Show Job Controls
Bid Cobra

DAWSON SH 349 (0380-06-017)

Items: 158

County: DAWSON
Length: N/A
Highway: SH 349
District: LUBBOCK
Control Number: 0380-06-017
DBE Goal: N/A
Project: STP 2017(394)
Guaranty: N/A
Time: 323 WORKING DAYS
Engineer's Estimate: $21,571,623.45
Date: 02/02/2017 (9 years ago)
Contract Number: N/A
Type: GRADE,BASE,ACP,STR,BR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$21,571,623.45
$17,078,039.55
Over/Under Est: -20.83% -$4,493,583.90
$18,269,500.00
Over/Under Est: -15.31% -$3,302,123.45
Amt Left: 6.98% $1,191,460.45
Over/Under Est: -14.15% -$3,051,670.52
Amt Left: 8.44% $1,441,913.38
Delta: -1.37% -$250,452.93
$18,632,987.39
Over/Under Est: -13.62% -$2,938,636.06
Amt Left: 9.1% $1,554,947.84
Delta: -0.61% -$113,034.46
$18,899,668.00
Over/Under Est: -12.39% -$2,671,955.45
Amt Left: 10.67% $1,821,628.45
Delta: -1.43% -$266,680.61
$20,054,768.11
Over/Under Est: -7.03% -$1,516,855.34
Amt Left: 17.43% $2,976,728.56
Delta: -6.11% -$1,155,100.11
Over/Under Est: 4.85% $1,045,520.05
Amt Left: 32.43% $5,539,103.95
Delta: -12.78% -$2,562,375.39

Bid Items & Bid Tabulations

158 Total 0 of 158
DAWSON  |  SH 349  |  LUBBOCK  |  0380-06-017  |  02/02/2017  |  $21,571,623.45  |  STP 2017(394)  |  GRADE,BASE,ACP,STR,BR  |  323 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
REECE ALBERT, INC.
WEBBER, LLC
ALLEN BUTLER CONSTRUCTION, INC.
FNF CONSTRUCTION, INC.
DUININCK, INC.
GILVIN-TERRILL, LTD.
PRICE CONSTRUCTION, LTD.
PREPARING ROW
STA 143.000 $2,000.000 $468.420 $8,590.000 $45.130 $500.000 $965.000 $315.000 $232.190
PREP ROW (TREE)(GREATER THAN 24" DIA)
EA 4.000 $2,000.000 $727.300 $930.000 $1,484.070 $1,500.000 $2,100.000 $600.000 $1,137.590
REMOVING CONC (MEDIANS)
SY 289.000 $10.000 $7.310 $15.000 $32.850 $36.000 $15.500 $30.000 $34.730
REMOVING CONC (DRIVEWAYS)
SY 448.000 $10.000 $4.710 $19.000 $21.300 $45.000 $13.000 $30.000 $22.400
REMOVING CONC (CURB AND GUTTER)
LF 1,756.000 $10.000 $3.360 $7.250 $9.150 $12.000 $3.150 $4.000 $5.830
REMOV STAB BASE AND ASPH PAV (0"-12")
SY 28,445.000 $10.000 $4.090 $5.250 $6.200 $6.000 $6.100 $5.000 $5.110
EXCAVATION (ROADWAY)
CY 44,319.900 $10.000 $9.010 $10.000 $3.570 $4.000 $7.050 $3.950 $3.780
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 100,671.600 $15.000 $17.190 $5.000 $15.230 $21.850 $27.000 $16.000 $9.170
COMPOST MANUF TOPSOIL (4")
SY 158,223.000 $2.500 $2.230 $1.650 $1.620 $2.050 $1.150 $1.500 $2.620
SPOT SODDING
SY 140.000 $10.000 $18.250 $19.000 $9.320 $16.000 $13.500 $16.000 $112.820
DRILL SEEDING (PERM) (RURAL) (SANDY)
AC 32.690 $600.000 $676.070 $600.000 $553.470 $600.000 $755.000 $600.000 $611.940
DRILL SEEDING (TEMP)(WARM OR COOL)
AC 32.690 $500.000 $560.040 $500.000 $669.990 $500.000 $855.000 $500.000 $506.910
