ECTOR FM 1882 (2005-02-017)

Items: 66

County: ECTOR
Length: N/A
Highway: FM 1882
District: ODESSA
Control Number: 2005-02-017
DBE Goal: N/A
Project: F 2023(304)
Guaranty: N/A
Time: 210 WORKING DAYS
Engineer's Estimate: $11,667,891.38
Date: 09/06/2023 (2 years ago)
Contract Number: N/A
Type: HIGHWAY IMPROVEMENT
Mail/Deliver Bids To: N/A
ODA-PRELETTINGQUESTIONS
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$11,667,891.38
Over/Under Est: -12.88% -$1,502,291.95
$11,439,968.25
Over/Under Est: -1.95% -$227,923.13
Amt Left: 12.54% $1,274,368.82
$11,755,677.14
Over/Under Est: 0.75% $87,785.76
Amt Left: 15.64% $1,590,077.71
Delta: -2.76% -$315,708.89
$14,908,802.00
Over/Under Est: 27.78% $3,240,910.62
Amt Left: 46.66% $4,743,202.57
Delta: -26.82% -$3,153,124.86
Subcontractor Percentage Amount
TEX OP CONSTRUCTION, LP 2.71% $285,301.46
O. TREVINO CONSTRUCTION, LLC 2.45% $257,929.37
TRP CONSTRUCTION GROUP, LLC 1.39% $146,335.44
HJC FARMS, INC. 0.79% $83,169.06
DK CONTRACTING, LLC 0.73% $76,852.42
SCR CIVIL CONSTRUCTION, LLC 0.71% $74,746.88
CONTRACTORS SERVICE, LTD. 0.69% $72,641.33
WILLIS ELECTRIC CO., LP 0.16% $16,844.37
FC TRAFFIC CONTROL, INC. 0.03% $3,158.32
DESERT PAVING, INC. 0.03% $3,158.32
R.E.B.D. TRUCKING LLC 0.00% $0.00
Total: 9.69% $1,020,136.97

