DENTON FM 407 (1568-02-014)

Items: 96

County: DENTON
Length: N/A
Highway: FM 407
District: DALLAS
Control Number: 1568-02-014
DBE Goal: N/A
Project: F 2023(563)
Guaranty: N/A
Time: 203 WORKING DAYS
Engineer's Estimate: $8,979,831.49
Date: 03/07/2023 (3 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
AMANDA MILLER
CHRISTOPHER ROCHA
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$8,979,831.49
$8,970,766.90
Over/Under Est: -0.1% -$9,064.59
Over/Under Est: 0.88% $79,357.41
Amt Left: 0.99% $88,422.00
Over/Under Est: 11.13% $999,299.23
Amt Left: 11.24% $1,008,363.82
Delta: -10.15% -$919,941.82
$9,997,936.34
Over/Under Est: 11.34% $1,018,104.85
Amt Left: 11.45% $1,027,169.44
Delta: -0.19% -$18,805.62
$12,199,404.18
Over/Under Est: 35.85% $3,219,572.69
Amt Left: 35.99% $3,228,637.28
Delta: -22.02% -$2,201,467.84
Subcontractor Percentage Amount
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. 17.97% $1,740,386.23
JR WEST TEXAS CONCRETE LLC 17.78% $1,721,984.82
TEXOP CONSTRUCTION 1.11% $107,502.99
TRP CONSTRUCTION GROUP, LLC 1.06% $102,660.51
MARCOMS CONSTRUCTION LLC 0.64% $61,983.71
FORTSON CONTRACTING, INC. 0.30% $29,054.86
DALLAS LITE AND BARRICADE, INC. 0.29% $28,086.37
WEST TEXAS ROCK RESOURCES, LLC 0.04% $3,873.98
Total: 39.19% $3,795,533.47

Bid Items & Bid Tabulations

96 Total 0 of 96
DENTON  |  FM 407  |  DALLAS  |  1568-02-014  |  03/07/2023  |  $8,979,831.49  |  F 2023(563)  |  REHAB EXIST ROADWAY  |  203 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
EUROVIA ATLANTIC COAST LLC
TEXAS MATERIALS GROUP, INC.
ED BELL CONSTRUCTION COMPANY
JAGOE-PUBLIC COMPANY
ALTUS CONSTRUCTION LLC
PREPARING ROW
STA 318.000 $1,200.000 $400.000 $1,900.000 $750.000 $250.000 $3,375.810
REMOVING CONC (RIPRAP)
SY 35.000 $12.000 $35.000 $82.000 $52.500 $140.000 $11.250
REMOVING CONC (DRIVEWAYS)
SY 1,902.000 $17.680 $20.000 $14.000 $21.000 $11.500 $16.880
REMOV STAB BASE AND ASPH PAV (0"-12")
SY 16,694.000 $14.000 $13.000 $3.500 $8.400 $15.000 $13.500
EXCAVATION (ROADWAY)
CY 28,165.540 $11.500 $28.000 $7.500 $13.650 $35.000 $12.380
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 16,103.925 $15.420 $41.000 $9.000 $21.000 $17.000 $16.880
BACKFILL (TY A OR B)
STA 318.000 $220.000 $400.000 $160.000 $157.500 $260.000 $196.920
BLADING
STA 318.000 $223.000 $145.000 $95.000 $1,500.000 $100.000 $196.920
COMPOST MANUF TOPSOIL (4")
SY 205,015.000 $1.200 $0.940 $1.050 $0.940 $1.750 $1.130
BLOCK SODDING
SY 15,000.000 $4.360 $4.580 $6.000 $4.580 $6.000 $5.630
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 190,015.000 $0.200 $0.150 $0.150 $0.150 $1.400 $1.130
DRILL SEED (TEMP)(WARM OR COOL)
SY 95,007.000 $0.180 $0.100 $0.150 $0.100 $1.250 $1.130
VEGETATIVE WATERING
MG 45,747.000 $2.500 $0.250 $0.010 $2.100 $1.000 $28.130