VEGETATIVE WATERING
MG 2,568.000 $25.000 $24.910 $24.000 $55.130 $23.000 $24.500 $21.500 $34.850
SOIL RETENTION BLANKETS (CL 1) (TY D)
SY 18,627.000 $2.000 $1.190 $1.050 $1.170 $1.250 $1.000 $1.500 $1.080
SOIL RETENTION BLANKETS (CL 2) (TY H)
SY 7,771.000 $4.000 $5.410 $4.650 $5.240 $5.000 $4.100 $5.000 $4.890
PLANT MATERIAL (30 GAL) (TREE)
EA 396.000 $200.000 $348.030 $440.000 $506.860 $500.000 $505.000 $450.000 $315.000
VEGETATIVE WATERING
MG 950.000 $20.000 $58.010 $90.000 $55.130 $87.000 $89.500 $85.200 $64.800
PROOF ROLLING
HR 100.000 $200.000 $61.820 $60.000 $95.540 $75.000 $145.000 $85.000 $120.810
FL BS (CMP IN PLC)(TY A GR 4) (6")
SY 104,540.000 $12.000 $7.080 $6.500 $8.010 $7.000 $9.100 $9.000 $7.910
PRIME COAT (MC-30)
GAL 20,908.000 $4.000 $3.630 $3.000 $3.990 $5.000 $3.550 $3.500 $4.340
EMULS ASPH (EROSN CONT)(CSS-1H)
GAL 18,998.000 $4.000 $2.220 $2.250 $4.420 $2.500 $2.750 $3.000 $2.430
FOG SEAL (CSS-1H)
GAL 6,170.000 $4.000 $2.980 $2.250 $4.500 $2.500 $2.750 $3.000 $2.510
AGGR(TY-PB GR-4 SAC-B)
CY 1,246.000 $200.000 $114.630 $96.000 $214.930 $175.000 $140.000 $100.000 $216.760
ASPH (MC-800)
GAL 54,942.000 $4.000 $3.250 $3.050 $3.210 $4.000 $3.650 $3.500 $3.670
D-GR HMA TY-B PG70-28
TON 35,479.000 $110.000 $96.980 $85.000 $93.090 $77.000 $86.500 $100.000 $120.000
STONE-MTRX-ASPH SMA-D SAC-B PG70-28
TON 12,135.000 $140.000 $130.060 $125.000 $120.610 $110.000 $130.000 $120.000 $130.000
CEM STABIL BKFL
CY 961.800 $200.000 $213.300 $189.000 $150.270 $185.000 $250.000 $250.000 $250.650
FOUNDATON LOADTEST(D4945)(DRILLD SHAFT)
EA 1.000 $50,000.000 $36,286.270 $55,000.000 $16,312.840 $38,000.000 $32,500.000 $32,000.000 $32,844.000
DRILL SHAFT (18 IN)
LF 120.000 $100.000 $69.700 $53.500 $111.990 $67.000 $68.500 $100.000 $69.300
DRILL SHAFT (36 IN)
LF 823.000 $300.000 $220.510 $191.000 $254.640 $233.000 $210.000 $250.000 $212.100
DRILL SHAFT (42 IN)
LF 747.000 $400.000 $258.430 $249.000 $245.010 $312.000 $280.000 $400.000 $280.350
DRILL SHAFT (SIGN MTS) (12 IN)
LF 16.000 $150.000 $133.410 $130.000 $151.480 $158.000 $105.000 $200.000 $120.750
DRILL SHAFT (SIGN MTS) (24 IN)
LF 83.000 $180.000 $174.010 $170.000 $198.080 $187.000 $130.000 $300.000 $157.500
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 260.000 $200.000 $191.410 $205.000 $192.260 $247.000 $170.000 $275.000 $173.250
DRILL SHAFT (TRF SIG POLE) (36 IN)
LF 39.000 $300.000 $290.010 $318.000 $291.300 $374.000 $260.000 $350.000 $262.500
CL C CONC (ABUT)(HPC)
CY 200.400 $2,000.000 $1,090.790 $863.000 $1,316.220 $955.000 $935.000 $1,000.000 $945.000
CL C CONC (CAP)(HPC)
CY 66.700 $1,500.000 $1,376.500 $1,170.000 $1,419.950 $1,170.000 $935.000 $1,000.000 $945.000
CL C CONC (COLUMN)(HPC)
CY 19.700 $1,500.000 $1,887.040 $1,940.000 $2,778.730 $1,478.000 $1,400.000 $1,000.000 $1,365.000
