DONLEY US 287 (0042-06-076)

Items: 44

County: DONLEY
Length: N/A
Highway: US 287
District: CHILDRESS
Control Number: 0042-06-076
DBE Goal: N/A
Project: F 2024(069)
Guaranty: N/A
Time: 95 WORKING DAYS
Engineer's Estimate: $6,658,832.52
Date: 09/06/2023 (2 years ago)
Contract Number: N/A
Type: HIGHWAY IMPROVEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$6,658,832.52
$6,446,300.55
Over/Under Est: -3.19% -$212,531.97
$6,799,859.07
Over/Under Est: 2.12% $141,026.55
Amt Left: 5.48% $353,558.52
$6,929,166.19
Over/Under Est: 4.06% $270,333.67
Amt Left: 7.49% $482,865.64
Delta: -1.90% -$129,307.12
Over/Under Est: 14.42% $959,980.25
Amt Left: 18.19% $1,172,512.22
Delta: -9.95% -$689,646.58
Over/Under Est: 16.17% $1,076,670.87
Amt Left: 20% $1,289,202.84
Delta: -1.53% -$116,690.62
Subcontractor Percentage Amount
TRP CONSTRUCTION GROUP, LLC 3.00% $188,399.68
BARRICADES UNLIMITED 0.47% $29,515.95
SURFACE PREPARATION TECHNOLOGIES, LLC 0.34% $21,351.96
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.25% $15,699.97
Total: 4.06% $254,967.56

