Bid Cobra

DENTON IH 35 (0195-03-095)

Items: 31

County: DENTON
Length: N/A
Highway: IH 35
District: DALLAS
Control Number: 0195-03-095
DBE Goal: N/A
Project: C 195-3-95
Guaranty: N/A
Time: 92 WORKING DAYS
Engineer's Estimate: $1,493,562.55
Date: 10/01/2020 (5 years ago)
Contract Number: N/A
Type: FULL DEPTH CONCRETE REPAIRS AND PAVEMENT MARKINGS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$1,493,562.55
$1,113,467.90
Over/Under Est: -25.45% -$380,094.65
Over/Under Est: -20.06% -$299,616.65
Amt Left: 7.23% $80,478.00
$1,419,854.45
Over/Under Est: -4.94% -$73,708.10
Amt Left: 27.52% $306,386.55
Delta: -18.92% -$225,908.55
Over/Under Est: -4% -$59,701.75
Amt Left: 28.77% $320,392.90
Delta: -0.99% -$14,006.35
Over/Under Est: 12.12% $180,968.05
Amt Left: 50.39% $561,062.70
Delta: -16.78% -$240,669.80
$2,042,664.06
Over/Under Est: 36.76% $549,101.51
Amt Left: 83.45% $929,196.16
Delta: -21.98% -$368,133.46
$2,692,658.94
Over/Under Est: 80.28% $1,199,096.39
Amt Left: 141.83% $1,579,191.04
Delta: -31.82% -$649,994.88

Bid Items & Bid Tabulations

31 Total 0 of 31
DENTON  |  IH 35  |  DALLAS  |  0195-03-095  |  10/01/2020  |  $1,493,562.55  |  C 195-3-95  |  FULL DEPTH CONC REPAIRS AND PAVMT MR...  |  92 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
O. TREVINO CONSTRUCTION, LLC
SILVER CREEK CONSTRUCTION, INC.
DBI SERVICES, LLC
D&S CONCRETE CONTRACTORS LLC
ADVANCE CONTRACTING GROUP
J.D. ABRAMS, L.P.
JAGOE-PUBLIC COMPANY
FULL - DEPTH REPAIR CRCP (13")
SY 2,078.000 $290.000 $187.000 $210.000 $300.000 $260.000 $340.000 $415.000 $546.000
FULL - DEPTH REPAIR CPCD (8")
SY 308.000 $245.000 $189.000 $255.000 $195.000 $250.000 $190.000 $300.000 $401.000
FULL - DEPTH REPAIR CPCD (10")
SY 758.000 $245.000 $220.000 $255.000 $210.000 $255.000 $222.000 $320.000 $362.000
FULL - DEPTH REPAIR CPCD (15")
SY 1,204.000 $285.000 $199.000 $209.000 $315.000 $265.000 $460.000 $445.000 $634.000
CLEANING AND SEALING EXISTING JOINTS
LF 1,000.000 $4.350 $17.000 $4.000 $15.000 $10.000 $45.000 $45.000 $36.850
MOBILIZATION
LS 1.000 $137,283.900 $110,000.000 $119,000.000 $100,000.000 $140,000.000 $30,000.000 $58,000.000 $250,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $10,000.000 $10,250.000 $10,000.000 $5,300.000 $13,000.000 $8,000.000 $25,000.000 $5,500.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 800.000 $3.600 $6.000 $3.000 $5.000 $5.000 $7.000 $6.000 $6.260
BIODEG EROSN CONT LOGS (REMOVE)
LF 800.000 $1.050 $1.100 $1.000 $2.000 $1.000 $2.000 $1.100 $3.690
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 246.000 $1.650 $2.250 $1.000 $1.000 $2.000 $2.000 $2.000 $0.960
REFL PAV MRKR TY I-C
EA 2.000 $5.650 $10.500 $4.000 $13.000 $4.000 $11.000 $10.500 $10.530
REFL PAV MRKR TY II-C-R
EA 42.000 $5.650 $10.500 $4.000 $13.000 $4.000 $12.000 $10.500 $10.530
ELIM EXT PAV MRK & MRKS (4")
LF 7,112.000 $1.050 $0.700 $0.400 $0.750 $0.650 $1.000 $0.630 $0.630
ELIM EXT PAV MRK & MRKS (8")
LF 40.000 $1.950 $1.300 $0.750 $1.500 $1.000 $1.500 $1.260 $1.260
ELIM EXT PAV MRK & MRKS (12")
LF 280.000 $3.200 $2.300 $1.500 $3.000 $2.500 $2.300 $2.260 $2.260
ELIM EXT PAV MRK & MRKS (24")
LF 36.000 $3.300 $4.500 $3.500 $6.000 $5.000 $4.600 $4.550 $4.530
PAV SURF PREP FOR MRK (4")
LF 7,112.000 $0.300 $0.200 $0.100 $0.150 $0.250 $1.000 $0.160 $0.160
PAV SURF PREP FOR MRK (8")
LF 40.000 $0.750 $0.300 $0.150 $0.250 $0.350 $0.600 $0.270 $0.260
PAV SURF PREP FOR MRK (12")
LF 280.000 $1.000 $1.050 $0.400 $1.000 $0.500 $1.200 $1.050 $1.050
PAV SURF PREP FOR MRK (24")
LF 36.000 $1.450 $1.600 $1.250 $1.500 $2.000 $2.000 $1.580 $1.580
PORTABLE CHANGEABLE MESSAGE SIGN
EA 3.000 $11,500.000 $11,500.000 $5,000.000 $2,000.000 $4,000.000 $2,000.000 $5,000.000 $9,500.000
MULTIPOLYMER PAV MRK (W)(4")(SLD)
LF 3,261.000 $2.300 $1.000 $0.650 $1.150 $5.500 $1.000 $0.900 $0.890
MULTIPOLYMER PAV MRK (W)(4")(BRK)
LF 590.000 $2.750 $1.100 $0.650 $1.350 $5.500 $1.100 $1.050 $1.050
MULTIPOLYMER PAV MRK (W)(8")(SLD)
LF 40.000 $3.250 $2.150 $1.250 $2.700 $1.500 $3.000 $2.100 $2.110
MULTIPOLYMER PAV MRK (W)(12")(SLD)
LF 280.000 $4.750 $8.000 $4.000 $10.000 $3.350 $10.000 $7.880 $7.900
MULTIPOLYMER PAV MRK (W)(24")(SLD)
LF 36.000 $6.250 $14.250 $8.000 $15.000 $7.000 $15.000 $14.200 $14.210
MULTIPOLYMER PAV MRK (Y)(4")(SLD)
LF 3,261.000 $1.150 $1.000 $0.750 $1.000 $5.500 $1.000 $0.900 $0.890
MULTIYPOLYMER PAV MRK (W) (ARROW)
EA 6.000 $168.000 $341.000 $2.000 $325.000 $175.000 $400.000 $352.000 $0.340
MULTIPOLYMER PAV MRK (W) (WORD)
EA 6.000 $197.000 $415.000 $194.000 $395.000 $200.000 $500.000 $415.000 $415.910
TMA (STATIONARY)
DAY 92.000 $260.000 $175.000 $300.000 $200.000 $200.000 $250.000 $400.000 $270.990
TMA (MOBILE OPERATION)
HR 40.000 $110.000 $65.000 $75.000 $55.000 $80.000 $90.000 $60.000 $45.870
Totals: $1,493,562.550 $1,113,467.900 $1,193,945.900 $1,419,854.450 $1,433,860.800 $1,674,530.600 $2,042,664.060 $2,692,658.940