REINF CONC SLAB (HPC)
SF 33,828.000 $20.000 $23.980 $17.700 $22.200 $22.600 $17.500 $25.000 $17.640
APPROACH SLAB (HPC)
CY 406.800 $800.000 $672.630 $392.000 $514.750 $688.000 $520.000 $1,000.000 $525.000
RETAINING WALL (MSE)
SF 62,820.000 $43.000 $31.810 $54.250 $30.920 $36.500 $30.500 $43.000 $84.370
PRESTR CONC GIRDER (TX54)
LF 3,205.570 $225.000 $158.400 $135.000 $155.390 $208.000 $160.000 $300.000 $162.750
PRESTR CONC GIRDER (TX62)
LF 1,035.200 $250.000 $200.470 $149.000 $169.450 $221.000 $185.000 $300.000 $185.850
SILICONE RESIN PAINT FINISH
SF 2,268.000 $15.000 $1.350 $1.000 $7.860 $3.600 $0.280 $1.000 $0.960
RIPRAP (CONC)(4 IN)
CY 440.300 $500.000 $516.490 $487.000 $272.040 $577.000 $520.000 $750.000 $498.750
RIPRAP (CONC)(5 IN)
CY 12.800 $600.000 $691.370 $548.000 $611.570 $1,231.000 $470.000 $750.000 $525.000
CLEANING AND SEALING JOINTS (CL 7)
LF 7.000 $100.000 $100.920 $500.000 $1,165.200 $60.000 $41.500 $35.000 $315.000
STR STEEL (MISC NON - BRIDGE)
LB 3,507.000 $10.000 $2.670 $7.000 $1.740 $2.000 $8.300 $4.000 $7.880
RAIL (TY SSTR)(HPC)
LF 4,150.200 $75.000 $56.670 $49.000 $56.920 $84.000 $75.000 $65.000 $71.660
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
LF 142.000 $100.000 $100.900 $75.000 $86.170 $120.000 $75.000 $75.000 $75.600
ARMOR JOINT (SEALED)
LF 161.000 $200.000 $91.110 $95.000 $79.870 $143.000 $60.500 $75.000 $60.900
CONC BOX CULV (4 FT X 2 FT)
LF 420.000 $400.000 $291.410 $218.000 $407.820 $432.000 $365.000 $250.000 $472.500
CONC BOX CULV (4 FT X 2 FT)(EXTEND)
LF 32.000 $400.000 $1,327.220 $350.000 $466.080 $753.000 $415.000 $1,000.000 $420.000
RC PIPE (CL III)(24 IN)
LF 300.000 $200.000 $75.950 $85.250 $105.310 $101.000 $83.500 $70.000 $84.000
RC PIPE (CL III)(36 IN)
LF 98.000 $250.000 $121.990 $119.000 $202.760 $188.000 $165.000 $150.000 $168.000
HEADWALL (CH - PW - 0) (DIA= 36 IN)
EA 2.000 $7,000.000 $9,816.760 $10,000.000 $9,904.230 $13,000.000 $8,800.000 $14,000.000 $8,925.000
WINGWALL (PW - 1) (HW=3 FT)
EA 1.000 $7,000.000 $15,455.130 $6,340.000 $10,486.830 $10,000.000 $9,400.000 $16,000.000 $9,450.000
WINGWALL (PW - 1) (HW=4 FT)
EA 1.000 $7,000.000 $16,238.790 $10,000.000 $16,312.840 $14,000.000 $14,500.000 $15,000.000 $14,700.000
SET (TY I)(S= 4 FT)(HW= 3 FT)(4:1) (C)
EA 11.000 $5,000.000 $6,350.260 $8,040.000 $5,826.010 $5,400.000 $5,200.000 $5,400.000 $5,250.000
SET (TY I)(S= 4 FT)(HW= 3 FT)(6:1) (C)
EA 1.000 $5,000.000 $14,983.960 $11,207.200 $12,234.630 $12,500.000 $11,000.000 $5,450.000 $11,025.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 10.000 $2,000.000 $1,142.830 $1,470.000 $1,398.240 $2,225.000 $1,200.000 $1,500.000 $1,260.000
REMOV STR (PIPE)
LF 53.000 $50.000 $18.120 $35.000 $70.080 $50.000 $260.000 $100.000 $262.500
