 $1,045.000 $907.425
Totals: $2,466,921.45 $2,756,557.25 $2,760,856.25 $3,279,027.70