DUVAL TO (0922-23-010)
Items: 48
County: DUVAL
Length: N/A
Highway: TO
District: LAREDO
Control Number: 0922-23-010
DBE Goal: 600.0%
Project: BR 2B23(173)
Guaranty: N/A
Time: 148 WORKING DAYS
Engineer's Estimate: $2,644,774.19
Date: 08/01/2024 (1 year ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
ROGELIO CHAPA
ANGEL MARTINEZ
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,644,774.19 | |||
| $2,301,233.00 |
-12.99%
-$343,541.19
|
|||
| $2,415,890.30 |
-8.65%
-$228,883.89
|
4.98%
$114,657.30
|
||
| $2,688,859.00 |
1.67%
$44,084.81
|
16.84%
$387,626.00
|
-11.30%
-$272,968.70
|
|
| $2,867,543.00 |
8.42%
$222,768.81
|
24.61%
$566,310.00
|
-6.65%
-$178,684.00
|
|
| $2,954,725.50 |
11.72%
$309,951.31
|
28.4%
$653,492.50
|
-3.04%
-$87,182.50
|
|
| $3,000,816.83 |
13.46%
$356,042.64
|
30.4%
$699,583.83
|
-1.56%
-$46,091.33
|
|
| $3,010,523.53 |
13.83%
$365,749.34
|
30.82%
$709,290.53
|
-0.32%
-$9,706.70
|
E
Engineer's Estimate
$2,644,774.19
1
Awarded
$2,301,233.00
Over/Under Est:
-12.99%
-$343,541.19
$2,415,890.30
Over/Under Est:
-8.65%
-$228,883.89
Amt Left:
4.98%
$114,657.30
$2,688,859.00
Over/Under Est:
1.67%
$44,084.81
Amt Left:
16.84%
$387,626.00
Delta:
-11.30%
-$272,968.70
$2,867,543.00
Over/Under Est:
8.42%
$222,768.81
Amt Left:
24.61%
$566,310.00
Delta:
-6.65%
-$178,684.00
$2,954,725.50
Over/Under Est:
11.72%
$309,951.31
Amt Left:
28.4%
$653,492.50
Delta:
-3.04%
-$87,182.50
$3,000,816.83
Over/Under Est:
13.46%
$356,042.64
Amt Left:
30.4%
$699,583.83
Delta:
-1.56%
-$46,091.33
$3,010,523.53
Over/Under Est:
13.83%
$365,749.34
Amt Left:
30.82%
$709,290.53
Delta:
-0.32%
-$9,706.70
| Subcontractor | Percentage | Amount |
|---|---|---|
| GREGORY PILE DRIVING, INC. | 7.33% | $172,806.84 |
| J. R. (JOE) RAMON & SONS, INC. | 3.61% | $85,106.78 |
| SOIL TECH ADVANCE INC. | 2.98% | $70,254.35 |
| TORO BRAVO CONSTRUCTION, LLC | 1.89% | $44,557.29 |
| HIGHWAY BARRICADES AND SERVICES, LLC | 1.13% | $26,640.07 |
| DEPENDABLE FENCE | 0.33% | $7,779.84 |
| PENHALL COMPANY | 0.27% | $6,365.33 |
| Total: | 17.54% | $413,510.50 |
Bid Items & Bid Tabulations
48
Total
0 of 48