PREPARING ROW
|
STA
|
6.000
|
$3,000.000
|
$4,000.000
|
$13,657.540
|
$16,650.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
837.000
|
$15.000
|
$8.000
|
$16.760
|
$73.260
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
5,375.000
|
$10.000
|
$15.000
|
$17.250
|
$73.260
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY C)
|
CY
|
1,035.000
|
$20.000
|
$8.000
|
$50.190
|
$36.630
|
|
|
BLADING
|
HR
|
20.000
|
$100.000
|
$65.000
|
$108.740
|
$102.600
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
7,106.000
|
$1.500
|
$2.000
|
$3.050
|
$2.190
|
|
|
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
|
SY
|
7,106.000
|
$2.000
|
$0.500
|
$0.350
|
$0.420
|
|
|
CELL FBR MLCH SEED(TEMP)(WARM)
|
SY
|
1,777.000
|
$1.000
|
$0.750
|
$0.500
|
$0.300
|
|
|
CELL FBR MLCH SEED(TEMP)(COOL)
|
SY
|
1,777.000
|
$1.000
|
$0.750
|
$0.500
|
$0.340
|
|
|
VEGETATIVE WATERING
|
MG
|
60.000
|
$100.000
|
$45.000
|
$37.620
|
$73.260
|
|
|
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
|
CY
|
598.000
|
$75.000
|
$95.000
|
$89.370
|
$79.390
|
|
|
FL BS (RDWY DEL) (TY E GR 1-2)
|
TON
|
254.000
|
$50.000
|
$32.000
|
$54.080
|
$41.700
|
|
|
REWORK BS MTL (TY C) (6") (ORD COMP)
|
SY
|
605.000
|
$5.000
|
$9.000
|
$16.840
|
$3.990
|
|
|
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
|
TON
|
33.000
|
$165.000
|
$165.000
|
$186.950
|
$210.000
|
|
|
LIME TRT (SUBGRADE)(6")
|
SY
|
2,862.000
|
$2.000
|
$3.500
|
$16.760
|
$5.700
|
|
|
PRIME COAT (MC-30)
|
GAL
|
620.000
|
$5.000
|
$5.000
|
$5.000
|
$8.760
|
|
|
AGGR(TY-PB GR-4 SAC-B)
|
CY
|
88.000
|
$100.000
|
$125.000
|
$135.000
|
$193.770
|
|
|
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
|
GAL
|
3,528.000
|
$4.000
|
$4.000
|
$4.250
|
$6.480
|
|
|
D-GR HMA TY-B PG70-22
|
TON
|
326.000
|
$100.000
|
$96.000
|
$107.000
|
$118.410
|
|
|
D-GR HMA TY-D SAC-B PG70-22
|
TON
|
682.000
|
$90.000
|
$96.000
|
$107.000
|
$118.410
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
|
SY
|
250.000
|
$75.000
|
$100.000
|
$110.000
|
$161.340
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
1,911.000
|
$3.000
|
$4.000
|
$3.200
|
$3.330
|
|
|
CEM STABIL BKFL
|
CY
|
576.000
|
$175.000
|
$135.000
|
$166.000
|
$137.770
|
|
|
TEMPORARY SPL SHORING
|
SF
|
2,643.000
|
$15.000
|
$40.000
|
$14.300
|
$29.030
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
152.000
|
$75.000
|
$45.000
|
$45.520
|
$73.080
|
|
|
DRILL SHAFT (42 IN)
|
LF
|
959.000
|
$200.000
|
$210.000
|
$213.090
|
$229.590
|
|
|
DRILL SHAFT (60 IN)
|
LF
|
560.000
|
$400.000
|
$550.000
|
$596.250
|
$688.020
|
|
|
CL C CONC (ABUT)
|
CY
|
134.400
|
$750.000
|
$700.000
|
$814.460
|
$1,010.830
|
|
|
CL C CONC (CAP)
|
CY
|
115.200
|
$800.000
|
$950.000
|
$777.180
|
$1,127.440
|
|
|
CL C CONC (COLUMN)
|
CY
|
90.700
|
$900.000
|
$850.000
|
$957.480
|
$1,078.680
|
|
|
CL C CONC (TIE BEAM)
|
CY
|
94.800
|
$2,500.000
|
$550.000
|
$689.470
|
$880.400
|
|
|
REINF CONC SLAB
|
SF
|
36,400.000
|
$15.000
|
$14.000
|
$17.000
|
$23.940
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
147.000
|
$500.000
|
$375.000
|
$513.610
|
$532.540
|
|
|
RIPRAP (STONE PROTECTION)(18 IN)
|
CY
|
1,500.000
|
$150.000
|
$125.000
|
$140.500
|
$110.000
|
|
|
ELASTOMERIC BEARING (E5)
|
EA
|
8.000
|
$2,000.000
|
$1,600.000
|
$3,477.190
|
$2,652.960
|
|
|
ELASTOMERIC BEARING (F5)
|
EA
|
8.000
|
$2,000.000
|
$1,600.000
|
$3,477.190
|
$2,523.210
|
|
|
SLIDING ELASTOMERIC BEARING (ES 4)
|
EA
|
16.000
|
$1,900.000
|
$1,700.000
|
$2,846.300
|
$2,204.470
|
|
|
STR STEEL (PLATE GIRDER)
|
LB
|
1,546,000.000
|
$1.850
|
$1.600
|
$1.360
|
$1.820
|
|
|
RAIL (TY T223)
|
LF
|
1,116.000
|
$90.000
|