Bid Items & Bid Tabulations

66 Total 0 of 66
ECTOR  |  FM 1882  |  ODESSA  |  2005-02-017  |  09/06/2023  |  $11,667,891.38  |  F 2023(304)  |  HWY IMPRV  |  210 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
FNF CONSTRUCTION, INC.
REECE ALBERT, INC.
FNH CONSTRUCTION, LLC
REMOVING CONC (APPR SLAB)
SY 203.000 $20.000 $110.000 $275.000 $172.930 $20.000
REMOVING STAB BASE & ASPH PAV (9")
SY 77,030.000 $7.790 $7.250 $7.500 $10.680 $12.000
REMOVING STAB BASE AND ASPH PAV(8")
SY 34,337.000 $7.800 $6.550 $6.500 $9.520 $11.000
BLADING
HR 30.000 $245.000 $415.000 $150.000 $841.420 $150.000
PROOF ROLLING
HR 30.000 $140.000 $165.000 $125.000 $160.530 $150.000
REWORK BS MTL (TY D)(SURF)(ORD COMP)
SY 111,367.000 $1.900 $1.150 $2.500 $0.540 $6.000
PRIME COAT (AE-P)
GAL 22,273.000 $5.600 $5.120 $9.000 $6.330 $8.000
FOG SEAL (CSS-1H)
GAL 22,273.000 $5.950 $4.660 $4.000 $3.080 $8.000
FULL-DPTH REP(BR APPROACH SLAB)(9"-13")
SY 203.000 $450.000 $879.750 $450.000 $327.800 $850.000
ADJUSTING MANHOLES (WATER VALVE BOX)
EA 2.000 $1,475.000 $2,012.500 $2,500.000 $1,857.140 $1,100.000
MOBILIZATION
LS 1.000 $1,060,676.730 $575,000.000 $1,150,000.000 $388,166.810 $1,300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $30,000.000 $30,000.000 $45,000.000 $3,549.900 $8,500.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 514.000 $10.750 $18.000 $10.000 $6.960 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 514.000 $2.400 $9.000 $1.250 $8.150 $9.000
CONC SIDEWALKS (5")
SY 626.000 $200.000 $120.750 $175.000 $130.620 $85.000
CURB RAMPS (TY 7)
SY 4.000 $205.000 $431.250 $650.000 $950.390 $400.000
MTL W-BEAM GD FEN (STEEL POST)
LF 425.000 $35.000 $41.400 $50.000 $47.970 $50.000
MTL BEAM GD FEN TRANS (T101)
EA 4.000 $1,800.000 $2,127.500 $2,500.000 $2,464.960 $2,000.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,690.000 $1,725.000 $2,000.000 $1,998.620 $2,000.000
REMOVE METAL BEAM GUARD FENCE
LF 425.000 $3.840 $3.450 $4.000 $4.000 $5.000
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $375.000 $345.000 $400.000 $399.720 $1,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,650.000 $3,852.500 $4,500.000 $4,463.570 $4,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $375.000 $345.000 $400.000 $399.720 $2,000.000
WIRE FENCE (TY A)
LF 1,915.000 $23.000 $23.000 $25.000 $17.800 $5.000
ALUMINUM SIGNS (TY A)
SF 497.000 $35.000 $34.500 $35.000 $39.970 $30.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 34.000 $1,000.000 $834.900 $1,000.000 $967.330 $1,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 16.000 $1,150.000 $1,009.700 $1,250.000 $1,169.860 $1,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 8.000 $1,325.000 $1,236.250 $1,500.000 $1,432.340 $1,500.000
REMOVE SM RD SN SUP&AM
EA 58.000 $140.000 $125.000 $125.000 $133.240 $100.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 100.000 $30.000 $34.000 $20.000 $57.690 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BR)
EA 10.000 $45.000 $49.450 $200.000 $57.290 $100.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 90.000 $100.000 $97.750 $200.000 $113.250 $100.000
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 1,250.000 $5.000 $5.180 $4.500 $6.000 $6.000
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 1,250.000 $4.950 $5.180 $4.500 $6.000 $6.000
WK ZN PAV MRK REMOV (W)6"(BRK)
LF 32,705.000 $1.500 $0.350 $0.300 $0.400 $0.500
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 14,705.000 $1.000 $0.250 $0.250 $0.290 $0.500
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 595.000 $6.000 $3.160 $3.000 $3.660 $5.000
WK ZN PAV MRK REMOV (W)(ARROW)
EA 49.000 $190.000 $115.000 $105.000 $133.240 $250.000
WK ZN PAV MRK REMOV (W)(WORD)
EA 19.000 $205.000 $132.250 $120.000 $153.230 $250.000
WK ZN PAV MRK REMOV (Y)6"(BRK)
LF 16,100.000 $1.600 $0.350 $0.350 $0.400 $1.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 92,770.000 $1.100 $0.250 $0.250 $0.290 $0.500
WK ZN PAV MRK REMOV (Y)12"(SLD)
LF 640.000 $4.900 $1.900 $1.750 $2.200 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,600.000 $1.500 $2.850 $2.000 $1.340 $6.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,775.000 $1.500 $2.850 $2.000 $1.280 $6.000
REFL PAV MRK TY II (W) 6" (BRK)
LF 32,705.000 $0.300 $0.280 $0.300 $0.320 $0.500
REFL PAV MRK TY II (W) 6" (SLD)
LF 20,705.000 $0.160 $0.180 $0.200 $0.210 $0.500
REFL PAV MRK TY II (W) 24" (SLD)
LF 460.000 $3.600 $4.600 $5.000 $5.330 $10.000
REFL PAV MRK TY II (W) (ARROW)
EA 49.000 $84.000 $86.250 $100.000 $99.930 $150.000
REFL PAV MRK TY II (W) (WORD)
EA 19.000 $92.000 $103.500 $115.000 $119.920 $150.000
REFL PAV MRK TY II (Y) 6" (BRK)
LF 16,100.000 $0.340 $0.280 $0.300 $0.320 $0.500
REFL PAV MRK TY II (Y) 6" (SLD)
LF 42,270.000 $0.350 $0.180 $0.200 $0.210 $0.500
REFL PAV MRK TY II (Y) 12" (SLD)
LF 640.000 $2.400 $4.600 $5.000 $5.330 $6.000
REFL PAV MRKR TY I-C
EA 1,250.000 $4.950 $5.180 $5.500 $6.000 $6.000
REFL PAV MRKR TY II-A-A
EA 1,250.000 $4.400 $5.180 $5.500 $6.000 $6.000
ELIM EXT PAV MRK & MRKS (4")
LF 56,500.000 $0.900 $0.860 $1.000 $1.000 $1.000
ELIM EXT PAV MRK & MRKS (24")
LF 60.000 $3.000 $4.600 $5.000 $5.330 $6.000
ELIM EXT PAV MRK & MRKS (ARROW)
EA 11.000 $35.000 $86.250 $100.000 $99.930 $150.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 8.000 $30.000 $86.250 $100.000 $99.930 $150.000
BACKPLATE W/REFL BRDR(4 SEC)
EA 2.000 $200.000 $1,092.500 $1,300.000 $1,265.790 $500.000
BACKPLATE W/REFL BRDR(3 SEC)
EA 18.000 $170.000 $977.500 $1,150.000 $1,132.550 $500.000
SP MIXES SP-B SAC-B PG70-22
TON 49,002.000 $120.000 $125.000 $124.000 $153.760 $170.000
TOM-C SAC-A
TON 7,001.000 $280.000 $145.000 $199.000 $214.800 $220.000
BONDING COURSE
GAL 30,439.000 $6.000 $4.710 $5.000 $2.720 $8.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 1,680.000 $72.500 $60.000 $35.000 $39.970 $150.000
TMA (STATIONARY)
DAY 210.000 $220.000 $90.000 $250.000 $218.360 $250.000
TMA (MOBILE OPERATION)
DAY 70.000 $250.000 $1,020.000 $650.000 $577.120 $550.000
Totals: $11,667,891.380 $10,165,599.430 $11,439,968.250 $11,755,677.140 $14,908,802.000