DALLAS IH0030 (6389-96-001)

Items: 41

County: DALLAS
Length: N/A
Highway: IH0030
District: DALLAS
Control Number: 6389-96-001
DBE Goal: N/A
Project: RMC - 638996001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $681,140.00
Date: 12/01/2021 (4 years ago)
Contract Number: N/A
Type: TRAFFIC CONTROL SERVICES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$681,140.00
$769,375.00
Over/Under Est: 12.95% $88,235.00
Over/Under Est: 18.5% $126,007.00
Amt Left: 4.91% $37,772.00
Over/Under Est: 19.79% $134,820.00
Amt Left: 6.05% $46,585.00
Delta: -1.09% -$8,813.00
Over/Under Est: 103.92% $707,860.00
Amt Left: 80.54% $619,625.00
Delta: -70.23% -$573,040.00

Bid Items & Bid Tabulations

41 Total 0 of 41
DALLAS  |  IH0030  |  DALLAS  |  6389-96-001  |  12/01/2021  |  $681,140.00  |  RMC - 638996001  |  TRAF CONTROL SERVICES  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SELECT MAINTENANCE, L.L.C.
BARRICADES UNLIMITED
STATEWIDE SAFETY SYSTEMS
FC TRAFFIC CONTROL, INC.
MOBILIZATION (CALLOUT)
EA 98.000 $300.000 $100.000 $400.000 $150.000 $3,000.000
MOBILIZATION (EMERGENCY)
EA 72.000 $200.000 $250.000 $1,000.000 $1,000.000 $10,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 21.000 $175.000 $150.000 $167.000 $175.000 $100.000
TMA (STATIONARY)
DAY 345.000 $150.000 $300.000 $1,000.000 $850.000 $250.000
TMA (MOBILE OPERATION)
HR 375.000 $75.000 $175.000 $90.000 $100.000 $50.000
TMA (MOBILE OPERATIONS) (SNOW & ICE)
HR 900.000 $140.000 $115.000 $170.000 $125.000 $75.000
LANE CLOSURE (SETUP AND REMOV)(TY 1)
EA 3.000 $500.000 $775.000 $10.000 $385.000 $100.000
LANE CLOSURE (SETUP AND REMOV)(TY 2)
EA 3.000 $500.000 $725.000 $10.000 $385.000 $100.000
LANE CLOSURE (SETUP AND REMOV)(TY 3)
EA 7.000 $500.000 $575.000 $10.000 $385.000 $100.000
LANE CLOSURE (SETUP AND REMOV)(TY 4)
EA 7.000 $650.000 $675.000 $10.000 $395.000 $100.000
LANE CLOSURE (SETUP AND REMOV)(TY 5)
EA 49.000 $650.000 $525.000 $250.000 $495.000 $100.000
LANE CLOSURE (SETUP AND REMOV)(TY 6)
EA 49.000 $775.000 $650.000 $250.000 $505.000 $100.000
LANE CLOSURE (SETUP AND REMOV)(TY 7)
EA 15.000 $1,000.000 $775.000 $250.000 $695.000 $100.000
LANE CLOSURE (SETUP AND REMOV)(TY 8)
EA 3.000 $1,350.000 $1,200.000 $250.000 $750.000 $100.000
LANE CLOSURE (SETUP AND REMOV)(TY 9)
EA 75.000 $1,000.000 $375.000 $300.000 $475.000 $100.000
LANE CLOSURE (SETUP AND REMOV)(TY 11)
EA 18.000 $1,300.000 $2,000.000 $1,170.000 $750.000 $1,000.000
LANE CLOSURE (SETUP AND REMOV)(TY 12)
EA 9.000 $600.000 $675.000 $250.000 $385.000 $100.000
LANE CLOSURE (SETUP AND REMOV)(TY 13)
EA 9.000 $680.000 $775.000 $250.000 $400.000 $100.000
LANE CLOSURE (SETUP AND REMOV)(TY 14)
EA 9.000 $610.000 $625.000 $250.000 $475.000 $100.000
LANE CLOSURE (SETUP AND REMOV)(TY 15)
EA 9.000 $900.000 $725.000 $250.000 $495.000 $100.000
LANE CLOSURE (SETUP AND REMOV)(TY 16)
EA 10.000 $450.000 $425.000 $250.000 $250.000 $100.000
LANE CLOSURE (SETUP AND REMOV)(TY 17)
EA 8.000 $475.000 $425.000 $250.000 $250.000 $125.000
LANE CLOSURE (MAINTENANCE) (TY 1)
HR 6.000 $150.000 $350.000 $10.000 $100.000 $150.000
LANE CLOSURE (MAINTENANCE) (TY 2)
HR 6.000 $200.000 $350.000 $10.000 $100.000 $150.000
LANE CLOSURE (MAINTENANCE) (TY 3)
HR 30.000 $150.000 $300.000 $10.000 $100.000 $150.000
LANE CLOSURE (MAINTENANCE) (TY 4)
HR 3.000 $250.000 $350.000 $10.000 $105.000 $150.000
LANE CLOSURE (MAINTENANCE) (TY 5)
HR 162.000 $225.000 $225.000 $80.000 $125.000 $150.000
LANE CLOSURE (MAINTENANCE) (TY 6)
HR 128.000 $200.000 $250.000 $80.000 $140.000 $150.000
LANE CLOSURE (MAINTENANCE) (TY 7)
HR 56.000 $200.000 $275.000 $80.000 $175.000 $150.000
LANE CLOSURE (MAINTENANCE) (TY 8)
HR 7.000 $250.000 $400.000 $80.000 $180.000 $150.000
LANE CLOSURE (MAINTENANCE) (TY 9)
HR 90.000 $225.000 $250.000 $80.000 $120.000 $150.000
LANE CLOSURE (MAINTENANCE) (TY 11)
HR 310.000 $200.000 $300.000 $80.000 $180.000 $150.000
LANE CLOSURE (MAINTENANCE) (TY 12)
HR 42.000 $130.000 $300.000 $80.000 $100.000 $150.000
LANE CLOSURE (MAINTENANCE) (TY 13)
HR 36.000 $150.000 $350.000 $80.000 $110.000 $150.000
LANE CLOSURE (MAINTENANCE) (TY 14)
HR 27.000 $175.000 $325.000 $10.000 $125.000 $150.000
LANE CLOSURE (MAINTENANCE) (TY 15)
HR 27.000 $150.000 $400.000 $10.000 $125.000 $150.000
LANE CLOSURE (MAINTENANCE) (TY 16)
HR 48.000 $125.000 $200.000 $80.000 $80.000 $150.000
LANE CLOSURE (MAINTENANCE) (TY 17)
HR 36.000 $95.000 $200.000 $80.000 $80.000 $150.000
LANE CLOSURE (SETUP AND REMOV)(TY 22)
HR 7.000 $100.000 $200.000 $10.000 $55.000 $150.000
LANE CLOSURE (SETUP AND REMOV)(TY 23)
HR 7.000 $100.000 $200.000 $10.000 $80.000 $150.000
FURNISH ADDITIONAL FLAGGER
HR 10.000 $100.000 $200.000 $10.000 $55.000 $150.000
Totals: $681,140.000 $769,375.000 $807,147.000 $815,960.000 $1,389,000.000