Job Info for 0795-02-017

County: DONLEY Highway: FM 1260 Date: 07/10/2024 (4 months ago) Engineer's Estimate: $7,119,726 Control Number: 0795-02-017
Project: BR 2B24(268) District: CHILDRESS Time: 270 WORKING DAYS Type: BRIDGE REPLACEMENT
Bidder's List
Informational:
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $7,119,726.35
C. E. BARKER, LTD.   $6,672,833.23 1
-6.28% | -$446,893.12
COPPELL CONSTRUCTION CO., INC.   $7,035,909.50 2
-1.18% | -$83,816.85
5.44% | $363,076.27
EARTH BUILDERS, L.P.   $7,774,096.80 3
9.19% | $654,370.45
16.5% | $1,101,263.57
10.49% | $738,187.30
ALTUS CONSTRUCTION LLC   $7,969,149.18 4
11.93% | $849,422.83
19.43% | $1,296,315.95
2.51% | $195,052.38
GILVIN-TERRILL, LTD.   $8,264,693.00 5
16.08% | $1,144,966.65
23.86% | $1,591,859.77
3.71% | $295,543.82
Subcontractor Percentage Amount
HB FARMER FOUNDATION, LLC 16.00% $1,067,653.32
BLACKSMITH VENTURES LLC 3.60% $240,222.00
HJC FARMS, INC. 2.26% $150,806.03
TORO BRAVO CONSTRUCTION, LLC 1.78% $118,776.43
SOUTH TEXAS TRAFFIC ALLIANCE INC. 0.83% $55,384.52
TRP CONSTRUCTION GROUP, LLC 0.67% $44,707.98
PROFESSIONAL TRAFFIC CONTROL LLC 0.19% $12,678.38
Total: 25.33% $1,690,228.66

