PREPARING ROW
|
AC
|
6.280
|
$600.000
|
$173.400
|
$170.000
|
$400.000
|
|
|
PREP ROW (TREE) (18"-36" DIA.)
|
EA
|
4.000
|
$3,000.000
|
$881.300
|
$2,100.000
|
$3,000.000
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
33.000
|
$10.000
|
$48.130
|
$64.500
|
$70.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY A)
|
CY
|
3,054.000
|
$25.000
|
$48.440
|
$67.000
|
$51.270
|
|
|
BACKFILL (TY A)
|
STA
|
273.110
|
$200.000
|
$292.350
|
$205.000
|
$275.000
|
|
|
BLADING
|
HR
|
51.000
|
$350.000
|
$182.340
|
$260.000
|
$415.000
|
|
|
DRILL SEEDING (PERM) (RURAL) (CLAY)
|
AC
|
1.460
|
$440.000
|
$1,823.200
|
$1,800.000
|
$2,000.000
|
|
|
DRILL SEEDING (TEMP)(WARM OR COOL)
|
AC
|
7.620
|
$330.000
|
$593.600
|
$600.000
|
$625.000
|
|
|
EMULS ASPH (EROSN CONT)(MULTI)
|
GAL
|
3,592.000
|
$4.000
|
$3.350
|
$4.450
|
$4.150
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
3,887.000
|
$5.000
|
$1.860
|
$2.000
|
$2.550
|
|
|
PLANE ASPH CONC PAV (2")
|
SY
|
2,293.000
|
$2.500
|
$1.630
|
$2.300
|
$4.340
|
|
|
PLANE ASPH CONC PAV (2 1/2")
|
SY
|
71,565.000
|
$2.500
|
$1.940
|
$2.300
|
$1.550
|
|
|
PLANE ASPH CONC PAV (2.5" TO 4.5")
|
SY
|
4,312.000
|
$10.000
|
$4.140
|
$5.450
|
$4.750
|
|
|
CLEANING AND SEALING JOINTS (CL 3)
|
LF
|
312.000
|
$60.000
|
$22.260
|
$27.000
|
$34.000
|
|
|
CONC BOX CULV (5 FT X 2 FT)(EXTEND)
|
LF
|
8.000
|
$2,000.000
|
$1,916.190
|
$1,900.000
|
$1,945.000
|
|
|
CONC BOX CULV (5 FT X 1.5 FT) (EXTEND)
|
LF
|
6.000
|
$2,000.000
|
$1,642.450
|
$1,600.000
|
$1,665.000
|
|
|
CONC BOX CULV (6 FT X 2.5 FT) (EXTEND)
|
LF
|
12.000
|
$2,000.000
|
$2,025.690
|
$2,000.000
|
$2,055.000
|
|
|
CONC BOX CULV (4 FT X 1.5 FT)(EXTEND)
|
LF
|
4.000
|
$1,500.000
|
$1,423.460
|
$1,400.000
|
$1,445.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
30.000
|
$200.000
|
$109.500
|
$105.000
|
$110.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
1,733.000
|
$150.000
|
$153.300
|
$150.000
|
$155.000
|
|
|
SET (TY I)(S= 4 FT)(HW= 3 FT)(4:1) (C)
|
EA
|
2.000
|
$7,000.000
|
$7,664.760
|
$7,500.000
|
$8,315.000
|
|
|
SET (TY I)(S= 5 FT)(HW= 3 FT)(4:1) (C)
|
EA
|
3.000
|
$7,000.000
|
$14,234.550
|
$14,000.000
|
$14,975.000
|
|
|
SET (TY I)(S= 5 FT)(HW= 3 FT)(6:1) (C)
|
EA
|
3.000
|
$7,000.000
|
$16,424.480
|
$16,000.000
|
$17,195.000
|
|
|
SET (TY I)(S= 6 FT)(HW= 4 FT)(4:1) (C)
|
EA
|
6.000
|
$12,000.000
|
$14,234.560
|
$14,000.000
|
$14,975.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
8.000
|
$800.000
|
$3,284.900
|
$3,200.000
|
$3,800.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
110.000
|
$3,000.000
|
$4,379.860
|
$4,300.000
|
$5,000.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
20.000
|
$1,500.000
|
$1,094.970
|
$1,100.000
|
$1,110.000
|
|
|
REMOV STR (PIPE)
|
LF
|
882.000
|
$50.000
|
$21.900
|
$21.500
|
$25.000
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
28.000
|
$370.000
|
$93.070
|
$91.000
|
$95.000
|
|
|
REMOV STR (CATTLE GUARD)
|
EA
|
1.000
|
$1,000.000
|
$2,275.320
|
$1,600.000
|
$5,800.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$405,000.000
|
$350,000.000
|
$570,000.000
|
$645,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
6.000
|
$15,000.000
|
$16,000.000
|
$14,000.000
|
$34,000.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
1,200.000
|
$5.500
|
$3.710
|
$3.750
|
$8.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
1,200.000
|
$2.000
|
$0.900
|
$0.910
|
$2.250
|
|
|
DRIVEWAYS (ACP)
|
SY
|
1,781.000
|
$50.000
|
$41.430
|
$85.500
|
$26.000
|
|
|
DRIVEWAYS (BASE)
|
SY
|
1,737.000
|
$42.000
|
$28.850
|
$29.000
|
$19.000
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
46,335.000
|
$0.170
|
$0.150
|
$0.150
|
$0.250
|
|
|
RUMBLE STRIPS (CENTERLINE)
|
LF
|
23,092.000
|
$0.500
|
$0.250
|
$0.200
|
$0.300
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
475.000
