Bid Cobra

DALLAS IH 45 (0092-02-141)

Items: 53

County: DALLAS
Length: N/A
Highway: IH 45
District: DALLAS
Control Number: 0092-02-141
DBE Goal: N/A
Project: BR 2023(441)
Guaranty: N/A
Time: 186 WORKING DAYS
Engineer's Estimate: $3,919,617.20
Date: 02/01/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
JUAN PAREDES
AMANDA MCKITTRICK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$3,919,617.20
$4,336,407.90
Over/Under Est: 10.63% $416,790.70
Over/Under Est: 11.61% $455,112.60
Amt Left: 0.88% $38,321.90
Over/Under Est: 14.9% $584,021.67
Amt Left: 3.86% $167,230.97
Delta: -2.95% -$128,909.07
Over/Under Est: 17.03% $667,352.05
Amt Left: 5.78% $250,561.35
Delta: -1.85% -$83,330.38
Subcontractor Percentage Amount
ODUM SERVICES, LLC 10.16% $496,019.12
DALLAS LITE AND BARRICADE, INC. 5.84% $285,113.35
AVILES CONSTRUCTION SERVICE, INC 4.95% $241,662.86
S&S BRIDGE PAINTING 0.64% $31,245.30
STRIPING TECHNOLOGY, L.P. 0.00% $0.00
DELTA STRUCTURAL TECHNOLOGY, LLC 0.00% $0.00
FC TRAFFIC CONTROL, INC. 0.00% $0.00
HOUSTON SAWING & DRILLING 0.00% $0.00
Total: 21.59% $1,054,040.63