FLEXIBLE PAVEMENT STRUCTURE REPAIR(12")
SY 800.000 $150.000 $120.000 $150.000 $157.500 $110.000 $112.530
PLANE ASPH CONC PAV(0" TO 2")
SY 77,733.000 $2.050 $1.500 $2.020 $3.150 $2.000 $3.380
TRENCH EXCAVATION PROTECTION
LF 211.000 $2.500 $10.000 $10.000 $20.000 $13.750 $11.250
TEMPORARY SPL SHORING
SF 2,833.000 $31.800 $23.000 $40.000 $75.000 $24.250 $94.610
RIPRAP (MOW STRIP)(4 IN)
CY 41.000 $500.000 $650.000 $650.000 $840.000 $1,000.000 $478.240
RIPRAP (STONE COMMON)(GROUT)(18 IN)
CY 319.000 $205.000 $339.000 $325.000 $435.000 $380.000 $281.320
CONC BOX CULV (5 FT X 4 FT)(EXTEND)
LF 51.000 $540.000 $1,140.000 $1,240.000 $650.000 $850.000 $1,350.320
CONC BOX CULV (5 FT X 5 FT)(EXTEND)
LF 22.000 $750.000 $1,295.000 $1,395.000 $660.000 $1,100.000 $1,350.320
CONC BOX CULV (6 FT X 4 FT)(EXTEND)
LF 60.000 $720.000 $1,275.000 $1,375.000 $710.000 $950.000 $1,350.320
CONC BOX CULV (8 FT X 4 FT)(EXTEND)
LF 43.000 $780.000 $1,500.000 $1,650.000 $805.000 $1,300.000 $1,350.320
CONC BOX CULV (8 FT X 5 FT)(EXTEND)
LF 78.000 $1,100.000 $1,630.000 $1,690.000 $760.000 $1,300.000 $1,687.900
RC PIPE (CL III)(18 IN)
LF 2,142.000 $65.000 $55.000 $60.000 $75.000 $135.000 $61.410
RC PIPE (CL III)(24 IN)
LF 698.000 $86.000 $75.000 $85.000 $95.000 $155.000 $94.210
RC PIPE (CL III)(30 IN)
LF 80.000 $120.000 $108.000 $122.000 $140.000 $180.000 $135.790
RC PIPE (CL III)(36 IN)
LF 179.000 $154.800 $158.000 $175.000 $250.000 $320.000 $191.060
RC PIPE (CL III)(42 IN)
LF 89.000 $200.000 $227.000 $250.000 $500.000 $380.000 $251.100
HEADWALL (CH - PW - 0) (DIA= 24 IN)
EA 2.000 $15,400.000 $6,000.000 $6,500.000 $1,000.000 $9,000.000 $13,503.230
HEADWALL (CH - PW - 0) (DIA= 36 IN)
EA 4.000 $8,500.000 $9,000.000 $9,000.000 $12,000.000 $9,000.000 $16,879.030
HEADWALL (CH - PW - 0) (DIA= 42 IN)
EA 4.000 $7,450.000 $11,250.000 $12,000.000 $15,000.000 $15,000.000 $16,879.030
HEADWALL (CH - PW - S) (DIA= 42 IN)
EA 2.000 $10,000.000 $15,000.000 $15,000.000 $20,000.000 $26,000.000 $22,505.380
WINGWALL (PW - 2) (HW=6 FT)
EA 8.000 $17,500.000 $21,125.000 $21,125.000 $22,000.000 $25,000.000 $28,131.720
WINGWALL (PW - 2) (HW=7 FT)
EA 4.000 $19,820.000 $31,500.000 $31,500.000 $28,000.000 $35,000.000 $33,758.070
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 111.000 $816.500 $1,230.000 $1,300.000 $1,000.000 $2,000.000 $1,010.210
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 30.000 $1,400.000 $1,400.000 $1,600.000 $1,700.000 $2,800.000 $1,683.680
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 4.000 $3,200.000 $4,100.000 $4,400.000 $4,300.000 $4,700.000 $4,607.980
SET (TY II) (36 IN) (RCP) (3: 1) (C)
EA 4.000 $2,746.000 $2,400.000 $2,500.000 $2,900.000 $4,600.000 $4,099.920