|
$30.000
|
$37.100
|
$37.500
|
$43.500
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$2,400.000
|
$2,628.800
|
$2,700.000
|
$4,165.000
|
|
|
MTL BEAM GD FEN TRANS (T101)
|
EA
|
4.000
|
$1,700.000
|
$2,093.500
|
$2,100.000
|
$2,055.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
725.000
|
$5.000
|
$5.300
|
$5.350
|
$3.350
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
4.000
|
$500.000
|
$424.000
|
$430.000
|
$335.000
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$400.000
|
$371.000
|
$375.000
|
$335.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
8.000
|
$3,200.000
|
$3,789.500
|
$3,800.000
|
$3,950.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
4.000
|
$380.000
|
$371.000
|
$375.000
|
$335.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
2.000
|
$2,000.000
|
$3,127.000
|
$3,200.000
|
$2,775.000
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(W)(TL3)
|
EA
|
2.000
|
$50,000.000
|
$52,682.000
|
$58,000.000
|
$61,075.000
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 2
|
EA
|
20.000
|
$250.000
|
$238.500
|
$240.000
|
$340.000
|
|
|
MAILBOX INSTALL-D (TWG-POST) TY 2
|
EA
|
8.000
|
$250.000
|
$308.460
|
$310.000
|
$395.000
|
|
|
MAILBOX INSTALL-M (TWG-POST) TY 2
|
EA
|
2.000
|
$500.000
|
$413.400
|
$420.000
|
$585.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
23.000
|
$800.000
|
$733.520
|
$740.000
|
$1,030.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
6.000
|
$900.000
|
$966.720
|
$975.000
|
$1,240.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
2.000
|
$1,000.000
|
$1,272.000
|
$1,300.000
|
$1,445.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
19.000
|
$130.000
|
$159.000
|
$105.000
|
$115.000
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
86.000
|
$20.000
|
$21.200
|
$27.000
|
$17.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
18.000
|
$43.000
|
$48.760
|
$49.500
|
$40.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
|
EA
|
45.000
|
$100.000
|
$131.440
|
$135.000
|
$160.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND
|
EA
|
41.000
|
$100.000
|
$131.440
|
$135.000
|
$160.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
743.000
|
$2.000
|
$1.190
|
$1.050
|
$1.200
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
2,968.000
|
$0.750
|
$1.190
|
$1.050
|
$1.250
|
|
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
|
LF
|
25.000
|
$17.000
|
$31.800
|
$32.000
|
$33.300
|
|
REFL PAV MRKR TY I-C
|
EA
|
18.000
|
$4.500
|
$10.600
|
$10.500
|
$11.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
792.000
|
$5.000
|
$5.300
|
$5.350
|
$5.550
|
|
|
D-GR HMA TY-B PG64-28
|
TON
|
10,434.000
|
$95.000
|
$107.800
|
$105.000
|
$130.000
|
|
|
SP MIXES SP-D SAC-A PG70-28
|
TON
|
15,092.000
|
$114.000
|
$114.920
|
$105.400
|
$130.000
|
|
|
TACK COAT
|
GAL
|
17,903.000
|
$3.000
|
$4.740
|
$7.850
|
$4.600
|
|
|
UNDERSEAL COURSE
|
GAL
|
18,971.000
|
$3.000
|
$2.960
|
$4.700
|
$3.200
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$15,000.000
|
$8,630.680
|
$8,000.000
|
$21,000.000
|
|
|
HPPM W/RET REQ TY I(W)4"(BRK)(090MIL)
|
LF
|
579.000
|
$0.500
|
$1.060
|
$1.050
|
$1.100
|
|
|
HPPM W/RET REQ TY I(W)4"(SLD)(090MIL)
|
LF
|
54,583.000
|
$0.500
|
$0.490
|
$0.490
|
$0.500
|
|
|
HPPM W/RET REQ TY I(Y)4"(BRK)(090MIL)
|
LF
|
6,221.000
|
$0.500
|
$0.520
|
$0.520
|
$0.550
|
|
|
HPPM W/RET REQ TY I(Y)4"(SLD)(090MIL)
|
LF
|
28,156.000
|
$0.500
|
$0.490
|
$0.490
|
$0.500
|
|
|
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
|
LF
|
80.000
|
$35.000
|
$31.800
|
$32.000
|
$33.300
|
|
|
TMA (STATIONARY)
|
DAY
|
90.000
|
$300.000
|
$366.690
|
$270.000
|
$530.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
70.000
|
$90.000
|
$97.970
|
$96.500
|
$95.000
|
|
Totals: |
$5,165,348.450
|
$5,447,354.404
|
$5,710,149.030
|
$6,467,743.600
|