MOBILIZATION
LS 1.000 $1,963,000.000 $714,073.280 $1,800,000.000 $1,314,135.120 $1,856,816.970 $1,800,000.000 $1,960,000.000 $2,233,989.490
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 19.000 $15,000.000 $4,870.530 $2,600.000 $73,040.430 $10,000.000 $9,000.000 $11,000.000 $16,424.900
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 810.000 $20.000 $23.140 $24.400 $14.760 $29.000 $26.000 $25.000 $38.170
ROCK FILTER DAMS (REMOVE)
LF 810.000 $10.000 $5.230 $8.600 $14.220 $10.000 $9.350 $9.000 $9.050
CONSTRUCTION EXITS (INSTALL) (TY 3)
SY 444.000 $20.000 $11.000 $22.000 $9.900 $26.000 $26.000 $22.000 $29.140
CONSTRUCTION EXITS (REMOVE)
SY 444.000 $8.000 $4.660 $7.350 $3.600 $9.000 $10.500 $8.000 $7.740
SANDBAGS FOR EROSION CONTROL (12")
LF 4,320.000 $10.000 $8.910 $13.500 $17.480 $16.000 $13.500 $14.000 $28.230
TEMP SEDMT CONT FENCE (INSTALL)
LF 15,280.000 $5.000 $1.990 $1.550 $2.330 $2.000 $4.000 $2.000 $4.480
TEMP SEDMT CONT FENCE (REMOVE)
LF 15,280.000 $3.000 $0.970 $0.650 $1.170 $0.750 $1.050 $0.700 $0.690
CONSTRUCTING DETOURS
SY 7,486.000 $50.000 $34.740 $50.000 $41.860 $42.000 $50.000 $63.000 $79.200
INTERSECTIONS (ACP)
SY 987.000 $40.000 $62.890 $30.250 $82.410 $53.000 $90.500 $70.000 $152.790
DRIVEWAYS (CONC)
SY 486.000 $70.000 $83.520 $94.000 $95.430 $113.000 $83.500 $75.000 $117.180
DRIVEWAYS (ACP)
SY 479.000 $40.000 $51.290 $15.200 $108.550 $36.000 $75.500 $70.000 $84.700
RUMBLE STRIPS (SHOULDER)
LF 32,740.000 $0.250 $0.140 $0.150 $0.340 $0.130 $0.320 $0.290 $0.130
RUMBLE STRIPS (CENTERLINE)
LF 16,370.000 $0.250 $0.240 $0.150 $0.450 $0.170 $0.400 $0.390 $0.220
MTL W-BEAM GD FEN (STEEL POST)
LF 450.000 $30.000 $22.040 $19.000 $22.140 $25.000 $24.500 $19.000 $24.940
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,000.000 $1,612.470 $1,390.000 $1,619.630 $2,200.000 $2,200.000 $1,390.000 $2,205.000
SHORT RADIUS
LF 100.000 $50.000 $30.160 $26.000 $30.300 $31.000 $31.000 $26.000 $31.500
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,200.000 $1,015.040 $875.000 $1,019.560 $1,400.000 $1,400.000 $875.000 $1,417.500
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 100.000 $30.000 $20.880 $18.000 $20.970 $25.000 $24.500 $18.000 $24.940
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $3,000.000 $2,262.090 $1,950.000 $2,272.150 $2,600.000 $2,600.000 $1,950.000 $2,625.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 2.000 $300.000 $145.010 $125.000 $145.650 $180.000 $235.000 $200.000 $183.750
MAILBOX INSTALL-M (TWG-POST) TY 2
EA 2.000 $400.000 $493.020 $425.000 $495.210 $360.000 $390.000 $300.000 $367.500
IN RD IL (TY SA) 50T-10 (400W EQ) LED
EA 26.000 $3,500.000 $4,060.160 $4,000.000 $4,078.210 $3,100.000 $3,600.000 $4,250.000 $3,675.000
CONDT (PVC) (SCH 40) (2")
