ECTOR VA (0906-00-219)
Items: 12
County: ECTOR
Length: N/A
Highway: VA
District: ODESSA
Control Number: 0906-00-219
DBE Goal: N/A
Project: C 906-00-219
Guaranty: N/A
Time: 36 WORKING DAYS
Engineer's Estimate: $1,577,172.44
Date: 03/08/2023 (3 years ago)
Contract Number: N/A
Type: IH PAVEMENT MARKINGS (2023)
Mail/Deliver Bids To: N/A
PRELETTINGQUESTIONS
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,577,172.44 | |||
| $1,103,053.92 |
-30.06%
-$474,118.52
|
|||
| $1,226,821.32 |
-22.21%
-$350,351.12
|
11.22%
$123,767.40
|
||
| $1,233,755.44 |
-21.77%
-$343,417.00
|
11.85%
$130,701.52
|
-0.57%
-$6,934.12
|
|
| $1,392,083.99 |
-11.74%
-$185,088.45
|
26.2%
$289,030.07
|
-12.83%
-$158,328.55
|
|
| $1,399,795.96 |
-11.25%
-$177,376.48
|
26.9%
$296,742.04
|
-0.55%
-$7,711.97
|
|
| $1,477,329.68 |
-6.33%
-$99,842.76
|
33.93%
$374,275.76
|
-5.54%
-$77,533.72
|
|
| $1,754,509.86 |
11.24%
$177,337.42
|
59.06%
$651,455.94
|
-18.76%
-$277,180.18
|
|
| $1,764,665.85 |
11.89%
$187,493.41
|
59.98%
$661,611.93
|
-0.58%
-$10,155.99
|
E
Engineer's Estimate
$1,577,172.44
1
Awarded
$1,103,053.92
Over/Under Est:
-30.06%
-$474,118.52
$1,226,821.32
Over/Under Est:
-22.21%
-$350,351.12
Amt Left:
11.22%
$123,767.40
$1,233,755.44
Over/Under Est:
-21.77%
-$343,417.00
Amt Left:
11.85%
$130,701.52
Delta:
-0.57%
-$6,934.12
$1,392,083.99
Over/Under Est:
-11.74%
-$185,088.45
Amt Left:
26.2%
$289,030.07
Delta:
-12.83%
-$158,328.55
$1,399,795.96
Over/Under Est:
-11.25%
-$177,376.48
Amt Left:
26.9%
$296,742.04
Delta:
-0.55%
-$7,711.97
$1,477,329.68
Over/Under Est:
-6.33%
-$99,842.76
Amt Left:
33.93%
$374,275.76
Delta:
-5.54%
-$77,533.72
$1,754,509.86
Over/Under Est:
11.24%
$177,337.42
Amt Left:
59.06%
$651,455.94
Delta:
-18.76%
-$277,180.18
$1,764,665.85
Over/Under Est:
11.89%
$187,493.41
Amt Left:
59.98%
$661,611.93
Delta:
-0.58%
-$10,155.99
Bid Items & Bid Tabulations
12
Total
0 of 12