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 4.000 $5,300.000 $4,600.000 $5,000.000 $7,500.000 $6,900.000 $8,050.170
CLEAN EXIST CULVERTS
EA 14.000 $2,050.000 $2,000.000 $2,100.000 $2,500.000 $3,100.000 $2,250.540
REMOV STR (WINGWALL)
EA 12.000 $1,800.000 $800.000 $800.000 $2,500.000 $1,100.000 $2,250.540
REMOV STR (HEADWALL)
EA 2.000 $1,250.000 $1,000.000 $1,000.000 $1,500.000 $1,400.000 $2,250.540
REMOV STR (PIPE)
LF 68.000 $23.900 $20.000 $20.000 $50.000 $31.750 $28.130
REMOV STR (SMALL)
EA 76.000 $370.000 $600.000 $600.000 $1,150.000 $670.000 $2,813.170
REMOVING ROCK RIPRAP
LF 320.000 $52.500 $70.870 $75.000 $20.000 $18.500 $135.030
MOBILIZATION
LS 1.000 $850,000.000 $625,000.000 $900,000.000 $994,000.000 $790,000.000 $1,181,532.420
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $14,000.000 $22,000.000 $12,000.000 $52,500.000 $30,000.000 $16,879.030
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 2,509.000 $32.000 $36.160 $50.000 $37.280 $40.250 $30.400
ROCK FILTER DAMS (REMOVE)
LF 2,509.000 $12.000 $11.150 $15.000 $13.650 $12.500 $10.010
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 399.000 $23.000 $38.970 $30.000 $27.830 $20.000 $24.040
CONSTRUCTION EXITS (REMOVE)
SY 399.000 $9.600 $10.720 $10.000 $10.500 $5.000 $7.580
TEMP SEDMT CONT FENCE (INSTALL)
LF 5,504.000 $3.020 $3.280 $3.500 $2.730 $3.600 $3.070
TEMP SEDMT CONT FENCE (REMOVE)
LF 5,504.000 $0.720 $0.770 $0.100 $0.630 $0.850 $0.730
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 4,682.000 $5.200 $4.880 $5.000 $4.410 $5.400 $4.560
BIODEG EROSN CONT LOGS (REMOVE)
LF 4,682.000 $1.090 $0.770 $1.000 $0.890 $0.850 $1.360
DRIVEWAYS (ACP)
SY 8,505.000 $52.000 $44.650 $59.680 $51.000 $45.000 $47.040
DRIVEWAYS (CONC) (HES)
SY 1,542.000 $150.000 $126.000 $115.000 $135.000 $120.000 $79.430
RUMBLE STRIPS (SHOULDER)
LF 45,616.000 $0.200 $0.260 $0.220 $0.250 $0.250 $0.060
RUMBLE STRIPS (CENTERLINE)
LF 17,924.000 $0.200 $0.260 $0.220 $0.250 $0.250 $0.070
MTL W-BEAM GD FEN (STEEL POST)
LF 802.000 $30.000 $26.000 $39.000 $27.300 $29.000 $35.450
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,200.000 $2,625.000 $3,350.000 $2,756.250 $2,900.000 $3,319.540
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 30.000 $320.000 $320.000 $285.000 $299.250 $360.000 $356.710
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 1.000 $753.000 $720.000 $725.000 $761.250 $800.000 $872.080
GROUND BOX TY BATTERY (162915)W/APRON
EA 1.000 $2,275.000 $2,500.000 $4,000.000 $3,000.000 $2,800.000 $11,252.690
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 77.000 $750.000 $585.000 $617.000 $647.850 $650.000 $786.560
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 21.000 $30.000 $25.000 $26.000 $26.250 $27.750 $24.760
