DALLAS IH 35E (0196-03-289)

Items: 89

County: DALLAS
Length: 3.1940 MILES
Highway: IH 35E
District: DALLAS
Control Number: 0196-03-289
DBE Goal: 7.5%
Project: F 2024(946)
Guaranty: $100,000.00
Time: 267 WORKING DAYS
Engineer's Estimate: $20,026,678.50
Date: 09/06/2024 (1 year ago)
Contract Number: 9243206
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00141252
Project Description: FULL DEPTH CONCRETE REPAIR, MILL, INLAY, BRIDGE REPAIR AND PAVEMENT MARKINGS
Mail/Deliver Bids To: N/A
NATHAN PETTER
DUNG NGUYEN
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$20,026,678.50
$22,250,006.04
Over/Under Est: 11.1% $2,223,327.54
Over/Under Est: 17.25% $3,453,788.63
Amt Left: 5.53% $1,230,461.09
$23,779,129.50
Over/Under Est: 18.74% $3,752,451.00
Amt Left: 6.87% $1,529,123.46
Delta: -1.27% -$298,662.37
Over/Under Est: 22.87% $4,581,100.75
Amt Left: 10.6% $2,357,773.21
Delta: -3.48% -$828,649.75
Subcontractor Percentage Amount
AUSTIN BRIDGE & ROAD SERVICES, LP 29.72% $6,766,574.00
JR WEST TEXAS CONCRETE LLC 7.06% $1,607,402.84
MACIAS SPECIALTY CONTRACTING LLC 4.09% $931,200.80
AXIS CONTRACTING, INC. 3.95% $899,325.95
SOUTHERN CROSS CONTRACTORS, LLC 3.11% $708,076.89
S & S BRIDGE PAINTING, INC. 1.63% $371,114.25
LINEAR TRAFFIC MARKINGS LLC 0.50% $113,838.73
ACT SAW CUTTING & REMOVAL 0.23% $52,365.81
GLOBAL EROSION CONTROL, INC. 0.23% $52,365.81
FC TRAFFIC CONTROL, INC. 0.21% $47,812.27
STOIC CIVIL CONSTRUCTION, INC. 0.19% $43,258.72
SUPERIOR TRAFFIC CONTROL, LLC 0.05% $11,383.87
WEST TEXAS ROCK RESOURCES, LLC 0.02% $4,553.55
Total: 50.99% $11,609,273.49

Bid Items & Bid Tabulations

89 Total 0 of 89
DALLAS  |  IH 35E  |  DALLAS  |  0196-03-289  |  09/06/2024  |  $20,026,678.50  |  F 2024(946)  |  REHAB EXIST ROADWAY  |  267 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GIBSON & ASSOCIATES, INC.
AUSTIN BRIDGE & ROAD SERVICES, LP
FNH CONSTRUCTION, LLC
RAGLE CONSTRUCTION, INC.
REMOV CONC (RIPRAP)
SY 520.000 $20.000 $35.200 $26.990 $100.000 $22.000
REMOV CONC (CURB)
LF 101.000 $30.000 $13.200 $49.510 $100.000 $16.000
REMOV CONC (TRAFFIC BARRIER)
LF 630.000 $20.000 $30.000 $250.000 $150.000 $23.000
EMBANK (FNL)(DC)(TY C2)
CY 384.000 $50.000 $82.500 $58.410 $100.000 $100.000
BLOCK SODDING
SY 1,520.000 $4.500 $6.600 $5.000 $10.000 $14.900
VEGETATIVE WATERING
TGL 227.000 $25.000 $72.600 $60.750 $50.000 $60.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 33,678.000 $145.000 $181.100 $151.340 $185.000 $157.480
TACK COAT
GAL 33,678.000 $6.000 $4.600 $0.250 $6.000 $4.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 950.000 $125.000 $172.500 $145.000 $85.000 $150.000
PLANE ASPH CONC PAV(0" TO 3")
SY 306,153.000 $2.500 $1.840 $1.900 $4.000 $1.670
FULL - DEPTH REPAIR CRCP (8")
CY 968.000 $1,000.000 $1,432.200 $1,302.000 $1,000.000 $1,302.000
FLOWABLE BACKFILL
CY 107.000 $412.000 $590.000 $844.440 $350.000 $357.000
CL C CONC (ABUT)(EXTEND)
CY 8.000 $3,000.000 $5,500.000 $5,500.000 $6,500.000 $2,900.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 1,123.000 $150.000 $91.000 $126.000 $175.000 $100.000
CONC STR REPAIR(DECK REP (FULL DEPTH))
SF 1,265.000 $300.000 $250.000 $250.000 $265.000 $150.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 3,791.000 $240.000 $245.000 $245.000 $265.000 $150.000
RIPRAP (CONC)(4 IN)
CY 560.000 $568.000 $687.500 $897.820 $550.000 $776.000
RIPRAP (MOW STRIP)(4 IN)
