Job Info for 0004-07-139

County: ECTOR Highway: IH 20 Date: 11/01/2023 (1 year ago) Engineer's Estimate: $2,769,227 Control Number: 0004-07-139
Project: BR 2024(304) District: ODESSA Time: 180 WORKING DAYS Type: BRIDGE MAINTENANCE
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,769,226.90
SCOTT TUCKER CONSTRUCTION COMPANY, LLC   $1,999,084.70 1
-27.81% | -$770,142.20
SCR CIVIL CONSTRUCTION, LLC   $2,131,728.25 2
-23.02% | -$637,498.65
6.64% | $132,643.55
RAGLE CONSTRUCTION, INC.   $2,449,020.75 3
-11.56% | -$320,206.15
22.51% | $449,936.05
14.88% | $317,292.50
SOUTHERN ROAD & BRIDGE, LLC   $3,111,918.00 4
12.37% | $342,691.10
55.67% | $1,112,833.30
27.07% | $662,897.25
FNH CONSTRUCTION, LLC   $3,307,010.00 5
19.42% | $537,783.10
65.43% | $1,307,925.30
6.27% | $195,092.00
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC   $3,375,995.00 6
21.91% | $606,768.10
68.88% | $1,376,910.30
2.09% | $68,985.00
Subcontractor Percentage Amount
JB PINNACLE GROUP, LLC 8.24% $164,724.58
DEPENDABLE FENCE 3.71% $74,166.04
TEXAS CURB CUT 1.35% $26,987.64
Total: 13.30% $265,878.26

