Job Info for 0143-08-097

County: DEWITT Highway: US 87 Date: 02/03/2017 (7 years ago) Engineer's Estimate: $3,203,872 Control Number: 0143-08-097
Project: NH 2017(700) District: YOAKUM Time: 148 WORKING DAYS Type: WIDEN ROADWAY

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,203,871.95
HUNTER INDUSTRIES, LTD.   $3,015,734.94 1
-5.87% | -$188,137.01
DEAN WORD COMPANY, LTD.   $3,058,795.87 2
-4.53% | -$145,076.08
1.43% | $43,060.93
CURRAN CONTRACTING COMPANY   $3,315,452.70 3
3.48% | $111,580.75
9.94% | $299,717.76
8.39% | $256,656.83
J. CARROLL WEAVER, INC.   $3,812,200.46 4
18.99% | $608,328.51
26.41% | $796,465.52
14.98% | $496,747.76

Bid Items

Items: 90, 0 filtered
DEWITT US 87  |  YOAKUM  |  0143-08-097  |  02/03/2017  |  $3,203,872  |  NH 2017(700)  |  WIDEN ROADWAY  |  148 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate HUNTER INDUSTRIES, LTD. DEAN WORD COMPANY, LTD. CURRAN CONTRACTING COMPANY J. CARROLL WEAVER, INC.
104 6022 REMOVING CONC (CURB AND GUTTER) LF 413.000 $4.000 $8.000 $6.688 $3.450 $12.210
110 6001 EXCAVATION (ROADWAY) CY 16,419.000 $15.000 $11.240 $7.073 $12.000 $17.590
132 6005 EMBANKMENT (FINAL)(ORD COMP)(TY C) CY 6,923.000 $15.000 $8.060 $10.390 $4.350 $5.100
150 6002 BLADING HR 40.000 $150.000 $92.110 $116.523 $237.150 $33.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 63,880.000 $1.000 $0.900 $0.867 $0.300 $2.570
164 6026 CELL FBR MLCH SEED(PERM)(URBAN)(SANDY) AC 13.200 $1,500.000 $1,279.210 $1,241.418 $2,100.450 $1,863.400
164 6030 CELL FBR MLCH SEED(TEMP)(WARM) AC 3.300 $500.000 $1,078.760 $1,046.892 $3,113.600 $532.400
164 6032 CELL FBR MLCH SEED(TEMP)(COOL) AC 3.300 $500.000 $1,078.760 $1,046.892 $3,113.600 $532.400
168 6001 VEGETATIVE WATERING MG 1,610.000 $20.000 $20.180 $23.394 $23.800 $13.200
247 6057 FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS) CY 10,144.000 $60.000 $55.740 $52.337 $65.250 $59.970
310 6009 PRIME COAT (MC-30) GAL 6,513.000 $4.000 $3.340 $3.581 $2.950 $3.720
316 6249 AGGR(TY-PE GR-4 SAC-B) CY 385.000 $90.000 $69.410 $93.174 $149.350 $163.750
316 6400 ASPH (AC-15P OR AC-10-2TR OR CRS-2P) GAL 16,903.000 $2.500 $2.600 $2.513 $3.550 $2.660
341 6010 D-GR HMA TY-B PG70-22 TON 6,693.000 $62.000 $61.760 $64.938 $65.450 $95.770
341 6042 D-GR HMA TY-D SAC-B PG70-22 TON 4,127.000 $62.000 $62.640 $69.919 $70.400 $97.110
351 6008 FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") SY 500.000 $90.000 $67.150 $106.567 $67.400 $88.410
400 6005 CEM STABIL BKFL CY 135.000 $150.000 $136.910 $115.300 $155.150 $198.000
403 6001 TEMPORARY SPL SHORING SF 2,070.000 $30.000 $23.620 $12.600 $5.450 $24.200
432 6002 RIPRAP (CONC)(5 IN) CY 268.700 $450.000 $516.880 $492.200 $506.000 $555.500
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 51.000 $500.000 $551.900 $481.500 $472.000 $503.800
450 6006 RAIL (TY T223) LF 63.000 $185.000 $118.870 $143.100 $180.000 $104.500
451 6007 RETROFIT RAIL (TY T223) LF 66.000 $165.000 $197.410 $271.800 $275.000 $126.500
460 6002 CMP (GAL STL 18 IN) LF 23.000 $60.000 $49.880 $60.480 $87.550 $55.000
462 6045 CONC BOX CULV (3 FT X 2 FT)(EXTEND) LF 67.000 $300.000 $477.610 $322.580 $743.000 $748.000
462 6148 CONC BOX CULV (10 FT X 13 FT) (EXTEND) LF 7.000 $1,000.000 $2,122.710 $1,516.500 $2,776.000 $1,314.500