CY 976.000 $650.000 $687.500 $765.630 $550.000 $764.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 233.000 $162.000 $200.200 $253.310 $185.000 $215.000
CLEANING AND SEALING EXIST JOINTS (CL3)
LF 32.000 $50.000 $100.000 $100.000 $110.000 $58.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 1,460.000 $25.000 $40.000 $40.000 $80.000 $32.000
STR STEEL (MISC NON-BRIDGE)
LB 219.000 $28.000 $20.000 $5.000 $100.000 $53.200
RETROFIT RAIL (TY SSTR)
LF 2,052.000 $200.000 $159.500 $498.000 $200.000 $238.000
RAISING EXIST STRUCT
LS 1.000 $368,500.000 $250,000.000 $250,000.000 $400,000.000 $373,000.000
ADJUST STL SHOES
EA 53.000 $3,500.000 $5,200.000 $5,200.000 $5,500.000 $15,820.000
MOBILIZATION
LS 1.000 $2,000,000.000 $2,150,000.000 $2,582,851.380 $2,400,000.000 $3,150,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 17.000 $30,000.000 $110,000.000 $160,715.870 $15,000.000 $124,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $24,200.000 $22,000.000 $25,000.000 $16,500.000 $50,000.000
TMA (STATIONARY)
DAY 344.000 $250.000 $300.000 $500.000 $250.000 $400.000
TMA (MOBILE OPERATION)
DAY 45.000 $250.000 $400.000 $900.000 $550.000 $802.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 268.000 $20.000 $22.000 $34.000 $40.000 $34.000
CONSTRUCTION EXITS (REMOVE)
SY 268.000 $8.000 $11.000 $14.000 $20.000 $14.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,000.000 $3.500 $2.610 $3.250 $4.000 $3.250
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,000.000 $1.000 $1.320 $1.050 $2.000 $1.050
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 2,000.000 $4.250 $6.600 $4.750 $18.000 $4.750
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,000.000 $1.250 $2.200 $1.050 $9.000 $1.050
PTB (FUR & INST)(STEEL)
LF 1,516.000 $75.000 $38.000 $95.000 $85.000 $89.000
PTB (REMOVE)(STEEL)
LF 1,516.000 $20.000 $10.000 $25.000 $30.000 $3.700
PTB (MOVE)(F SHAPE)(TY 1) OR (STL)
LF 45,480.000 $15.000 $8.000 $5.130 $20.000 $5.800
PERM CTB (F-SHAPE) (TY 1)
LF 630.000 $235.000 $159.500 $492.000 $250.000 $164.000
CONC CURB (TY II)
LF 101.000 $30.000 $46.200 $45.000 $65.000 $22.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 30,000.000 $0.400 $0.140 $0.220 $0.500 $0.290
MTL W-BEAM GD FEN (TIM POST)
LF 20,136.000 $25.000 $23.820 $23.000 $30.000 $23.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 28.000 $3,000.000 $2,139.500 $2,675.590 $1,850.000 $2,883.510
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 18.000 $1,400.000 $1,648.900 $1,125.000 $1,850.000 $1,125.000
MTL BM GD FEN TRANS (NON - SYM)
EA 1.000 $2,250.000 $984.500 $600.000 $5,000.000 $600.000
REMOVE METAL BEAM GUARD FENCE
LF 19,868.000 $3.500 $2.200 $2.250 $3.000 $2.250
REMOVE TERMINAL ANCHOR SECTION
EA 15.000 $350.000 $220.000 $125.000 $500.000 $125.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 28.000 $245.000 $220.000 $225.000 $500.000 $225.000
RM MTL BM GD FENCE TRANS (TL-2)
EA 1.000 $300.000 $220.000 $225.000 $500.000 $225.000
GUARDRAIL END TREATMENT (INSTALL)
EA 18.000 $3,200.000 $3,382.500 $2,877.500 $3,250.000 $2,877.500
GUARDRAIL END TREATMENT (REMOVE)
EA 18.000 $600.000 $220.000 $250.000 $1,500.000 $250.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 30.000 $1,950.000 $1,182.500 $2,500.000 $6,500.000 $1,235.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $15,000.000 $874.500 $2,500.000 $3,000.000 $825.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $25,000.000 $8,332.500 $15,000.000 $30,000.000 $6,995.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
