Job Info for 0092-14-108

County: DALLAS Highway: IH 45 Date: 01/05/2024 (10 months ago) Engineer's Estimate: $3,433,160 Control Number: 0092-14-108
Project: C 92-14-108 District: DALLAS Time: 262 WORKING DAYS Type: BRIDGE MAINTENANCE
Bidder's List
Informational:
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,433,160.00
BECK-REIT & SONS, LTD.   $3,175,651.00 1
-7.5% | -$257,509.00
GARRET SHIELDS INFRASTRUCTURE   $3,184,008.00 2
-7.26% | -$249,152.00
0.26% | $8,357.00
IBCTX, LLC   $3,442,616.00 3
0.28% | $9,456.00
8.41% | $266,965.00
8.12% | $258,608.00
FNH CONSTRUCTION, LLC   $3,999,690.50 4
16.5% | $566,530.50
25.95% | $824,039.50
16.18% | $557,074.50
JAY-REESE CONTRACTORS, INC.   $4,491,421.50 5
30.82% | $1,058,261.50
41.43% | $1,315,770.50
12.29% | $491,731.00
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC   $4,992,431.00 6
45.42% | $1,559,271.00
57.21% | $1,816,780.00
11.15% | $501,009.50
Subcontractor Percentage Amount
G J SEEDING, LLC 3.47% $110,195.09
SUPERIOR TRAFFIC CONTROL, LLC 1.28% $40,648.33
Total: 4.75% $150,843.42

Bid Items

Items: 19, 0 filtered
DALLAS IH 45  |  DALLAS  |  0092-14-108  |  01/05/2024  |  $3,433,160  |  C 92-14-108  |  BRIDGE MAINT  |  262 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate BECK-REIT & SONS, LTD. GARRET SHIELDS INFRASTRUCTURE IBCTX, LLC FNH CONSTRUCTION, LLC JAY-REESE CONTRACTORS, INC. BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
100 6002 PREPARING ROW STA 6.000 $5,000.000 $3,300.000 $4,000.000 $50,000.000 $55,000.000 $53,000.000 $5,500.000
110 6002 EXCAVATION (CHANNEL) CY 4,083.000 $18.500 $44.000 $50.000 $55.000 $50.000 $80.000 $50.000
161 6017 COMPOST MANUF TOPSOIL (4") SY 2,355.000 $5.000 $12.000 $5.000 $10.000 $10.000 $10.000 $2.000
162 6002 BLOCK SODDING SY 2,355.000 $6.500 $10.000 $8.000 $6.000 $10.000 $5.000 $10.000
164 6051 DRILL SEED (TEMP)(WARM OR COOL) SY 2,355.000 $2.250 $6.000 $2.000 $1.000 $2.000 $0.500 $1.000
168 6001 VEGETATIVE WATERING MG 438.300 $35.000 $50.000 $70.000 $50.000 $25.000 $60.000 $50.000
432 6031 RIPRAP (STONE PROTECTION)(12 IN) CY 200.000 $205.000 $199.000 $200.000 $190.000 $155.000 $190.000 $300.000
432 6035 RIPRAP (STONE PROTECTION)(24 IN) CY 582.000 $215.000 $199.000 $230.000 $195.000 $185.000 $255.000 $325.000
432 6036 RIPRAP (STONE PROTECTION)(30 IN) CY 11,524.000 $225.000 $199.000 $200.000 $200.000 $230.000 $255.000 $325.000
500 6001 MOBILIZATION LS 1.000 $300,000.000 $355,000.000 $300,000.000 $120,000.000 $300,000.000 $451,000.000 $500,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 17.000 $5,000.000 $1,000.000 $5,000.000 $10,000.000 $8,500.000 $4,000.000 $5,000.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 343.000 $27.500 $50.000 $20.000 $40.000 $40.000 $30.000 $50.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 343.000 $13.750 $10.000 $1.000 $20.000 $20.000 $12.000 $25.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 911.000 $4.000 $5.000 $5.000 $5.000 $4.000 $3.500 $6.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 911.000 $2.000 $1.000 $1.000 $2.000 $2.000 $1.000 $3.000
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 1,881.000 $12.000 $6.000 $5.000 $7.000 $18.000 $4.500 $15.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 1,881.000 $6.000 $1.000 $1.000 $2.000 $9.000 $1.000 $2.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $17,500.000 $14,000.000 $1,000.000 $30,000.000 $16,500.000 $20,000.000 $5,000.000
6185 6002 TMA (STATIONARY) DAY 237.000 $200.000 $1.000 $1.000 $25.000 $250.000 $300.000 $200.000
Totals: $3,433,160.00 $3,175,651.00 $3,184,008.00 $3,442,616.00 $3,999,690.50 $4,491,421.50 $4,992,431.00