EASTLAND US 183 (0127-02-148)

Items: 20

County: EASTLAND
Length: N/A
Highway: US 183
District: BROWNWOOD
Control Number: 0127-02-148
DBE Goal: N/A
Project: F 2021(747)
Guaranty: N/A
Time: 39 WORKING DAYS
Engineer's Estimate: $1,483,634.80
Date: 07/01/2021 (4 years ago)
Contract Number: N/A
Type: RESURFACE ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (9)
E
Engineer's Estimate
$1,483,634.80
$1,372,072.30
Over/Under Est: -7.52% -$111,562.50
Over/Under Est: -6.25% -$92,753.35
Amt Left: 1.37% $18,809.15
$1,446,353.77
Over/Under Est: -2.51% -$37,281.03
Amt Left: 5.41% $74,281.47
Delta: -3.99% -$55,472.32
$1,469,424.17
Over/Under Est: -0.96% -$14,210.63
Amt Left: 7.1% $97,351.87
Delta: -1.60% -$23,070.40
$1,613,371.16
Over/Under Est: 8.74% $129,736.36
Amt Left: 17.59% $241,298.86
Delta: -9.80% -$143,946.99
Over/Under Est: 10.86% $161,147.08
Amt Left: 19.88% $272,709.58
Delta: -1.95% -$31,410.72
$1,678,962.80
Over/Under Est: 13.17% $195,328.00
Amt Left: 22.37% $306,890.50
Delta: -2.08% -$34,180.92
Over/Under Est: 19.17% $284,354.36
Amt Left: 28.86% $395,916.86
Delta: -5.30% -$89,026.36
$1,813,669.50
Over/Under Est: 22.25% $330,034.70
Amt Left: 32.18% $441,597.20
Delta: -2.58% -$45,680.34

Bid Items & Bid Tabulations

20 Total 0 of 20
EASTLAND  |  US 183  |  BROWNWOOD  |  0127-02-148  |  07/01/2021  |  $1,483,634.80  |  F 2021(747)  |  RESURF ROADWAY  |  39 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
BLACKSMITH VENTURES LLC
A. L. HELMCAMP, INC.
DUININCK, INC.
RK HALL, LLC
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
CONTRACT PAVING CO.
LONE STAR PAVING COMPANY
GILVIN-TERRILL, LTD.
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 1,000.000 $60.000 $45.000 $55.000 $55.000 $68.000 $69.900 $77.300 $53.000 $85.000 $80.000
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 3,072.000 $10.000 $3.500 $7.000 $1.400 $4.550 $6.400 $10.630 $8.000 $20.000 $10.000
MOBILIZATION
LS 1.000 $75,000.000 $50,000.000 $50,000.000 $100,000.000 $80,000.000 $50,000.000 $123,040.000 $30,000.000 $105,000.000 $180,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $3,000.000 $5,000.000 $4,850.000 $3,250.000 $10,500.000 $5,000.000 $5,110.990 $6,000.000 $25,000.000 $40,000.000
RUMBLE STRIPS (SHOULDER)
LF 56,200.000 $0.200 $0.150 $0.170 $0.370 $0.200 $0.170 $0.120 $0.400 $0.150 $0.250
RUMBLE STRIPS (CENTERLINE)
LF 28,100.000 $0.200 $0.170 $0.200 $0.400 $0.230 $0.190 $0.130 $0.610 $0.170 $0.350
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 940.000 $1.000 $1.000 $1.000 $0.490 $1.000 $2.850 $1.170 $2.000 $1.000 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 5,620.000 $1.000 $1.000 $1.000 $0.490 $1.000 $2.860 $0.810 $2.000 $1.000 $1.000
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 225.000 $1.200 $0.500 $0.410 $0.530 $0.360 $0.400 $1.230 $10.000 $0.500 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 135.000 $6.000 $10.000 $8.000 $10.000 $7.000 $7.700 $7.370 $14.000 $9.500 $6.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 2,620.000 $0.350 $0.350 $0.400 $0.350 $0.340 $0.370 $0.610 $0.420 $0.330 $0.500
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 56,200.000 $0.350 $0.350 $0.400 $0.350 $0.340 $0.370 $0.490 $0.650 $0.330 $0.400
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 4,648.000 $0.350 $0.350 $0.400 $0.340 $0.340 $0.370 $0.610 $0.550 $0.320 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 33,300.000 $0.350 $0.350 $0.400 $0.340 $0.340 $0.370 $0.540 $0.800 $0.320 $0.440
REFL PAV MRKR TY I-C
EA 150.000 $4.000 $4.000 $4.000 $4.200 $3.450 $3.800 $4.300 $5.000 $4.000 $3.500
REFL PAV MRKR TY II-A-A
EA 663.000 $4.000 $4.000 $4.000 $4.200 $3.450 $3.800 $4.300 $8.000 $4.000 $3.500
SP MIXES SP-D SAC-B PG76-22
TON 12,961.000 $90.000 $86.000 $84.000 $87.400 $88.000 $99.260 $98.070 $97.000 $101.000 $90.000
BONDING COURSE
GAL 24,468.000 $3.000 $3.000 $3.500 $2.500 $2.700 $3.630 $2.190 $6.000 $2.650 $6.000
TMA (STATIONARY)
DAY 20.000 $250.000 $150.000 $350.000 $330.000 $200.000 $374.560 $46.920 $500.000 $500.000 $500.000
TMA (MOBILE OPERATION)
HR 48.000 $50.000 $40.000 $75.000 $65.000 $90.000 $48.400 $1.560 $200.000 $35.000 $95.000
Totals: $1,483,634.800 $1,372,072.300 $1,390,881.450 $1,446,353.770 $1,469,424.170 $1,613,371.160 $1,644,781.880 $1,678,962.800 $1,767,989.160 $1,813,669.500