EA 1.000 $2,800.000 $4,000.000 $4,001.420 $10,000.000 $1,500.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 205.000 $35.000 $38.500 $25.000 $100.000 $25.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 31,386.000 $0.750 $0.610 $0.320 $1.500 $0.320
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 31,386.000 $0.750 $0.610 $0.300 $1.500 $0.300
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 31,386.000 $0.750 $0.610 $0.300 $1.500 $0.300
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 31,378.000 $1.000 $3.000 $0.500 $1.500 $2.000
REFL PAV MRK TY I(W)(ENTR GORE)(100MIL)
EA 7.000 $500.000 $2,750.000 $900.000 $1,500.000 $900.000
REFL PAV MRK TY I(W)(EXIT GORE)(100MIL)
EA 7.000 $500.000 $2,750.000 $1,300.000 $1,500.000 $1,300.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 31,386.000 $0.750 $0.940 $0.620 $1.500 $0.620
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 31,386.000 $0.750 $0.940 $0.590 $1.500 $0.590
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 31,386.000 $0.750 $0.940 $0.590 $1.500 $0.590
REFL PAV MRKR TY II-C-R
EA 3,140.000 $5.000 $8.640 $3.900 $6.000 $3.900
JT CLEANING AND SEALING (EXPANSION JTS)
LF 600.000 $30.000 $50.000 $80.000 $50.000 $26.000
LONGT CRACK CLEANING AND SEALING (CRCP)
LF 100.000 $30.000 $25.000 $19.000 $50.000 $19.000
FIBER REINFORCED POLYMER PATCHING MATLS
LB 1,000.000 $15.000 $13.000 $12.000 $30.000 $11.750
SPOT TREE TRIMMING / BRUSH REMOVAL
LF 30.000 $15.000 $110.000 $76.680 $500.000 $1,000.000
TREE REMOVAL (4" - 12" DIA)
EA 2.000 $500.000 $880.000 $1,150.270 $2,500.000 $1,000.000
DITCH CLEAN / RESHAPING(CU YD IN PLACE)
CY 245.000 $65.000 $66.000 $70.670 $100.000 $40.000
REPLACE RAIL ELEMENT (W-BEAM)
LF 30.000 $15.000 $22.000 $17.000 $500.000 $17.000
REPLACE TIMBER POST W/O CONC FND
EA 10.000 $100.000 $115.500 $25.000 $2,500.000 $25.000
REALIGN POSTS
EA 153.000 $25.000 $71.500 $10.000 $500.000 $10.000
REPAIR (T4 (A))
LF 310.000 $100.000 $320.000 $320.000 $400.000 $493.000
CONCRETE RAIL REPAIR (IN-KIND)
LF 177.000 $200.000 $780.000 $780.000 $800.000 $331.000
CNC CRACK REPAIR (DISCRETE)(GRAVITY)
LF 937.000 $50.000 $43.000 $40.000 $60.000 $46.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 438.000 $35.000 $143.000 $143.000 $200.000 $99.000
CNC CRACK REPAIR (DISCRETE)(SURF SEAL)
LF 9.000 $76.000 $50.000 $50.000 $75.000 $28.000
CNC CRACK REPAIR (FLOOD)(GRAVITY)
SF 279,367.000 $5.000 $2.400 $2.500 $3.500 $2.300
REP STL BRIDGE MEMBER (DIAPHRAGM)
EA 11.000 $3,800.000 $1,500.000 $1,500.000 $5,000.000 $2,500.000
BRIDGE JOINT REPAIR (ARMOR)
LF 2,872.000 $475.000 $925.000 $925.000 $1,000.000 $474.000
REPLACING ELASTOMERIC BEARING PADS
EA 8.000 $12,000.000 $9,500.000 $9,500.000 $11,000.000 $25,000.000
CONCRETE BEAM REPAIR
EA 2.000 $40,000.000 $2,500.000 $2,500.000 $5,000.000 $3,200.000
CONCRETE BEAM REPAIR (CFRP)
EA 43.000 $30,000.000 $4,200.000 $4,200.000 $6,500.000 $2,300.000
STEEL BRIDGE ZONE PAINTING
LS 1.000 $170,000.000 $427,915.000 $372,100.000 $420,000.000 $3,500,000.000
BENT CAP/ABUTMENT CAP CLEANING
EA 11.000 $2,000.000 $1,400.000 $1,000.000 $2,500.000 $1,600.000
Totals: $20,026,678.500 $22,250,006.040 $23,480,467.130 $23,779,129.500 $24,607,779.250