REMOVING CONC (RIPRAP)
|
CY
|
70.000
|
$75.000
|
$200.000
|
|
|
REMOVING CONC (CURB)
|
LF
|
12.000
|
$7.500
|
$35.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY A)
|
CY
|
13.000
|
$20.000
|
$150.000
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
556.000
|
$2.000
|
$10.000
|
|
|
PLANE ASPH CONC PAV(0" TO 3")
|
SY
|
2,214.000
|
$2.500
|
$15.000
|
|
|
FLOWABLE BACKFILL
|
CY
|
742.000
|
$240.000
|
$650.000
|
|
|
TEMPORARY SPL SHORING (COFFERDAM)
|
SF
|
240.000
|
$5.000
|
$1.000
|
|
|
CONC STR REPAIR(CLEAN & COAT WTH EPOXY)
|
SF
|
76.000
|
$350.000
|
$400.000
|
|
|
CONC STR REPAIR (VERTICAL & OVERHEAD)
|
SF
|
290.000
|
$195.000
|
$500.000
|
|
|
CONC STR REPR(REMOV AND REPL WINGWALL)
|
CY
|
1.000
|
$8,000.000
|
$4,000.000
|
|
|
CONC STR REP (REMOVE AND REPL BM END)
|
CY
|
1.000
|
$1,000.000
|
$10,000.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
70.000
|
$500.000
|
$1,600.000
|
|
|
RIPRAP (STONE PROTECTION)(18 IN)
|
CY
|
83.000
|
$145.000
|
$450.000
|
|
|
BEDDING MATERIAL (3 IN)
|
CY
|
8.000
|
$100.000
|
$500.000
|
|
|
CLEANING AND SEALING EXISTING JOINTS
|
LF
|
515.000
|
$35.000
|
$30.000
|
|
|
CLEAN & PAINT EXIST STR (SYSTEM II)
|
LS
|
2.000
|
$10,000.000
|
$75,000.000
|
|
|
CLEAN EXIST CULVERTS
|
CY
|
131.000
|
$30.000
|
$150.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$150,000.000
|
$205,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
16.000
|
$18,000.000
|
$15,000.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
4,672.000
|
$9.000
|
$6.750
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
4,672.000
|
$4.000
|
$2.500
|
|
|
ONE-WAY TRAF CONT (FLAGGER CONT)
|
HR
|
208.000
|
$135.000
|
$85.000
|
|
|
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
|
LF
|
210.000
|
$75.000
|
$125.000
|
|
|
PORT CTB (MOVE)(SGL SLP)(TY 1)
|
LF
|
210.000
|
$5.000
|
$6.000
|
|
|
PORT CTB (REMOVE)(SGL SLP)(TY 1)
|
LF
|
210.000
|
$12.000
|
$30.000
|
|
|
CONC CURB (TY II)
|
LF
|
12.000
|
$19.000
|
$175.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
2.000
|
$1,200.000
|
$750.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
2.000
|
$1,000.000
|
$750.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
2.000
|
$10,000.000
|
$11,000.000
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
2,700.000
|
$4.000
|
$15.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
100.000
|
$1.000
|
$2.150
|
|
REFL PAV MRK TY II (W) 6" (BRK)
|
LF
|
215.000
|
$0.350
|
$0.950
|
|
REFL PAV MRK TY II (W) 6" (SLD)
|
LF
|
3,020.000
|
$0.350
|
$0.950
|
|
REFL PAV MRK TY II (Y) 6" (BRK)
|
LF
|
1,080.000
|
$0.200
|
$0.950
|
|
REFL PAV MRK TY II (Y) 6" (SLD)
|
LF
|
860.000
|
$0.350
|
$0.950
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
2,160.000
|
$0.650
|
$0.950
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
270.000
|
$1.000
|
$0.950
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
14.000
|
$5.000
|
$15.000
|
|
TRAFFIC BUTTON TY I-C
|
EA
|
2,700.000
|
$5.700
|
$15.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
2,430.000
|
$0.500
|
$1.300
|
|
|
POTHOLE REPAIR (STANDARD)
|
SY
|
4.000
|
$88.000
|
$1,200.000
|
|
|
JT / CRCK SEAL (RUBBER - ASPHALT)
|
LMI
|
0.380
|
$540.000
|
$50,000.000
|
|
|
TREE TRIMMING / BRUSH REMOVAL
|
MI
|
0.040
|
$10,000.000
|
$60,000.000
|
|
|
DITCH CLEANING AND RESHAPING (FOOT)
|
LF
|
120.000
|
$15.000
|
$35.000
|
|
|
REPAIR RAIL ELEMENT (W - BEAM)
|
LF
|
13.000
|
$30.000
|
$50.000
|
|
|
REALIGN POSTS
|
EA
|
1.000
|
$25.000
|
$75.000
|
|
|
INSTALL BLOCKOUT (TYPE SPECIFIED)
|
EA
|
1.000
|
$16.000
|
$100.000
|
|
|
REPLACE TERMINAL ANCHOR POSTS
|
EA
|
2.000
|
$300.000
|
$150.000
|
|
|
CNC CRACK REPAIR (DISCRETE)(INJECT)
|
LF
|
322.000
|
$115.000
|
$90.000
|
|
|
REP STL BRDG MEMB (WELD REPAIR)
|
EA
|
1.000
|
$100.000
|
$2,000.000
|
|
|
BRIDGE JOINT REPAIR (HEADER)
|
LF
|
7.000
|
$175.000
|
$500.000
|
|
|
BRIDGE JOINT REPLACEMENT (HEADER)
|
LF
|
498.000
|
$350.000
|
$225.000
|
|
|
D-GR HMA TY-C SAC-A PG70-22 (EXEMPT)
|
TON
|
854.000
|
$125.000
|
$280.000
|
|
|
TACK COAT
|
GAL
|
415.000
|
$7.000
|
$30.000
|
|
|
REPLACE ELASTOMERIC BEARING PADS
|
EA
|
6.000
|
$14,000.000
|
$7,500.000
|
|
|
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
|
LF
|
2,016.000
|
$8.500
|
$18.000
|
|
|
TMA (STATIONARY)
|
DAY
|
76.000
|
$275.000
|
$350.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
18.000
|
$475.000
|
$550.000
|
|
Totals: |
$1,431,813.450
|
$2,271,557.750
|