LF 6,715.000 $5.000 $8.700 $3.500 $8.740 $7.000 $7.800 $4.000 $7.880
CONDT (PVC) (SCH 80) (2") (BORE)
LF 390.000 $20.000 $46.400 $20.000 $46.610 $19.000 $41.500 $30.000 $42.000
CONDT (PVC) (SCH 80) (4")
LF 300.000 $6.000 $11.600 $20.000 $11.650 $17.000 $10.500 $20.000 $10.500
CONDT (PVC) (SCH 80) (4") (BORE)
LF 75.000 $25.000 $58.000 $32.000 $58.260 $33.000 $52.000 $50.000 $52.500
ELEC CONDR (NO.8) BARE
LF 7,105.000 $1.200 $1.040 $0.800 $1.050 $1.750 $0.940 $1.350 $0.950
ELEC CONDR (NO.8) INSULATED
LF 14,210.000 $1.200 $1.160 $0.900 $1.170 $1.750 $1.050 $1.500 $1.050
ELEC CONDR (NO.6) BARE
LF 255.000 $1.500 $1.160 $1.500 $1.170 $1.750 $1.050 $1.750 $1.050
ELEC CONDR (NO.2) INSULATED
LF 45.000 $3.000 $2.260 $5.000 $2.270 $2.250 $2.050 $6.000 $2.050
GROUND BOX TY A (122311)W/APRON
EA 7.000 $900.000 $690.230 $925.000 $693.300 $675.000 $620.000 $1,250.000 $624.750
GROUND BOX TY D (162922)
EA 1.000 $600.000 $759.830 $800.000 $763.210 $850.000 $680.000 $1,000.000 $687.750
GROUND BOX TY D (162922)W/APRON
EA 2.000 $900.000 $759.830 $1,300.000 $763.210 $1,100.000 $680.000 $1,600.000 $687.750
ELC SRV TY A 240/480 060(SS)SS(E)SP(O)
EA 3.000 $3,800.000 $5,800.230 $6,000.000 $5,826.010 $6,700.000 $5,200.000 $6,875.000 $5,250.000
ELC SRV TY D 120/240 070(SS)AL(N)SP(O)
EA 1.000 $3,800.000 $4,060.160 $4,000.000 $4,078.210 $4,200.000 $3,600.000 $5,500.000 $3,675.000
ALUMINUM SIGNS (TY A)
SF 67.500 $25.000 $26.100 $18.000 $20.970 $24.000 $17.000 $20.000 $23.630
ALUMINUM SIGNS (TY G)
SF 870.000 $35.000 $27.840 $32.000 $37.290 $27.000 $23.500 $15.000 $25.200
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 15.000 $600.000 $516.220 $445.000 $518.520 $750.000 $470.000 $400.000 $766.500
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 47.000 $600.000 $301.610 $490.000 $302.950 $850.000 $530.000 $500.000 $840.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 9.000 $800.000 $957.040 $825.000 $961.290 $1,100.000 $780.000 $700.000 $1,076.250
IN SM RD SN SUP&AM TYS80(1)SA(U-2EXT)
EA 1.000 $900.000 $1,044.040 $900.000 $1,048.690 $1,300.000 $885.000 $1,300.000 $1,207.500
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
EA 3.000 $1,000.000 $1,107.850 $955.000 $1,159.380 $1,300.000 $935.000 $900.000 $1,207.500
IN SM RD SN SUP&AM TYS80(1)SA(U-EXAL)
EA 9.000 $1,000.000 $1,096.240 $945.000 $1,101.120 $1,250.000 $845.000 $800.000 $1,191.750
IN BRIDGE MNT CLEARANCE SGN ASSM(TY S)
EA 2.000 $2,000.000 $4,060.170 $2,650.000 $3,087.790 $3,700.000 $2,200.000 $1,500.000 $3,675.000
REMOVE SM RD SN SUP&AM
EA 30.000 $125.000 $98.600 $85.000 $99.040 $110.000 $52.000 $60.000 $105.000
INSTALL LRSS (STRUCT STEEL)
LB 5,438.400 $5.500 $5.800 $5.500 $6.290 $5.500 $7.300 $4.000 $5.250
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND(BR)
