DALLAS US 175 (0197-02-118)
Items: 23
County: DALLAS
Length: N/A
Highway: US 175
District: DALLAS
Control Number: 0197-02-118
DBE Goal: N/A
Project: NH 2017(729)
Guaranty: N/A
Time: 77 WORKING DAYS
Engineer's Estimate: $2,012,215.30
Date: 02/02/2017 (9 years ago)
Contract Number: N/A
Type: MILL,CONC,REPAIR,OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (9)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,012,215.30 | |||
| $1,511,372.54 |
-24.89%
-$500,842.76
|
|||
| $1,534,830.53 |
-23.72%
-$477,384.77
|
1.55%
$23,457.99
|
||
| $1,643,097.34 |
-18.34%
-$369,117.96
|
8.72%
$131,724.80
|
-7.05%
-$108,266.81
|
|
| $1,684,087.10 |
-16.31%
-$328,128.20
|
11.43%
$172,714.56
|
-2.49%
-$40,989.76
|
|
| $1,843,234.54 |
-8.4%
-$168,980.76
|
21.96%
$331,862.00
|
-9.45%
-$159,147.44
|
|
| $1,852,988.05 |
-7.91%
-$159,227.25
|
22.6%
$341,615.51
|
-0.53%
-$9,753.51
|
|
| $1,906,900.97 |
-5.23%
-$105,314.33
|
26.17%
$395,528.43
|
-2.91%
-$53,912.92
|
|
| $2,062,648.50 |
2.51%
$50,433.20
|
36.48%
$551,275.96
|
-8.17%
-$155,747.53
|
|
| $2,317,171.00 |
15.16%
$304,955.70
|
53.32%
$805,798.46
|
-12.34%
-$254,522.50
|
E
Engineer's Estimate
$2,012,215.30
1
$1,511,372.54
Over/Under Est:
-24.89%
-$500,842.76
$1,534,830.53
Over/Under Est:
-23.72%
-$477,384.77
Amt Left:
1.55%
$23,457.99
$1,643,097.34
Over/Under Est:
-18.34%
-$369,117.96
Amt Left:
8.72%
$131,724.80
Delta:
-7.05%
-$108,266.81
$1,684,087.10
Over/Under Est:
-16.31%
-$328,128.20
Amt Left:
11.43%
$172,714.56
Delta:
-2.49%
-$40,989.76
$1,843,234.54
Over/Under Est:
-8.4%
-$168,980.76
Amt Left:
21.96%
$331,862.00
Delta:
-9.45%
-$159,147.44
$1,852,988.05
Over/Under Est:
-7.91%
-$159,227.25
Amt Left:
22.6%
$341,615.51
Delta:
-0.53%
-$9,753.51
$1,906,900.97
Over/Under Est:
-5.23%
-$105,314.33
Amt Left:
26.17%
$395,528.43
Delta:
-2.91%
-$53,912.92
$2,062,648.50
Over/Under Est:
2.51%
$50,433.20
Amt Left:
36.48%
$551,275.96
Delta:
-8.17%
-$155,747.53
$2,317,171.00
Over/Under Est:
15.16%
$304,955.70
Amt Left:
53.32%
$805,798.46
Delta:
-12.34%
-$254,522.50
Bid Items & Bid Tabulations
23
Total
0 of 23