Bid Items

Items: 53, 0 filtered
DONLEY FM 1260  |  CHILDRESS  |  0795-02-017  |  07/10/2024  |  $7,119,726  |  BR 2B24(268)  |  BRIDGE REPL  |  270 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate C. E. BARKER, LTD. COPPELL CONSTRUCTION CO., INC. EARTH BUILDERS, L.P. ALTUS CONSTRUCTION LLC GILVIN-TERRILL, LTD.
106 6001 OBLITERATING ABANDONED ROAD STA 22.000 $2,500.000 $14,750.000 $2,500.000 $2,000.000 $3,120.770 $1,000.000
110 6001 EXCAVATION (ROADWAY) CY 5,746.000 $25.000 $30.850 $23.000 $25.000 $24.960 $25.000
110 6002 EXCAVATION (CHANNEL) CY 3,827.000 $20.000 $34.550 $30.000 $25.000 $19.340 $25.000
112 6002 SUBGRADE WIDENING (DENS CONT) STA 6.000 $4,200.000 $4,139.490 $15,000.000 $4,500.000 $1,728.430 $4,000.000
132 6002 EMBANKMENT (FINAL)(DENS CONT)(TY A) CY 3,291.000 $52.000 $21.030 $33.000 $30.000 $32.500 $25.000
134 6004 BACKFILL (TY A OR B) STA 6.000 $600.000 $827.900 $3,000.000 $300.000 $288.070 $2,000.000
150 6002 BLADING HR 14.000 $250.000 $147.840 $250.000 $150.000 $124.830 $175.000
164 6034 DRILL SEEDING (PERM) (RURAL) (SANDY) AC 2.690 $1,500.000 $8,574.650 $1,950.000 $2,200.000 $1,920.470 $1,500.000
164 6042 DRILL SEEDING (TEMP) (WARM) AC 1.350 $1,500.000 $1,507.960 $1,800.000 $2,000.000 $1,920.470 $1,500.000
164 6044 DRILL SEEDING (TEMP) (COOL) AC 1.350 $1,500.000 $1,951.470 $1,800.000 $2,000.000 $1,920.470 $1,500.000
168 6001 VEGETATIVE WATERING MG 105.000 $50.000 $59.140 $50.000 $50.000 $24.010 $55.000
247 6064 FL BS (CMP IN PLC)(TY A GR 4) (6") SY 8,963.000 $30.000 $19.510 $45.000 $55.000 $30.810 $30.000
310 6009 PRIME COAT (MC-30) GAL 1,793.000 $24.000 $17.740 $15.000 $10.000 $12.480 $7.000
316 6024 ASPH (CRS-2P) GAL 6,491.000 $12.000 $23.650 $20.000 $15.000 $21.770 $7.500
316 6080 AGGR(TY-B GR-5 SAC-A) CY 130.000 $250.000 $674.140 $250.000 $500.000 $133.510 $210.000
401 6001 FLOWABLE BACKFILL CY 144.000 $320.000 $231.810 $390.000 $450.000 $281.960 $800.000
416 6004 DRILL SHAFT (36 IN) LF 3,060.000 $350.000 $461.670 $370.000 $450.000 $483.430 $400.000
420 6013 CL C CONC (ABUT) CY 75.700 $2,400.000 $1,487.220 $1,750.000 $2,500.000 $2,277.580 $2,000.000
420 6029 CL C CONC (CAP) CY 163.900 $2,500.000 $1,521.430 $1,500.000 $2,500.000 $3,006.140 $2,000.000
420 6037 CL C CONC (COLUMN) CY 49.000 $5,200.000 $1,571.660 $2,500.000 $2,500.000 $2,761.310 $2,000.000
422 6001 REINF CONC SLAB SF 25,840.000 $50.000 $34.610 $45.000 $46.000 $52.220 $40.000
422 6015 APPROACH SLAB CY 107.100 $1,300.000 $955.420 $1,500.000 $2,000.000 $1,240.490 $2,000.000
425 6035 PRESTR CONC GIRDER (TX28) LF 2,380.000 $200.000 $249.890 $250.000 $260.000 $272.220 $250.000
425 6036 PRESTR CONC GIRDER (TX34) LF 634.000 $200.000 $252.950 $315.000 $290.000 $352.840 $250.000
432 6035 RIPRAP (STONE PROTECTION)(24 IN) CY 524.000 $280.000 $270.750 $365.000 $240.000 $314.510 $600.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 60.000 $750.000 $610.140 $750.000 $650.000 $755.310 $800.000
450 6023 RAIL (TY SSTR) LF 1,588.000 $150.000 $140.320 $225.000 $160.000 $112.330 $160.000
454 6018 SEALED EXPANSION JOINT (4 IN) (SEJ - M) LF 198.000 $250.000 $254.280 $285.000 $230.000 $317.760 $350.000
496 6010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) EA 1.000 $205,000.000 $43,944.770 $70,000.000 $100,000.000 $69,336.760 $200,000.000
496 6011 REMOV STR (BRIDGE 500 - 999 FT LENGTH) EA 1.000 $570,000.000 $191,539.880 $175,000.000 $550,000.000 $420,775.620 $900,000.000
500 6001 MOBILIZATION LS 1.000 $502,823.350 $630,000.000 $650,000.000 $800,000.000 $788,946.690 $810,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 15.000 $3,500.000 $5,377.100 $13,015.000 $2,000.000 $20,294.280 $40,000.000
506 6001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 400.000 $75.000 $59.140 $47.500 $75.000 $57.610 $45.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 400.000 $20.000 $29.570 $13.000 $15.000 $19.200 $15.000
506 6042 BIODEG EROSN CONT LOGS (INSTL) (18") LF 700.000 $9.000 $5.910 $7.500 $12.000 $10.240 $8.000
533 6001 RUMBLE STRIPS (SHOULDER) LF 5,220.000 $2.500 $2.370 $2.450 $0.010 $0.380 $1.450
533 6002 RUMBLE STRIPS (CENTERLINE) LF 2,610.000 $2.500 $2.370 $1.500 $0.010 $0.510 $1.450
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 1,000.000 $30.000 $39.030 $35.000 $40.000 $42.250 $35.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 8.000 $2,800.000 $3,607.270 $2,500.000 $2,600.000 $3,904.960 $3,000.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 8.000 $3,200.000 $3,873.380 $3,500.000 $4,000.000 $4,193.030 $4,000.000
552 6003 WIRE FENCE (TY C) LF 1,876.000 $25.000 $8.280 $35.000 $20.000 $34.570 $27.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 40.000 $30.000 $41.390 $25.000 $35.000 $44.810 $35.000
666 6174 REFL PAV MRK TY II (W) 6" (SLD) LF 250.000 $5.000 $1.180 $1.000 $1.000 $1.880 $1.000
666 6182 REFL PAV MRK TY II (W) 24" (SLD) LF 24.000 $25.000 $5.910 $5.000 $5.000 $5.630 $5.000
666 6210 REFL PAV MRK TY II (Y) 6" (SLD) LF 11,200.000 $0.800 $0.890 $0.750 $0.750 $0.900 $0.750
666 6225 PAVEMENT SEALER 6" LF 2,160.000 $3.500 $2.370 $2.000 $2.500 $1.550 $2.000
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 6,820.000 $2.250 $3.550 $3.000 $3.500 $1.330 $3.000
666 6318 RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL) LF 853.000 $4.000 $3.550 $3.000 $3.500 $1.340 $3.000
672 6009 REFL PAV MRKR TY II-A-A EA 468.000 $23.000 $11.830 $10.000 $15.000 $5.120 $10.000
678 6002 PAV SURF PREP FOR MRK (6") LF 2,160.000 $1.350 $2.370 $2.000 $2.500 $0.420 $2.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 6.000 $22,000.000 $16,557.940 $15,000.000 $18,000.000 $20,485.040 $18,500.000
6185 6002 TMA (STATIONARY) DAY 69.000 $320.000 $1,182.710 $300.000 $250.000 $216.050 $800.000
6185 6003 TMA (MOBILE OPERATION) HR 27.000 $130.000 $473.080 $250.000 $120.000 $108.030 $95.000
Totals: $7,119,726.35 $6,672,833.26 $7,035,909.50 $7,774,096.80 $7,969,149.21 $8,264,693.00