EA 17.000 $45.000 $87.000 $75.000 $64.090 $130.000 $130.000 $55.000 $131.250
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 24.000 $45.000 $29.000 $30.000 $25.630 $19.000 $18.000 $22.000 $18.380
INSTL DEL ASSM (D-DW)SZ 1(FLX)GND
EA 18.000 $50.000 $87.000 $100.000 $66.420 $130.000 $130.000 $57.000 $131.250
INSTL OM ASSM (OM-2Z)(FLX)GND(BI)
EA 28.000 $55.000 $87.000 $80.000 $67.580 $130.000 $130.000 $58.000 $131.250
INSTL OM ASSM (OM-3R)(FLX)SRF(BI)
EA 2.000 $75.000 $290.020 $300.000 $110.700 $275.000 $260.000 $336.000 $262.500
REMOVE DELIN & OBJECT MARKER ASSMS
EA 60.000 $30.000 $63.800 $55.000 $4.660 $11.000 $10.500 $13.000 $10.500
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 31,200.000 $0.250 $0.130 $0.100 $0.130 $0.120 $0.110 $0.110 $0.120
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 31,200.000 $0.250 $0.130 $0.100 $0.130 $0.120 $0.110 $0.110 $0.120
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 3,312.000 $2.000 $2.970 $0.400 $6.410 $2.100 $1.050 $1.000 $2.040
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,686.000 $2.000 $2.810 $0.450 $6.260 $2.200 $1.050 $1.000 $2.000
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 126.000 $0.500 $0.360 $0.300 $0.360 $0.350 $0.320 $0.310 $0.330
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,570.000 $1.000 $0.670 $0.600 $0.680 $0.600 $0.600 $0.580 $0.610
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 6,480.000 $0.550 $0.360 $0.300 $0.360 $0.350 $0.320 $0.310 $0.330
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 35,620.000 $0.350 $0.360 $0.300 $0.360 $0.350 $0.320 $0.310 $0.330
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 60,085.000 $0.350 $0.360 $0.300 $0.360 $0.350 $0.320 $0.310 $0.330
PREFAB PAV MRK TY B (W)(4")(SLD)
LF 950.000 $3.000 $5.800 $5.000 $5.830 $6.000 $5.200 $5.000 $5.250
PREFAB PAV MRK TY B (W)(4")(BRK)CNTST
LF 130.000 $5.000 $11.600 $10.000 $11.650 $11.000 $10.500 $10.000 $10.500
PREFAB PAV MRK TY B (Y)(4")(SLD)
LF 1,900.000 $3.000 $5.800 $5.000 $5.830 $5.200 $5.200 $5.000 $5.250
PREFAB PAV MRK TY B (Y)(MED NOSE)
EA 6.000 $800.000 $116.010 $100.000 $116.520 $110.000 $105.000 $100.000 $105.000
PREFAB PAV MRK TY C (W) (12") (LNDP)
LF 251.000 $5.000 $8.700 $7.500 $8.740 $8.000 $7.800 $7.500 $7.880
PREFAB PAV MRK TY C (W) (12") (SLD)
LF 820.000 $5.000 $8.700 $7.500 $8.740 $8.000 $7.800 $7.500 $7.880
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 190.000 $10.000 $17.400 $15.000 $17.480 $16.000 $15.500 $15.000 $15.750
PREFAB PAV MRK TY C (W) (ARROW)
EA 8.000 $300.000 $290.010 $250.000 $291.300 $275.000 $260.000 $250.000 $262.500
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 4.000 $500.000 $406.020 $350.000 $407.820 $375.000 $365.000 $350.000 $367.500
PREFAB PAV MRK TY C (W) (WORD)