$95.000
|
$94.040
|
$132.200
|
|
|
SEALED EXPANSION JOINT (5 IN) (SEJ - A)
|
LF
|
139.000
|
$120.000
|
$90.000
|
$113.890
|
$113.620
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
132.000
|
$85.000
|
$65.000
|
$142.770
|
$92.070
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$1,200.000
|
$1,000.000
|
$1,379.710
|
$1,688.490
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
1.000
|
$100,000.000
|
$220,000.000
|
$400,000.000
|
$171,041.860
|
|
|
REMOV STR (SMALL)
|
EA
|
3.000
|
$500.000
|
$1,000.000
|
$1,966.830
|
$1,142.950
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$500,000.000
|
$610,000.000
|
$722,000.000
|
$1,538,326.690
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
18.000
|
$3,500.000
|
$3,000.000
|
$1,000.000
|
$1,419.920
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
50.000
|
$50.000
|
$60.000
|
$56.410
|
$30.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
50.000
|
$10.000
|
$35.000
|
$35.900
|
$10.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
1,320.000
|
$3.000
|
$4.000
|
$3.590
|
$2.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
1,320.000
|
$1.000
|
$1.200
|
$1.230
|
$0.600
|
|
|
DRIVEWAYS (ACP)
|
SY
|
130.000
|
$60.000
|
$55.000
|
$47.930
|
$35.040
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
1,660.000
|
$1.000
|
$3.600
|
$10.650
|
$0.970
|
|
|
RUMBLE STRIPS (CENTERLINE)
|
LF
|
830.000
|
$2.000
|
$4.000
|
$10.650
|
$0.970
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
275.000
|
$30.000
|
$27.850
|
$25.490
|
$22.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$1,500.000
|
$1,860.000
|
$1,600.000
|
$1,800.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
325.000
|
$5.000
|
$5.000
|
$1.540
|
$1.500
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
4.000
|
$250.000
|
$200.000
|
$128.210
|
$200.000
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$200.000
|
$250.000
|
$153.850
|
$250.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$2,400.000
|
$2,940.000
|
$2,805.130
|
$2,300.000
|
|
|
MAILBOX INSTALL-S (WC-POST) TY 3
|
EA
|
1.000
|
$350.000
|
$200.000
|
$194.360
|
$200.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
4.000
|
$450.000
|
$450.000
|
$371.900
|
$300.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(T)
|
EA
|
2.000
|
$500.000
|
$525.000
|
$489.390
|
$300.000
|
|
|
RELOCATE SM RD SN SUP&AM TY TWT
|
EA
|
5.000
|
$450.000
|
$450.000
|
$348.210
|
$200.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
3.000
|
$250.000
|
$250.000
|
$102.560
|
$75.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
22.000
|
$15.000
|
$17.000
|
$10.260
|
$5.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
12.000
|
$50.000
|
$21.000
|
$14.100
|
$10.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
|
LF
|
2,700.000
|
$0.500
|
$1.500
|
$2.320
|
$0.750
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
|
LF
|
100.000
|
$2.000
|
$2.500
|
$3.870
|
$0.750
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
|
LF
|
2,308.000
|
$0.500
|
$1.500
|
$2.320
|
$0.750
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
18.000
|
$24.000
|
$50.000
|
$77.310
|
$15.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
34.000
|
$25.000
|
$50.000
|
$77.310
|
$10.000
|
|
|
NO. OF WORKING DAYS
|
$/D
|
20,000.000
|
$430.000
|
$330.000
|
$370.000
|
$350.000
|
|
|
TEMP CONSTRUCTION ACCESS
|
LS
|
1.000
|
$400,000.000
|
$235,000.000
|
$50,000.000
|
$1,260,517.300
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
5.000
|
$8,000.000
|
$18,000.000
|
$8,602.170
|
$6,500.000
|
|
Totals: |
$15,099,265.000
|
$12,717,082.250
|
$13,587,698.672
|
$16,397,597.306
|