Bid Items

Items: 36, 0 filtered
ECTOR IH 20  |  ODESSA  |  0004-07-139  |  11/01/2023  |  $2,769,227  |  BR 2024(304)  |  BRIDGE MAINT  |  180 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate SCOTT TUCKER CONSTRUCTION COMPANY, LLC SCR CIVIL CONSTRUCTION, LLC RAGLE CONSTRUCTION, INC. SOUTHERN ROAD & BRIDGE, LLC FNH CONSTRUCTION, LLC BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
428 6001 PENETRATING CONCRETE SURFACE TREATMENT SY 17,162.000 $13.000 $9.240 $20.000 $6.000 $21.000 $25.000 $30.000
429 6002 CONC STR REPAIR (EPOXY MORTAR) SF 295.000 $300.000 $235.680 $213.000 $190.000 $424.000 $650.000 $500.000
429 6007 CONC STR REPAIR (VERTICAL & OVERHEAD) SF 2,004.000 $250.000 $182.400 $190.000 $160.000 $300.000 $500.000 $400.000
429 6009 CONC STR REPAIR (STANDARD) SF 10.000 $350.000 $230.780 $185.000 $300.000 $285.000 $500.000 $1,000.000
432 6001 RIPRAP (CONC)(4 IN) CY 75.000 $2,000.000 $745.210 $756.000 $646.000 $595.000 $650.000 $1,000.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 56.000 $550.000 $1,160.940 $1,235.000 $700.000 $950.000 $650.000 $1,000.000
438 6004 CLEANING AND SEALING EXIST JOINTS(CL7) LF 1,038.000 $45.000 $53.640 $50.000 $49.000 $52.000 $100.000 $100.000
451 6024 RETROFIT RAIL (TY SSTR) LF 1,012.000 $350.000 $326.890 $307.500 $275.000 $225.000 $200.000 $400.000
500 6001 MOBILIZATION LS 1.000 $251,747.900 $199,908.000 $201,800.000 $240,000.000 $333,000.000 $325,000.000 $350,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 9.000 $40,000.000 $9,972.140 $3,900.000 $60,000.000 $18,000.000 $12,500.000 $2,000.000
506 6042 BIODEG EROSN CONT LOGS (INSTL) (18") LF 4,755.000 $20.000 $5.830 $10.900 $9.500 $8.000 $18.000 $15.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 4,755.000 $2.500 $1.600 $1.150 $1.000 $1.000 $9.000 $3.000
510 6003 ONE-WAY TRAF CONT (PORT TRAF SIG) MO 1.000 $10,000.000 $7,045.440 $10,500.000 $10,000.000 $9,500.000 $8,500.000 $7,000.000
512 6001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) LF 860.000 $90.000 $49.710 $24.000 $120.000 $95.000 $110.000 $100.000
512 6025 PORT CTB (MOVE)(SGL SLP)(TY 1) LF 860.000 $12.000 $16.450 $24.000 $7.000 $35.000 $40.000 $35.000
512 6049 PORT CTB (REMOVE)(SGL SLP)(TY 1) LF 860.000 $25.000 $20.170 $24.000 $18.000 $35.000 $40.000 $30.000
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 925.000 $40.000 $42.800 $42.500 $32.250 $50.000 $50.000 $45.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $3,000.000 $4,617.830 $3,780.000 $2,775.000 $4,500.000 $4,000.000 $4,000.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 2.000 $1,800.000 $2,222.130 $1,941.000 $1,250.000 $2,500.000 $2,500.000 $2,500.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 925.000 $3.500 $6.140 $6.000 $3.000 $8.000 $3.000 $8.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 1.000 $180.000 $1,354.270 $345.000 $300.000 $450.000 $1,000.000 $600.000
542 6003 REMOVE DOWNSTREAM ANCHOR TERMINAL EA 2.000 $250.000 $827.130 $345.000 $300.000 $450.000 $1,000.000 $600.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 2.000 $3,000.000 $4,057.130 $4,042.000 $3,300.000 $5,000.000 $5,000.000 $4,500.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 1.000 $350.000 $1,354.270 $350.000 $300.000 $500.000 $2,500.000 $1,650.000
545 6003 CRASH CUSH ATTEN (MOVE & RESET) EA 1.000 $3,000.000 $3,914.270 $4,000.000 $500.000 $1,850.000 $6,500.000 $2,500.000
545 6005 CRASH CUSH ATTEN (REMOVE) EA 1.000 $2,500.000 $2,054.270 $3,000.000 $663.000 $2,000.000 $2,500.000 $2,000.000
545 6019 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 1.000 $15,000.000 $13,085.670 $9,000.000 $20,000.000 $15,000.000 $30,000.000 $15,000.000
658 6013 INSTL DEL ASSM (D-SW)SZ (BRF)CTB EA 44.000 $30.000 $61.980 $37.000 $50.000 $75.000 $100.000 $55.000
658 6015 INSTL DEL ASSM (D-SW)SZ (BRF)GF1 EA 34.000 $30.000 $34.000 $20.000 $18.500 $75.000 $100.000 $50.000
658 6026 INSTL DEL ASSM (D-SY)SZ (BRF)CTB EA 44.000 $35.000 $61.980 $31.000 $50.000 $75.000 $100.000 $50.000
658 6028 INSTL DEL ASSM (D-SY)SZ (BRF)GF1 EA 16.000 $30.000 $51.450 $20.000 $18.500 $75.000 $100.000 $50.000
662 6092 WK ZN PAV MRK REMOV (W)36"(YLD TRI) EA 2.000 $1.500 $513.570 $2,300.000 $250.000 $1,500.000 $1,500.000 $500.000
780 6002 CNC CRACK REPAIR (DISCRETE)(INJECT) LF 245.000 $125.000 $176.590 $90.000 $105.000 $222.000 $100.000 $150.000
4207 6003 STEEL BRIDGE ZONE PAINTING REF STR #3 EA 3.000 $120,000.000 $89,783.580 $98,900.000 $133,000.000 $238,500.000 $100,000.000 $150,000.000
6185 6002 TMA (STATIONARY) DAY 177.000 $300.000 $309.140 $300.000 $400.000 $300.000 $250.000 $300.000
7306 6001 BRIDGE SUBSTRUCTURE CLEANING (ABUT) EA 4.000 $500.000 $3,491.070 $4,425.000 $2,100.000 $2,500.000 $10,000.000 $2,500.000
Totals: $2,769,226.90 $1,999,084.70 $2,131,728.25 $2,449,020.75 $3,111,918.00 $3,307,010.00 $3,375,995.00