Bid Items & Bid Tabulations

53 Total 0 of 53
DALLAS  |  IH 45  |  DALLAS  |  0092-02-141  |  02/01/2023  |  $3,919,617.20  |  BR 2023(441)  |  BRIDGE MAINT  |  186 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STRUCTURAL INTEGRITY GROUP LLC
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
GIBSON & ASSOCIATES, INC.
RAGLE CONSTRUCTION, INC.
REMOVING CONC (MISC)
SY 164.000 $30.000 $60.000 $50.000 $75.000 $19.000
REMOVING CONC (FLUME)
SY 752.000 $18.000 $42.000 $50.000 $155.000 $19.000
CEM STABIL BKFL
CY 7.000 $550.000 $535.000 $250.000 $600.000 $285.000
CL B CONC (FLUME)
CY 111.100 $550.000 $1,400.000 $700.000 $2,550.000 $650.000
SILICONE RESIN PAINT FINISH
SF 3,969.000 $30.000 $8.000 $8.000 $5.230 $4.750
PENETRATING CONCRETE SURFACE TREATMENT
SY 2,044.000 $9.500 $8.000 $9.000 $6.550 $5.950
CONC STR REPAIR(CLEAN & COAT WTH EPOXY)
SF 72.000 $400.000 $125.000 $350.000 $93.500 $125.000
CONC STR REPAIR(RAPID DECK REP(PRT DPT)
SF 1,678.000 $25.000 $150.000 $125.000 $85.000 $150.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 2,520.000 $230.000 $180.000 $200.000 $181.500 $120.000
RIPRAP (MOW STRIP)(4 IN)
CY 576.000 $600.000 $690.000 $650.000 $1,050.000 $590.000
CLEANING AND SEALING JOINTS (CL 7)
LF 1,796.000 $25.000 $45.000 $65.000 $51.000 $23.000
MULTI-LAYER POLYMER OVERLAY
SY 1,814.000 $75.000 $76.000 $65.000 $62.000 $50.000
MOBILIZATION
LS 1.000 $356,328.930 $340,000.000 $350,000.000 $359,000.000 $455,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $7,500.000 $25,000.000 $12,000.000 $11,800.000 $60,000.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 100.000 $6.000 $10.000 $10.000 $15.000 $7.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 100.000 $2.000 $3.000 $2.000 $5.000 $2.000
CONC CURB (TY II)
LF 147.000 $40.000 $60.000 $40.000 $130.000 $30.000
MTL W-BEAM GD FEN (TIM POST)
LF 8,625.000 $26.680 $25.500 $25.000 $21.180 $19.250
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 15.000 $2,200.000 $2,350.000 $2,000.000 $1,952.500 $1,775.000
MTL BEAM GD FEN TRANS (TL2)
EA 16.000 $1,500.000 $1,000.000 $1,500.000 $825.000 $750.000
SHORT RADIUS
LF 725.000 $57.250 $300.000 $200.000 $250.800 $150.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 10.000 $1,300.000 $1,325.000 $1,800.000 $1,100.000 $1,000.000
REMOVE METAL BEAM GUARD FENCE
LF 9,350.000 $2.500 $2.650 $3.500 $2.200 $2.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $250.000 $165.000 $250.000 $137.500 $125.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 6.000 $250.000 $165.000 $250.000 $137.500 $125.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 31.000 $275.000 $165.000 $250.000 $220.000 $125.000
GUARDRAIL END TREATMENT (INSTALL)
EA 27.000 $3,100.000 $3,550.000 $3,000.000 $2,970.000 $2,700.000
GUARDRAIL END TREATMENT (REMOVE)
EA 27.000 $265.000 $230.000 $300.000 $192.500 $175.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 264.000 $5.000 $2.500 $2.200 $10.000 $2.500
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 191.000 $5.000 $2.500 $2.000 $10.000 $2.500
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 128.000 $12.000 $8.000 $10.000 $11.000 $6.000
PAVEMENT SEALER 4"
LF 5,585.000 $0.200 $0.350 $0.500 $1.100 $0.250
PAVEMENT SEALER 6"
LF 630.000 $0.300 $0.450 $0.500 $2.200 $0.330
PAVEMENT SEALER 24"
LF 128.000 $2.000 $0.650 $1.000 $4.400 $0.500
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 2,279.000 $0.750 $1.150 $1.000 $2.200 $0.890
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 630.000 $1.250 $1.300 $1.200 $2.200 $0.990
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 3,306.000 $0.750 $1.150 $1.000 $2.200 $0.890
REFL PAV MRKR TY II-A-A
EA 32.000 $6.000 $8.000 $10.000 $11.000 $6.000
REFL PAV MRKR TY II-C-R
EA 42.000 $6.000 $8.000 $10.000 $11.000 $6.000
ELIM EXT PAV MRK & MRKS (4")
LF 5,585.000 $0.600 $1.300 $1.250 $1.100 $0.980
ELIM EXT PAV MRK & MRKS (6")
LF 630.000 $0.800 $1.500 $1.250 $2.200 $1.160
ELIM EXT PAV MRK & MRKS (24")
LF 128.000 $3.840 $3.250 $3.000 $4.400 $2.450
PAV SURF PREP FOR MRK (4")
LF 5,585.000 $0.250 $0.200 $0.250 $1.100 $0.150
PAV SURF PREP FOR MRK (6")
LF 630.000 $0.300 $0.250 $0.250 $1.100 $0.200
PAV SURF PREP FOR MRK (24")
LF 128.000 $1.000 $0.650 $0.750 $1.100 $0.500
JT / CRCK SEAL (HOT - POURED RUBBER)
LF 774.000 $50.000 $43.000 $10.000 $23.000 $3.500
CONC CRCK REPR(DISCRETE)(ROUT AND SEAL)
LF 185.000 $100.000 $48.000 $10.000 $35.000 $40.000
CARBON FIBER REINF POLYMER PROTECTION
SF 3,227.000 $160.000 $55.000 $60.000 $47.300 $55.000
POLYESTER POLYMER CONC OVERLAY (3/4")
SY 8,290.000 $100.000 $120.000 $165.000 $134.000 $163.500
SPECIAL SURFACE FILLER
GAL 80.200 $300.000 $340.000 $300.000 $412.500 $300.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 6.000 $7,500.000 $20,000.000 $10,000.000 $21,000.000 $20,000.000
TMA (STATIONARY)
DAY 300.000 $250.000 $250.000 $300.000 $300.000 $325.000
TMA (MOBILE OPERATION)
DAY 150.000 $300.000 $250.000 $200.000 $100.000 $550.000
Totals: $3,919,617.200 $4,336,407.900 $4,374,729.800 $4,503,638.870 $4,586,969.250