462 6149 CONC BOX CULV (10 FT X 12 FT) (EXTEND) LF 28.000 $1,000.000 $2,122.710 $1,976.810 $1,867.000 $1,375.000
464 6017 RC PIPE (CL IV)(18 IN) LF 158.000 $60.000 $47.180 $73.940 $112.900 $88.000
466 6162 WINGWALL (FW - S) (HW=15 FT) EA 1.000 $30,000.000 $48,716.120 $37,211.000 $43,350.000 $52,800.000
466 6163 WINGWALL (FW - S) (HW=16 FT) EA 1.000 $32,000.000 $50,653.090 $40,837.000 $51,100.000 $52,800.000
467 6111 SET (TY I)(S=3 FT)(HW= 4 FT)(3:1)(C) EA 2.000 $6,000.000 $5,895.820 $3,957.700 $5,570.000 $7,150.000
467 6112 SET (TY I)(S=3 FT)(HW= 4 FT)(4:1)(C) EA 5.000 $6,000.000 $5,121.030 $4,320.000 $5,400.000 $8,085.000
467 6348 SET (TY II) (18 IN) (CMP) (6: 1) (P) EA 6.000 $1,000.000 $1,305.460 $861.150 $1,100.000 $968.000
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 10.000 $1,000.000 $1,528.350 $1,222.810 $765.000 $968.000
467 6380 SET (TY II) (24 IN) (CMP) (6: 1) (P) EA 2.000 $1,200.000 $1,804.300 $1,136.760 $1,500.000 $7,150.000
480 6001 CLEAN EXIST CULVERTS EA 4.000 $1,000.000 $1,087.890 $1,070.000 $1,363.750 $1,650.000
496 6016 REMOV STR (PIPE) EA 1.000 $800.000 $374.660 $588.500 $457.200 $1,650.000
500 6001 MOBILIZATION LS 1.000 $250,000.000 $187,858.010 $306,591.648 $192,682.790 $233,506.550
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 10.000 $2,500.000 $2,599.830 $9,379.586 $5,137.300 $893.070
506 6001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 104.000 $25.000 $26.000 $25.235 $59.550 $52.800
506 6011 ROCK FILTER DAMS (REMOVE) LF 104.000 $8.000 $6.370 $6.180 $16.350 $41.800
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 3,821.000 $2.500 $2.390 $2.318 $5.350 $2.480
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 3,821.000 $0.750 $0.270 $0.258 $1.400 $2.480
512 6005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) LF 540.000 $50.000 $21.810 $15.783 $23.800 $58.260
512 6029 PORT CTB (MOVE)(F-SHAPE)(TY 1) LF 480.000 $10.000 $12.520 $9.363 $15.150 $18.620
512 6053 PORT CTB (REMOVE)(F-SHAPE)(TY 1) LF 540.000 $15.000 $19.530 $12.840 $15.600 $27.130
529 6008 CONC CURB & GUTTER (TY II) LF 412.000 $22.000 $27.380 $21.400 $28.900 $35.200
530 6002 INTERSECTIONS (ACP) SY 2,205.000 $40.000 $30.800 $49.937 $76.650 $38.500
530 6004 DRIVEWAYS (CONC) SY 102.000 $70.000 $66.280 $64.200 $83.800 $33.000
530 6005 DRIVEWAYS (ACP) SY 5,013.000 $40.000 $30.800 $24.771 $30.300 $41.800
530 6008 TURNOUTS (ACP) SY 137.000 $50.000 $122.690 $24.771 $66.150 $60.500
531 6010 CURB RAMPS (TY 7) EA 2.000 $2,500.000 $1,363.840 $19.260 $1,537.450 $2,750.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 512.500 $20.000 $19.640 $19.055 $19.650 $18.430
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $1,600.000 $1,909.240 $1,792.586 $1,377.900 $1,320.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 420.000 $1.500 $1.590 $1.545 $1.600 $1.380
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 4.000 $150.000 $132.670 $128.750 $132.600 $121.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 6.000 $2,200.000 $2,458.090 $2,385.480 $2,456.900 $2,007.500
545 6001 CRASH CUSH ATTEN (INSTL) EA 2.000 $12,000.000 $8,098.130 $8,085.500 $1,135.400 $9,350.000
545 6003 CRASH CUSH ATTEN (MOVE & RESET) EA 2.000 $850.000 $1,443.440 $1,030.000 $540.550 $1,650.000
