DALLAS SL0012 (6396-79-001)

Items: 14

County: DALLAS
Length: N/A
Highway: SL0012
District: DALLAS
Control Number: 6396-79-001
DBE Goal: N/A
Project: RMC - 639679001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $446,176.60
Date: 05/04/2022 (4 years ago)
Contract Number: N/A
Type: MISCELLANEOUS CONCRETE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$446,176.60
$435,646.50
Over/Under Est: -2.36% -$10,530.10
Over/Under Est: 12.53% $55,922.50
Amt Left: 15.25% $66,452.60
$516,243.00
Over/Under Est: 15.7% $70,066.40
Amt Left: 18.5% $80,596.50
Delta: -2.82% -$14,143.90
Over/Under Est: 26.48% $118,157.40
Amt Left: 29.54% $128,687.50
Delta: -9.32% -$48,091.00
Over/Under Est: 37.81% $168,712.75
Amt Left: 41.14% $179,242.85
Delta: -8.96% -$50,555.35
Over/Under Est: 46.69% $208,325.40
Amt Left: 50.24% $218,855.50
Delta: -6.44% -$39,612.65

Bid Items & Bid Tabulations

14 Total 0 of 14
DALLAS  |  SL0012  |  DALLAS  |  6396-79-001  |  05/04/2022  |  $446,176.60  |  RMC - 639679001  |  MISCELLANEOUS CONC REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TALBRAN ENTERPRISES LLC
ROY JORGENSEN ASSOCIATES, INC.
IBCTX, LLC
FNH CONSTRUCTION, LLC
GIBSON & ASSOCIATES, INC.
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
REMOVING CONC (RIPRAP)
CY 76.000 $100.000 $100.000 $125.000 $250.000 $30.000 $615.000 $165.000
REMOVING CONC (CURB AND GUTTER)
LF 1,133.000 $20.000 $30.000 $10.000 $15.000 $20.000 $38.000 $10.000
EMBANKMENT (FINAL) (DENS CONT) (TY C2)
CY 230.330 $20.000 $50.000 $270.000 $100.000 $50.000 $145.000 $150.000
FLOWABLE BACKFILL
CY 166.000 $235.000 $300.000 $210.000 $300.000 $350.000 $480.000 $600.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 351.000 $200.000 $250.000 $200.000 $240.000 $500.000 $240.000 $275.000
RIPRAP (CONC)(4 IN)
CY 76.000 $600.000 $500.000 $450.000 $600.000 $550.000 $1,510.000 $650.000
RIPRAP (CONC)(5 IN)
CY 30.000 $700.000 $500.000 $475.000 $650.000 $650.000 $512.000 $650.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 192.500 $240.000 $200.000 $180.000 $250.000 $185.000 $205.000 $275.000
MOBILIZATION
LS 1.000 $45,000.000 $50,000.000 $46,000.000 $51,600.000 $50,000.000 $9,400.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $7,500.000 $2,000.000 $7,500.000 $6,000.000 $8,500.000 $7,600.000 $16,000.000
CONC CURB & GUTTER (TY II)
LF 1,133.000 $50.000 $30.000 $40.000 $50.000 $55.000 $65.000 $60.000
CONCRETE RAIL REPAIR (MISC)
LF 73.000 $550.000 $500.000 $700.000 $900.000 $350.000 $350.000 $600.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 60.000 $150.000 $50.000 $100.000 $100.000 $100.000 $100.000 $75.000
TMA (STATIONARY)
DAY 80.000 $200.000 $300.000 $750.000 $150.000 $350.000 $260.000 $173.000
Totals: $446,176.600 $435,646.500 $502,099.100 $516,243.000 $564,334.000 $614,889.350 $654,502.000