Bid Items & Bid Tabulations

44 Total 0 of 44
DONLEY  |  US 287  |  CHILDRESS  |  0042-06-076  |  09/06/2023  |  $6,658,832.52  |  F 2024(069)  |  HWY IMPRV  |  95 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. LEE MILLIGAN, INC.
DUININCK, INC.
RK HALL, LLC
L A FULLER & SONS CONSTRUCTION, LTD.
KIEWIT INFRASTRUCTURE SOUTH CO.
BACKFILL (TY A OR B)
STA 616.900 $140.000 $127.000 $255.000 $230.000 $155.000 $288.550
DRILL SEEDING (PERM) (RURAL) (SANDY)
AC 28.000 $650.000 $600.000 $610.000 $621.500 $628.800 $653.180
VEGETATIVE WATERING
MG 2,290.000 $20.000 $20.000 $27.500 $30.000 $35.900 $69.470
EMULS ASPH (EROSN CONT)(CSS-1H)
GAL 27,218.000 $4.000 $3.850 $3.800 $3.690 $4.600 $4.850
PLANE ASPH CONC PAV (2")
SY 65,551.000 $2.000 $2.800 $2.700 $2.750 $2.700 $2.360
MOBILIZATION
LS 1.000 $377,500.000 $644,000.000 $650,000.000 $207,874.980 $751,230.000 $815,249.690
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $22,000.000 $35,100.000 $22,500.000 $20,324.460 $4,732.100 $35,000.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 5,640.000 $6.000 $5.250 $5.100 $5.170 $11.300 $5.480
RUMBLE STRIPS (SHOULDER)
LF 101,721.000 $0.200 $0.300 $0.150 $0.070 $0.100 $0.160
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 5,917.000 $2.400 $1.550 $1.550 $2.620 $4.100 $2.330
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 656.000 $3.000 $1.600 $1.550 $2.620 $7.300 $2.330
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 736.000 $1.400 $2.100 $2.150 $2.200 $2.200 $2.330
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 6,719.000 $1.400 $1.050 $1.100 $1.100 $1.100 $1.170
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 392.000 $12.000 $8.400 $8.600 $8.750 $8.750 $9.270
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 13.000 $180.000 $158.500 $160.000 $165.000 $165.000 $174.960
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 10.000 $250.000 $211.000 $215.000 $220.000 $220.000 $233.280
REF PAV MRK TY I(W)18"(YLD TRI)(100MIL)
EA 148.000 $40.000 $63.350 $65.000 $66.000 $66.000 $69.980
REFL PAV MRK TY II (W) 6" (BRK)
LF 20,463.000 $0.350 $0.200 $0.170 $0.180 $0.180 $0.190
REFL PAV MRK TY II (W) 6" (SLD)
LF 65,445.000 $0.350 $0.200 $0.170 $0.180 $0.180 $0.190
REFL PAV MRK TY II (W) 8" (DOT)
LF 736.000 $0.550 $0.200 $0.220 $0.220 $0.220 $0.230
REFL PAV MRK TY II (Y) 6" (BRK)
LF 3,233.000 $0.200 $0.200 $0.170 $0.180 $0.180 $0.190
REFL PAV MRK TY II (Y) 6" (SLD)
LF 74,839.000 $0.200 $0.200 $0.170 $0.180 $0.180 $0.190
PAVEMENT SEALER 6"
LF 3,750.000 $4.500 $0.900 $0.920 $0.940 $0.940 $0.990
PAVEMENT SEALER 24"
LF 392.000 $2.000 $5.300 $5.400 $5.500 $5.500 $5.830
PAVEMENT SEALER (ARROW)
EA 6.000 $1,200.000 $105.600 $110.000 $110.000 $110.000 $116.640
PAVEMENT SEALER (WORD)
EA 3.000 $1,500.000 $158.500 $160.000 $165.000 $165.000 $174.960
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 20,463.000 $0.750 $0.750 $0.760 $0.770 $0.770 $0.820
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 65,445.000 $0.750 $0.750 $0.760 $0.770 $0.770 $0.820
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 3,233.000 $0.750 $0.750 $0.760 $0.770 $0.770 $0.820
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 74,839.000 $0.750 $0.750 $0.760 $0.770 $0.770 $0.820
REFL PAV MRKR TY I-C
EA 647.000 $5.000 $4.750 $4.850 $4.950 $4.950 $5.250
REFL PAV MRKR TY II-A-A
EA 140.000 $3.550 $5.300 $5.400 $5.500 $5.500 $5.830
REFL PAV MRKR TY II-C-R
EA 990.000 $6.000 $4.750 $4.850 $4.950 $4.950 $5.250
ELIM EXT PAV MRK & MRKS (4")
LF 3,750.000 $1.200 $1.100 $1.100 $1.100 $1.100 $1.170
ELIM EXT PAV MRK & MRKS (24")
LF 392.000 $19.000 $3.150 $3.250 $3.300 $3.300 $3.500
ELIM EXT PAV MRK & MRKS (ARROW)
EA 6.000 $65.000 $110.000 $110.000 $110.000 $110.000 $116.640
PAV SURF PREP FOR MRK (6")
LF 3,750.000 $1.400 $0.350 $0.380 $0.390 $0.380 $0.410
PAV SURF PREP FOR MRK (24")
LF 392.000 $0.810 $3.150 $3.250 $3.300 $3.300 $3.500
PAV SURF PREP FOR MRK (ARROW)
EA 6.000 $40.000 $80.000 $81.000 $82.500 $82.500 $87.480
PAV SURF PREP FOR MRK (WORD)
EA 3.000 $40.000 $106.000 $110.000 $110.000 $110.000 $116.640
SP MIXES SP-C SAC-A PG70-28
TON 37,510.000 $140.000 $125.400 $135.000 $149.550 $153.600 $148.460
TACK COAT
GAL 34,102.000 $5.000 $4.750 $4.550 $5.770 $7.200 $5.580
TMA (STATIONARY)
DAY 22.000 $250.000 $450.000 $270.000 $552.650 $659.800 $557.290
TMA (MOBILE OPERATION)
HR 128.000 $70.000 $83.000 $110.000 $83.930 $71.850 $105.800
Totals: $6,658,832.520 $6,446,300.550 $6,799,859.070 $6,929,166.190 $7,618,812.770 $7,735,503.395