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 56.000 $90.000 $68.000 $45.000 $47.250 $44.500 $90.020
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 52,240.000 $0.950 $1.100 $0.010 $1.000 $2.800 $2.250
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 180.000 $1.110 $1.050 $2.000 $2.100 $1.200 $2.250
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 465.000 $7.570 $7.900 $5.690 $7.350 $8.800 $7.880
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 2.000 $154.000 $154.000 $110.000 $160.650 $170.000 $172.170
REFL PAV MRK TY I(W)(DBL ARROW)(100MIL)
EA 2.000 $190.000 $220.000 $160.000 $315.000 $240.000 $337.580
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 1.000 $174.000 $184.000 $118.000 $196.350 $200.000 $210.430
PAVEMENT SEALER 4"
LF 2,972.000 $0.190 $0.130 $0.190 $0.370 $0.140 $0.390
PAVEMENT SEALER 8"
LF 180.000 $0.300 $0.260 $0.280 $1.050 $0.300 $1.130
PAVEMENT SEALER 24"
LF 283.000 $0.900 $1.500 $0.750 $3.150 $1.700 $3.380
PAVEMENT SEALER (ARROW)
EA 2.000 $30.000 $29.000 $19.000 $42.000 $32.250 $45.010
PAVEMENT SEALER (WORD)
EA 1.000 $33.000 $35.000 $19.000 $54.600 $38.750 $58.510
PAVEMENT SEALER (DBL ARROW)
EA 2.000 $21.000 $43.000 $22.000 $115.500 $47.750 $123.780
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 66,458.000 $0.470 $0.500 $0.430 $0.460 $0.550 $0.500
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 4,472.000 $0.560 $0.590 $0.460 $0.770 $0.650 $0.820
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 44,911.000 $0.480 $0.500 $0.430 $0.460 $0.550 $0.500
REFL PAV MRKR TY II-A-A
EA 842.000 $5.200 $5.200 $3.400 $4.690 $5.800 $5.030
REFL PAV MRKR TY II-C-C
EA 10.000 $0.400 $5.350 $4.000 $9.940 $5.900 $10.660
PAV SURF PREP FOR MRK (4")
LF 2,972.000 $0.100 $0.020 $0.140 $0.600 $0.020 $0.640
PAV SURF PREP FOR MRK (8")
LF 180.000 $0.200 $0.070 $0.250 $2.100 $0.080 $2.250
PAV SURF PREP FOR MRK (24")
LF 318.000 $0.700 $0.560 $0.500 $6.300 $0.600 $6.750
RELOCT RDSD FLSH BCN AM (SOLAR PWRD)
EA 1.000 $3,500.000 $4,500.000 $8,000.000 $8,000.000 $5,000.000 $11,252.690
FULL - WIDTH MOWING
CYC 3.000 $2,630.000 $5,500.000 $3,500.000 $6,000.000 $11,000.000 $4,501.080
SP MIXES SP-B SAC-B PG64-22
TON 13,992.000 $117.900 $109.500 $112.000 $115.000 $102.000 $126.590
SP MIXES SP-C SAC-B PG64-22
TON 11,660.000 $150.000 $110.500 $130.000 $117.000 $105.000 $124.340
TACK COAT
GAL 14,311.000 $3.560 $3.250 $4.000 $3.000 $4.500 $0.280
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $6,883.230 $20,000.000 $9,500.000 $25,000.000 $30,000.000 $5,626.340
TMA (STATIONARY)
DAY 248.000 $97.430 $330.000 $1,300.000 $100.000 $250.000 $168.790
TMA (MOBILE OPERATION)
HR 160.000 $63.970 $100.000 $150.000 $100.000 $40.000 $112.530
Totals: $8,979,831.494 $8,970,766.905 $9,059,188.905 $9,979,130.726 $9,997,936.345 $12,199,404.189