EA 8.000 $500.000 $406.020 $350.000 $407.820 $375.000 $365.000 $350.000 $367.500
PREFAB PAV MRK TY C (W) (ISLAND)
EA 1.000 $1,000.000 $290.010 $250.000 $291.300 $275.000 $260.000 $250.000 $262.500
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 7.000 $200.000 $58.000 $50.000 $58.260 $52.000 $52.000 $50.000 $52.500
PREFAB PAV MRK TY C (Y) (MED NOSE)
EA 1.000 $800.000 $116.000 $100.000 $116.520 $110.000 $105.000 $100.000 $105.000
ELIM EXT PAV MRK & MRKS (4")
LF 51,570.000 $1.000 $0.730 $0.650 $0.730 $0.700 $0.660 $0.630 $0.660
ELIM EXT PAV MRK & MRKS (8")
LF 1,330.000 $2.000 $1.460 $1.250 $1.470 $1.300 $1.300 $1.260 $1.320
ELIM EXT PAV MRK & MRKS (24")
LF 300.000 $4.000 $5.800 $5.000 $5.830 $5.100 $5.200 $5.000 $5.250
PAV SURF PREP FOR MRK (6")
LF 2,850.000 $2.000 $0.750 $0.650 $0.760 $0.700 $0.680 $0.650 $0.680
PAV SURF PREP FOR MRK (8")
LF 130.000 $3.000 $0.750 $0.650 $0.760 $0.700 $0.680 $0.650 $0.680
INSTALL HWY TRF SIG (ISOLATED)
EA 1.000 $20,000.000 $30,161.220 $30,000.000 $30,295.270 $19,000.000 $33,000.000 $35,000.000 $27,300.000
VEH SIG SEC (12")LED(GRN)
EA 8.000 $250.000 $290.010 $225.000 $291.300 $210.000 $260.000 $250.000 $262.500
VEH SIG SEC (12")LED(GRN ARW)
EA 1.000 $250.000 $290.010 $225.000 $291.300 $210.000 $260.000 $250.000 $262.500
VEH SIG SEC (12")LED(YEL)
EA 8.000 $250.000 $290.010 $225.000 $291.300 $210.000 $260.000 $250.000 $262.500
VEH SIG SEC (12")LED(RED)
EA 8.000 $250.000 $290.010 $225.000 $291.300 $210.000 $260.000 $250.000 $262.500
BACK PLATE (12")(3 SEC)
EA 7.000 $150.000 $116.000 $100.000 $116.520 $75.000 $105.000 $100.000 $105.000
BACK PLATE (12")(4 SEC)
EA 1.000 $200.000 $129.930 $130.000 $130.510 $90.000 $115.000 $150.000 $117.600
TRF SIG CBL (TY A)(12 AWG)(5 CONDR)
LF 412.000 $3.000 $1.910 $2.750 $1.920 $2.300 $1.700 $3.000 $1.730
TRF SIG CBL (TY A)(12 AWG)(12 CONDR)
LF 300.000 $5.000 $3.020 $5.250 $3.030 $3.100 $2.700 $6.000 $2.730
INS TRF SIG PL AM(S)1 ARM(32')
EA 3.000 $6,500.000 $6,960.280 $8,500.000 $6,991.220 $7,100.000 $6,200.000 $9,000.000 $6,300.000
FULL - WIDTH MOWING
AC 130.760 $200.000 $203.010 $125.000 $203.910 $160.000 $57.000 $30.000 $94.500
LITTER REMOVAL
AC 130.760 $200.000 $197.210 $200.000 $198.080 $110.000 $62.500 $20.000 $84.000
ANTI - GRAFFITI COATNG(PERMNENT-TY III)
SF 50,843.000 $0.750 $0.920 $0.800 $1.250 $1.100 $0.820 $1.000 $0.830
TIP TESTING(DRILL SHAFT)
EA 3.000 $15,000.000 $12,542.430 $20,000.000 $2,660.540 $14,000.000 $11,500.000 $11,000.000 $11,352.600
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $25,000.000 $18,444.740 $5,000.000 $13,402.850 $25,000.000 $12,500.000 $10,000.000 $28,981.500
Totals: $21,571,623.450 $17,078,039.643 $18,269,500.000 $18,519,952.996 $18,632,987.390 $18,899,668.005 $20,054,768.115 $22,617,143.540