DONLEY US 287 (0042-06-076)
Items: 44
County: DONLEY
Length: N/A
Highway: US 287
District: CHILDRESS
Control Number: 0042-06-076
DBE Goal: N/A
Project: F 2024(069)
Guaranty: N/A
Time: 95 WORKING DAYS
Engineer's Estimate: $6,658,832.52
Date: 09/06/2023 (2 years ago)
Contract Number: N/A
Type: HIGHWAY IMPROVEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$6,658,832.52 | |||
| $6,446,300.55 |
-3.19%
-$212,531.97
|
|||
| $6,799,859.07 |
2.12%
$141,026.55
|
5.48%
$353,558.52
|
||
| $6,929,166.19 |
4.06%
$270,333.67
|
7.49%
$482,865.64
|
-1.90%
-$129,307.12
|
|
| $7,618,812.77 |
14.42%
$959,980.25
|
18.19%
$1,172,512.22
|
-9.95%
-$689,646.58
|
|
| $7,735,503.39 |
16.17%
$1,076,670.87
|
20%
$1,289,202.84
|
-1.53%
-$116,690.62
|
E
Engineer's Estimate
$6,658,832.52
1
Awarded
$6,446,300.55
Over/Under Est:
-3.19%
-$212,531.97
$6,799,859.07
Over/Under Est:
2.12%
$141,026.55
Amt Left:
5.48%
$353,558.52
$6,929,166.19
Over/Under Est:
4.06%
$270,333.67
Amt Left:
7.49%
$482,865.64
Delta:
-1.90%
-$129,307.12
$7,618,812.77
Over/Under Est:
14.42%
$959,980.25
Amt Left:
18.19%
$1,172,512.22
Delta:
-9.95%
-$689,646.58
$7,735,503.39
Over/Under Est:
16.17%
$1,076,670.87
Amt Left:
20%
$1,289,202.84
Delta:
-1.53%
-$116,690.62
| Subcontractor | Percentage | Amount |
|---|---|---|
| TRP CONSTRUCTION GROUP, LLC | 3.00% | $188,399.68 |
| BARRICADES UNLIMITED | 0.47% | $29,515.95 |
| SURFACE PREPARATION TECHNOLOGIES, LLC | 0.34% | $21,351.96 |
| WOLFE CONSTRUCTION GROUP, INCORPORATED | 0.25% | $15,699.97 |
| Total: | 4.06% | $254,967.56 |
Bid Items & Bid Tabulations
44
Total