Show Job Controls
Bid Cobra

ECTOR VA (0906-00-189)

Items: 24

County: ECTOR
Length: N/A
Highway: VA
District: ODESSA
Control Number: 0906-00-189
DBE Goal: N/A
Project: C 906-00-189
Guaranty: N/A
Time: 71 WORKING DAYS
Engineer's Estimate: $3,767,797.50
Date: 07/01/2021 (4 years ago)
Contract Number: N/A
Type: PAVEMENT MARKINGS (NON-IH)
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (9)
E
Engineer's Estimate
$3,767,797.50
$2,533,346.93
Over/Under Est: -32.76% -$1,234,450.57
Over/Under Est: -31.24% -$1,177,167.04
Amt Left: 2.26% $57,283.53
Over/Under Est: -22.18% -$835,701.61
Amt Left: 15.74% $398,748.96
Delta: -13.18% -$341,465.43
$2,983,187.01
Over/Under Est: -20.82% -$784,610.49
Amt Left: 17.76% $449,840.08
Delta: -1.74% -$51,091.12
Over/Under Est: -16.16% -$608,709.25
Amt Left: 24.7% $625,741.32
Delta: -5.90% -$175,901.24
$3,299,053.85
Over/Under Est: -12.44% -$468,743.65
Amt Left: 30.23% $765,706.92
Delta: -4.43% -$139,965.60
$3,770,395.40
Over/Under Est: 0.07% $2,597.90
Amt Left: 48.83% $1,237,048.47
Delta: -14.29% -$471,341.55
Over/Under Est: 5.77% $217,372.62
Amt Left: 57.31% $1,451,823.19
Delta: -5.70% -$214,774.72
Over/Under Est: 6.43% $242,161.25
Amt Left: 58.29% $1,476,611.82
Delta: -0.62% -$24,788.63

Bid Items & Bid Tabulations

24 Total 0 of 24
ECTOR  |  VA  |  ODESSA  |  0906-00-189  |  07/01/2021  |  $3,767,797.50  |  C 906-00-189  |  PAVMT MRK (NON-IH)  |  71 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CENTERLINE TECHNOLOGIES, LLC
PMI PAVEMENT MARKING, LLC
DOUBLE A CONTRACTING, L.P.
STRIPE-A-ZONE, INC.
TRP CONSTRUCTION GROUP, LLC
BATTERSON, LLP
L&L COMPANY
TOTAL HIGHWAY MAINTENANCE, LLC
INTERSTATE BARRICADES & MARKINGS, INC.
MOBILIZATION
LS 1.000 $653,567.650 $1.000 $3,500.000 $175,000.000 $1.000 $60,000.000 $110,000.000 $1.000 $250,000.000 $25,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $10,000.000 $1.000 $3,000.000 $1.000 $1.000 $5,000.000 $2,800.000 $1.000 $3,500.000 $2,500.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 39,306.000 $0.690 $0.550 $0.850 $0.800 $0.500 $0.700 $0.850 $1.000 $1.200 $0.950
REFL PAV MRK TY I (W)12"(LNDP)(100MIL)
LF 529.000 $2.080 $0.750 $2.060 $3.750 $3.000 $1.500 $2.800 $4.000 $3.150 $4.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 4,243.000 $5.360 $6.000 $5.300 $4.750 $5.000 $8.000 $5.800 $6.000 $6.450 $4.000
REFL PAV MRK TY I (Y)8"(SLD)(100MIL)
LF 2,558.000 $0.940 $0.550 $1.113 $0.950 $0.650 $2.500 $0.850 $1.000 $1.200 $0.950
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 58,918.000 $0.360 $0.280 $0.300 $0.306 $0.340 $0.350 $0.350 $0.450 $0.480 $0.400
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 1,298,592.000 $0.360 $0.250 $0.290 $0.280 $0.340 $0.320 $0.350 $0.450 $0.430 $0.400
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 126,751.000 $0.230 $0.280 $0.300 $0.300 $0.340 $0.350 $0.350 $0.450 $0.480 $0.400
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 358,018.000 $0.570 $0.250 $0.290 $0.290 $0.340 $0.320 $0.350 $0.450 $0.430 $0.400
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 2,530,343.000 $0.470 $0.440 $0.390 $0.480 $0.500 $0.520 $0.550 $0.650 $0.610 $0.650
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 331,064.000 $0.470 $0.440 $0.515 $0.500 $0.500 $0.550 $0.550 $0.650 $0.690 $0.650
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 1,084,332.000 $0.540 $0.440 $0.390 $0.485 $0.500 $0.520 $0.550 $0.650 $0.610 $0.650
PREFAB PAV MRK TY C (W) (ARROW)
EA 91.000 $201.670 $210.000 $180.000 $180.000 $190.000 $200.000 $180.000 $180.000 $245.000 $175.000
PREFAB PAV MRK TY C (W) (WORD)
EA 83.000 $258.330 $255.000 $230.000 $210.000 $210.000 $250.000 $225.000 $300.000 $320.000 $225.000
PREFAB PAV MRK TY C (W) (RR XING)
EA 8.000 $500.000 $650.000 $350.000 $560.000 $675.000 $750.000 $475.000 $500.000 $900.000 $350.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 105.000 $51.250 $38.000 $109.000 $18.000 $60.000 $45.000 $29.000 $30.000 $47.000 $22.000
REFL PAV MRKR TY I-C
EA 3,318.000 $4.030 $3.000 $3.540 $2.500 $3.500 $3.500 $3.750 $3.000 $3.850 $5.000
REFL PAV MRKR TY I-R
EA 602.000 $4.030 $5.000 $10.460 $6.000 $6.000 $7.000 $4.250 $3.000 $8.000 $5.000
REFL PAV MRKR TY II-A-A
EA 15,419.000 $3.550 $3.000 $3.450 $2.500 $3.050 $3.500 $3.750 $3.000 $3.850 $5.000
TRAFFIC BUTTON TY I-C
EA 81.000 $5.670 $20.000 $3.570 $6.000 $25.000 $3.500 $3.750 $3.000 $13.890 $5.000
PREFORMED CENTERLINE RUMBLE STRIP
LF 57,231.000 $3.680 $3.000 $4.500 $3.150 $4.000 $4.000 $3.250 $3.500 $4.250 $8.000
TMA (STATIONARY)
DAY 73.000 $253.890 $1.000 $225.000 $1.000 $1.000 $25.000 $1.000 $1.000 $125.000 $100.000
TMA (MOBILE OPERATION)
DAY 125.000 $153.770 $1.000 $30.000 $1.000 $1.000 $25.000 $1.000 $1.000 $125.000 $100.000
Totals: $3,767,797.500 $2,533,346.930 $2,590,630.464 $2,932,095.898 $2,983,187.010 $3,159,088.250 $3,299,053.850 $3,770,395.400 $3,985,170.120 $4,009,958.750