545 6005 CRASH CUSH ATTEN (REMOVE) EA 2.000 $500.000 $551.900 $669.500 $274.150 $550.000
560 6003 MAILBOX INSTALL-M (TWG-POST) TY 1 EA 3.000 $400.000 $371.470 $360.500 $406.300 $467.500
560 6007 MAILBOX INSTALL-S (WC-POST) TY 3 EA 15.000 $125.000 $159.200 $154.500 $189.900 $159.500
560 6008 MAILBOX INSTALL-D (WC-POST) TY 3 EA 1.000 $175.000 $185.740 $180.250 $219.600 $192.500
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 20.000 $400.000 $480.850 $466.642 $493.300 $385.000
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 2.000 $500.000 $515.760 $500.529 $580.300 $467.500
644 6027 IN SM RD SN SUP&AM TYS80(1)SA(P) EA 1.000 $500.000 $771.870 $749.068 $663.050 $495.000
644 6031 IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT) EA 6.000 $600.000 $737.380 $715.593 $758.500 $660.000
644 6034 IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT) EA 1.000 $800.000 $716.410 $695.250 $864.600 $907.500
644 6070 RELOCATE SM RD SN SUP&AM TY S80 EA 3.000 $300.000 $482.920 $468.650 $440.250 $302.500
644 6076 REMOVE SM RD SN SUP&AM EA 31.000 $60.000 $79.600 $77.250 $68.950 $49.500
658 6048 INSTL OM ASSM (OM-2Z)(FLX)GND EA 12.000 $40.000 $55.900 $54.250 $55.850 $29.700
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 13.000 $30.000 $20.920 $20.301 $20.900 $27.500
662 6063 WK ZN PAV MRK REMOV (W)4"(SLD) LF 36,532.000 $0.500 $0.500 $0.484 $0.550 $0.520
662 6075 WK ZN PAV MRK REMOV (W)24"(SLD) LF 480.000 $8.000 $6.370 $6.180 $10.500 $6.600
662 6095 WK ZN PAV MRK REMOV (Y)4"(SLD) LF 36,532.000 $0.500 $0.500 $0.484 $0.550 $0.520
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 920.000 $1.200 $1.680 $1.430 $1.250 $0.720
666 6041 REFL PAV MRK TY I (W)12"(SLD)(090MIL) LF 136.000 $1.500 $6.370 $6.180 $6.600 $6.600
666 6137 REFL PAV MRK TY I (Y)8"(SLD)(090MIL) LF 150.000 $1.000 $0.740 $0.721 $0.650 $0.770
666 6299 RE PM W/RET REQ TY I (W)4"(BRK)(090MIL) LF 40.000 $0.350 $0.380 $0.371 $0.400 $0.400
666 6302 RE PM W/RET REQ TY I (W)4"(SLD)(090MIL) LF 17,106.000 $0.350 $0.300 $0.288 $0.400 $0.310
666 6311 RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL) LF 3,970.000 $0.350 $0.340 $0.330 $0.400 $0.350
666 6314 RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL) LF 16,656.000 $0.350 $0.300 $0.288 $0.400 $0.310
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 34.000 $10.000 $12.740 $12.360 $15.900 $13.200
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 5.000 $300.000 $212.270 $206.000 $302.350 $220.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 1.000 $300.000 $318.410 $309.000 $397.800 $330.000
672 6009 REFL PAV MRKR TY II-A-A EA 417.000 $3.500 $4.250 $4.120 $6.150 $4.400
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 18,266.000 $0.250 $0.500 $0.484 $1.050 $0.520
752 6003 TREE TRIMMING / BRUSH REMOVAL MI 0.460 $20,000.000 $16,012.800 $34,093.000 $13,385.750 $36,410.000
752 6008 TREE REMOVAL (24" - 30" DIA) EA 19.000 $1,500.000 $3,170.010 $447.020 $3,076.450 $477.400
752 6010 TREE REMOVAL (36" - 42" DIA) EA 2.000 $4,000.000 $4,125.220 $5,807.140 $4,031.200 $6,201.800
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $10,000.000 $8,171.270 $8,560.000 $5,766.250 $16,500.000
Totals: $3,203,871.95 $3,015,734.97 $3,058,796.04 $3,315,452.71 $3,812,200.47