Job Info for 0924-06-627

County: EL PASO Highway: VA Date: 03/05/2021 (3 years ago) Engineer's Estimate: $509,882 Control Number: 0924-06-627
Project: C 924-6-627 District: EL PASO Time: 260 WORKING DAYS Type: BRIDGE MAINTENANCE

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $509,882.00
SCR CIVIL CONSTRUCTION, LLC   $431,801.50 1
-15.31% | -$78,080.50
LESNA CONSTRUCTION, INC.   $448,622.00 2
-12.01% | -$61,260.00
3.9% | $16,820.50
INTERNATIONAL EAGLE ENTERPRISES, INC.   $448,871.00 3
-11.97% | -$61,011.00
3.95% | $17,069.50
0.06% | $249.00
SYNERGY PROJECT CONTRACTORS, INC.   $452,584.28 4
-11.24% | -$57,297.72
4.81% | $20,782.78
0.83% | $3,713.28
MPB, INC.   $474,945.00 5
-6.85% | -$34,937.00
9.99% | $43,143.50
4.94% | $22,360.72
B & MS CONSTRUCTION, INC.   $504,644.22 6
-1.03% | -$5,237.78
16.87% | $72,842.72
6.25% | $29,699.22
TALBRAN ENTERPRISES LLC   $571,220.00 7
12.03% | $61,338.00
32.29% | $139,418.50
13.19% | $66,575.78
DAN WILLIAMS COMPANY   $617,932.00 8
21.19% | $108,050.00
43.11% | $186,130.50
8.18% | $46,712.00
FNH CONSTRUCTION, LLC   $676,838.00 9
32.74% | $166,956.00
56.75% | $245,036.50
9.53% | $58,906.00
BT CONSTRUCTORS, LLC   $838,607.64 10
64.47% | $328,725.64
94.21% | $406,806.14
23.90% | $161,769.64

Bid Items

Items: 8, 0 filtered
EL PASO VA  |  EL PASO  |  0924-06-627  |  03/05/2021  |  $509,882  |  C 924-6-627  |  BRIDGE MAINT  |  260 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate SCR CIVIL CONSTRUCTION, LLC LESNA CONSTRUCTION, INC. INTERNATIONAL EAGLE ENTERPRISES, INC. SYNERGY PROJECT CONTRACTORS, INC. MPB, INC. B & MS CONSTRUCTION, INC. TALBRAN ENTERPRISES LLC DAN WILLIAMS COMPANY FNH CONSTRUCTION, LLC BT CONSTRUCTORS, LLC
429 6004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) SF 420.000 $150.000 $172.400 $167.000 $300.000 $89.680 $200.000 $185.000 $255.000 $250.000 $350.000 $143.870
438 6001 CLEANING AND SEALING EXISTING JOINTS LF 4,575.000 $25.000 $50.500 $43.000 $19.000 $49.560 $45.000 $45.000 $60.000 $30.000 $60.000 $68.300
500 6001 MOBILIZATION LS 1.000 $25,000.000 $43,100.000 $45,000.000 $40,000.000 $23,600.000 $43,000.000 $65,000.000 $185,000.000 $60,000.000 $65,000.000 $106,735.060
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 13.000 $18,000.000 $3,300.000 $5,550.000 $12,000.000 $8,260.000 $7,100.000 $6,250.000 $100.000 $15,000.000 $8,500.000 $21,576.920
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 478.000 $5.500 $1.000 $6.000 $6.000 $3.540 $10.000 $6.810 $5.000 $15.000 $12.000 $7.680
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 478.000 $1.000 $1.000 $0.500 $1.000 $1.180 $5.000 $1.180 $1.000 $4.000 $9.000 $0.860
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $10,000.000 $14,400.000 $15,000.000 $12,000.000 $4,130.000 $15,000.000 $4,000.000 $100.000 $18,000.000 $16,000.000 $8,525.000
6185 6002 TMA (STATIONARY) DAY 252.000 $200.000 $50.000 $125.000 $50.000 $185.260 $50.000 $250.000 $1.000 $300.000 $150.000 $227.550
Totals: $509,882.00 $431,801.50 $448,622.00 $448,871.00 $452,584.28 $474,945.00 $504,644.22 $571,220.00 $617,932.00 $676,838.00 $838,607.64